Districtwide Projects
Jefferson Parish
Note: The estimated completion date is based
on the work order date and the contract
days allowed.
Unavoidable contingencies and unforeseen events
often develop during construction, which may
impact the actual completion date.
LA 45 Drainage Improvements |
H.002267.6 - Asphalt overlay of asphalt pavement
|
Proj. Engr: Zzzz Weber, Alan |
Route: |
LA 45
map
|
Contractor: Barriere Construction Co., LLC |
Miles:
| 1.01 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2012-04-09 |
$363,642 |
Summer of 2012 |
LA 3134 (Intracoastal Canal-La 45) |
H.002953.6 - Asphalt overlay of asphalt pavement
|
Proj. Engr: Zzzz Weber, Alan |
Route: |
LA 3134
map
|
Contractor: Barriere Construction Co., LLC |
Miles:
| 6.70 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2013-11-23 |
$2,967,635 |
Fall of 2014 |
Airline at Clearview Intersection Improv |
H.004424.6-R1 - Asphalt overlay of asphalt pavement
|
Proj. Engr: Zzzz Duplantis, Michael |
Route: |
US 61 LA 3152
map
|
Contractor: Magee Excavation & Development |
Miles:
| 0.72 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2021-07-30 |
$6,283,002 |
Beginning of 2023 |
La302: Barataria Br Tug Hit |
H.009184-R1 - Moveable bridges reconditioned
|
Proj. Engr: Zzzz Guidry, John |
Route: |
LA 302
map
|
Contractor: Boh Bros. Construction Co., Ll |
Miles:
| 0.10 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2011-07-28 |
$1,065,897 |
Fall of 2011 |
US 90z: Westbank Expressway Rehab |
H.010017.6 - Bridges reconditioned
|
Proj. Engr: Hollier, Corbett |
Route: |
I-910
map
|
Contractor: Southern Road & Bridge, LLC |
Miles:
| 5.50 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2021-12-13 |
$4,224,471 |
Beginning of 2024 |
LA 611-1 & La 611-3: Mill & Overlay |
H.010418.6 - Asphalt overlay of asphalt pavement
|
Proj. Engr: Keller, Gerald |
Route: |
LA 611-1
map
|
Contractor: Madden Gulf Coast, LLC |
Miles:
| 2.84 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-07-31 |
$2,722,655 |
Beginning of 2024 |
LA 49/Williams Blvd Corridor Improvs. |
H.010570.6 - Sidewalks/bike paths
|
Proj. Engr: Rizzo, Kevin |
Route: |
LA 49
map
|
Contractor: Barriere Construction Co., LLC |
Miles:
| 1.15 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-09-11 |
$15,369,777 |
Fall of 2025 |
LA 541 Embankment Repair |
H.010621.6 - Embankment repair
|
Proj. Engr: Capote, Nelson |
Route: |
LA 541
map
|
Contractor: Hard Rock Construction LLC |
Miles:
| 0.15 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2013-01-11 |
$132,590 |
Summer of 2013 |
Control Section 249-01 La 45: Barataria Blvd Beautification |
H.010644.6 - Landscaping
|
Proj. Engr: Capote, Nelson |
Route: |
LA 45
map
|
Contractor: Baton Rouge Turf & Landscape, |
Miles:
| 1.80 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2013-02-06 |
$45,000 |
Spring of 2013 |
Us90z: Harvey Canal Tunnel Rehabilitation |
H.010673.6-R1 - Miscellaneous
|
Proj. Engr: Hollier, Corbett |
Route: |
I-910
map
|
Contractor: C.E.C., Inc. |
Miles:
| 0.36 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-06-26 |
$53,718,699 |
Fall of 2026 |
Loyola Dr./I-10 Interchange to New Airport Terminal (Lanoia) |
H.011670.6 - Planning study
|
Proj. Engr: Marchand, Wayne |
Route: |
I-10
map
|
Contractor: Gilchrist Construction Company |
Miles:
| 0.65 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2019-08-30 |
$141,440,403 |
Fall of 2024 |
LA 541: La 18(Louisiana) - La 18 (4th) |
H.012553.6 - Asphalt overlay of asphalt pavement
|
Proj. Engr: Hollier, Corbett |
Route: |
LA 541
map
|
Contractor: Barriere Construction Co., LLC |
Miles:
| 4.61 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2019-05-14 |
$3,475,120 |
Spring of 2020 |
LA 23: Intersection Imp @ Gretna Blvd |
H.012596.6 - Traffic flow improvements - formerly turn lanes
|
Proj. Engr: Hollier, Corbett |
Route: |
LA 23
map
|
Contractor: Barber Bros. Contracting Co., |
Miles:
| 0.16 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2020-03-23 |
$74,971 |
Summer of 2020 |
LA 3139: Dickory Ave - Orleans P/L |
H.012918.6-R1 - Concrete pavement rehab-grinding/dowell retrofit/should drain install
|
Proj. Engr: Rizzo, Kevin |
Route: |
LA 3139 LA 3154
map
|
Contractor: Cycle Construction Co. L.L.C. |
Miles:
| 4.97 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-03-07 |
$8,405,880 |
Summer of 2023 |
LA 45/La 303 Rosethorne Path (Lafitte) |
H.013365.6 - Sidewalks/bike paths
|
Proj. Engr: Oustalet, Randy |
Route: |
LA 303 LA 45
map
|
Contractor: Gulf States Services, LLC |
Miles:
| 1.89 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-01-04 |
$1,207,983 |
Spring of 2024 |
Do2 Drop Inlet Cleaning Us90-Z |
H.013417.6 - Drainage
|
Proj. Engr: Capote, Nelson |
Route: |
I-910
map
|
Contractor: |
Miles:
| 7.57 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2018-06-06 |
$323,878 |
Fall of 2018 |
US 90z: Harvey Tunnel Lighting Repl. |
H.013706.6 - Miscellaneous
|
Proj. Engr: Capote, Nelson |
Route: |
I-910
map
|
Contractor: Diamond Electrical Co., Inc. |
Miles:
| 0.01 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2020-08-17 |
$6,048,845 |
Spring of 2023 |
LA 3017: 4th St-Lapalco Blvd |
H.013745.6 - Asphalt overlay of asphalt pavement
|
Proj. Engr: Hollier, Corbett |
Route: |
LA 3017
map
|
Contractor: Barriere Construction Co., LLC |
Miles:
| 2.68 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2021-04-01 |
$3,429,517 |
Fall of 2022 |
US 90 & La 3046: Mill & Overlay |
H.013757.6 - Asphalt overlay of asphalt pavement
|
Proj. Engr: Rizzo, Kevin |
Route: |
US 90 LA 3046
map
|
Contractor: Barriere Construction Co., LLC |
Miles:
| 4.24 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2021-02-02 |
$6,156,033 |
Fall of 2022 |
US 61: Carrollton Ave - Causeway Blvd |
H.013762.6 - Asphalt overlay of asphalt pavement
|
Proj. Engr: Rizzo, Kevin |
Route: |
US 61
map
|
Contractor: Barriere Construction Co., LLC |
Miles:
| 3.11 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2021-07-12 |
$5,361,824 |
Fall of 2022 |
I-10 & I-610: Overhead Sign Upgrade |
H.013829.6 - Signing
|
Proj. Engr: Keller, Gerald |
Route: |
I-10
map
|
Contractor: Tlp Construction Co. LLC |
Miles:
| 1.92 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-09-04 |
$740,036 |
Summer of 2024 |
LA 18: Barataria Blvd - Louisiana St |
H.014076.6 - Asphalt overlay of asphalt pavement
|
Proj. Engr: Hollier, Corbett |
Route: |
LA 18
map
|
Contractor: Barriere Construction Co., LLC |
Miles:
| 2.95 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-03-21 |
$2,851,239 |
Beginning of 2023 |
LA 428: Wb Lane at La 23 |
H.014079.6 - Traffic flow improvements - formerly turn lanes
|
Proj. Engr: Hollier, Corbett |
Route: |
LA 428 LA 18
map
|
Contractor: Buck Town Contractors & Co. |
Miles:
| 0.27 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-03-14 |
$927,039 |
Summer of 2022 |
LA 3152: Lane Modifications |
H.014092.6 - Traffic flow improvements - formerly turn lanes
|
Proj. Engr: Zzzz Duplantis, Michael |
Route: |
LA 3152
map
|
Contractor: Barriere Construction Co., LLC |
Miles:
| 0.83 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2021-09-23 |
$1,688,378 |
Beginning of 2022 |
LA 23: Lapalco Blvd - Dale Ave |
H.014102.6 - Concrete pavement rehab-grinding/dowell retrofit/should drain install
|
Proj. Engr: Hollier, Corbett |
Route: |
LA 23
map
|
Contractor: Barriere Construction Co., LLC |
Miles:
| 0.24 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-05-31 |
$1,033,348 |
Beginning of 2023 |
US 90: S. Kenner Ave - La 18 |
H.014154.6 - Asphalt overlay of asphalt pavement
|
Proj. Engr: Herrington, Benny |
Route: |
US 90
map
|
Contractor: Barriere Construction Co., LLC |
Miles:
| 7.53 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-05-23 |
$10,061,954 |
Summer of 2024 |
US 90z: West Bank Expwy Pave Markings |
H.014387.6 - Striping and pavement markers
|
Proj. Engr: Hollier, Corbett |
Route: |
I-910
map
|
Contractor: Southern Synergy LLC |
Miles:
| 9.82 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2021-12-01 |
$1,963,215 |
Fall of 2022 |
LA 48: Huey P - La 49 |
H.014480.6 - Asphalt overlay of asphalt pavement
|
Proj. Engr: Zzzz Duplantis, Michael |
Route: |
LA 48
map
|
Contractor: Boh Bros. Construction Co., Ll |
Miles:
| 6.23 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-09-20 |
$15,051,400 |
Summer of 2025 |
LA 45 @ Ronquille St Drainage Repair |
H.014566.6 - Drainage
|
Proj. Engr: Capote, Nelson |
Route: |
LA 45
map
|
Contractor: |
Miles:
| 0.00 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2021-03-02 |
$40,243 |
Spring of 2021 |
LA 302: Kerner Ferry Bridge Repairs Ph 2 |
H.014587.6-R1 - Moveable bridges reconditioned
|
Proj. Engr: Zzzz Morvant, Chris |
Route: |
LA 302
map
|
Contractor: |
Miles:
| 0.12 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2021-07-16 |
$5,193,245 |
Summer of 2022 |
US 61 @ N Elm St |
H.014661.6 - Signalization
|
Proj. Engr: Rizzo, Kevin |
Route: |
US 61
map
|
Contractor: Tlp Construction Co. LLC |
Miles:
| 0.02 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-08-05 |
$284,707 |
Fall of 2023 |
LA 49:40th St - 550ft N of Veterans Blvd |
H.014705.6 - Asphalt widening and overlay
|
Proj. Engr: Zzzz Duplantis, Michael |
Route: |
LA 49
map
|
Contractor: Barriere Construction Co., LLC |
Miles:
| 0.91 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-09-26 |
$3,530,776 |
Summer of 2023 |
District 02 Appr Slab Leveling Phase 3 |
H.014760.6 - Asphalt overlay of asphalt pavement
|
Proj. Engr: Hollier, Corbett |
Route: |
I-910 LA 3017
map
|
Contractor: Barber Bros. Contracting Co., |
Miles:
| 0.19 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-06-26 |
$668,567 |
Fall of 2023 |
LA 3154: La 3139 - US 61 |
H.014853.6 - Concrete pavement rehab-grinding/dowell retrofit/should drain install
|
Proj. Engr: Rizzo, Kevin |
Route: |
LA 3154
map
|
Contractor: Buck Town Contractors & Co. |
Miles:
| 0.77 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-07-10 |
$869,067 |
End of 2023 |
LA 18: Roadway Raising @ Imtt |
H.014954.6 - Miscellaneous
|
Proj. Engr: Herrington, Benny |
Route: |
LA 18
map
|
Contractor: |
Miles:
| 0.16 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-03-09 |
$194,499 |
Spring of 2022 |
LA 302: Bayou Barataria Mb Repl Phase 1 |
H.015028.6 - New location/replacement of moveable bridge
|
Proj. Engr: Morvant, Ryan |
Route: |
LA 302-P LA 302
map
|
Contractor: Boh Bros. Construction Co., Ll |
Miles:
| 0.56 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-02-17 |
$55,169,064 |
Beginning of 2028 |
US 90b: Manhattan Blvd to La 45 |
H.015112.6 - Miscellaneous
|
Proj. Engr: Hollier, Corbett |
Route: |
I-910
map
|
Contractor: The Truesdell Corporation |
Miles:
| 1.44 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-05-08 |
$6,069,069 |
Summer of 2024 |
US 90z Sidewalks Westwego |
H.015121.6 - Sidewalks/bike paths
|
Proj. Engr: Hollier, Corbett |
Route: |
map
|
Contractor: Gulf States Services, LLC |
Miles:
| 0.60 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-08-16 |
$398,965 |
Fall of 2023 |
4th St. - US 90b & Weyer Ave. - La 560-2 |
062-01-0031-R1 - Asphalt overlay of asphalt pavement
|
Proj. Engr: Capote, Nelson |
Route: |
LA 18
map
|
Contractor: Barriere Construction Co., LLC |
Miles:
| 0.50 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2011-02-07 |
$1,960,756 |
Summer of 2011 |
Lafourche Parish
Note: The estimated completion date is based
on the work order date and the contract
days allowed.
Unavoidable contingencies and unforeseen events
often develop during construction, which may
impact the actual completion date.
Canal Street Bridge Pedestrian Crossing |
H.001486.6 - Sidewalks/bike paths
|
Proj. Engr: Badeaux, Al |
Route: |
LA 20
map
|
Contractor: Sealevel Construction Inc. |
Miles:
| 0.07 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2013-05-23 |
$563,415 |
Spring of 2014 |
LA 1: Leeville to Golden Meadow (Phase 2) |
H.008145.6 - New location/replacement of bridge
|
Proj. Engr: Gisclair, Gary |
Route: |
LA 1 LA 3235
map
|
Contractor: James Construction Group LLC |
Miles:
| 8.70 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-02-08 |
$465,225,271 |
Beginning of 2028 |
Acadian Road Roundabout |
H.009320.6 - Traffic flow improvements - formerly turn lanes
|
Proj. Engr: Usey, Brandon |
Route: |
LA 20
map
|
Contractor: LA Contracting Enterprise LLC |
Miles:
| 0.52 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-04-03 |
$8,774,137 |
Spring of 2025 |
West Larose Vertical Lift Bridge Rehabilitation |
H.009479.6 - Moveable bridges reconditioned
|
Proj. Engr: Maurin, Roland |
Route: |
LA 1
map
|
Contractor: C.E.C., Inc. |
Miles:
| 1.00 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2015-05-04 |
$26,245,702 |
Fall of 2020 |
LA 308: Golden Meadow Br - Galliano Br |
H.009662.6 - Asphalt overlay of asphalt pavement
|
Proj. Engr: Usey, Brandon |
Route: |
LA 308
map
|
Contractor: Huey P. Stockstill, LLC |
Miles:
| 6.78 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-02-13 |
$6,304,563 |
Beginning of 2024 |
LA 1 Toll Plaza Improvements (Electrical) |
H.009858.6 - Miscellaneous
|
Proj. Engr: Zzzz Gisclair, Gary |
Route: |
LA 1
|
Contractor: Ernest P. Breaux Electrical, I |
Miles:
| 0.00 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2012-03-19 |
$429,065 |
Spring of 2012 |
Airport Connector Road and Bridge |
H.011915.6 - Concrete new pavement
|
Proj. Engr: Picciola, Joe |
Route: |
LA 3235 LA 1
map
|
Contractor: Sealevel Construction Inc. |
Miles:
| 1.13 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2021-08-08 |
$31,003,583 |
Fall of 2025 |
LA 1: La 1 Bridge - Falgout Ln |
H.013225.6 - Asphalt overlay of asphalt pavement
|
Proj. Engr: Usey, Brandon |
Route: |
LA 1
map
|
Contractor: Barriere Construction Co., LLC |
Miles:
| 9.74 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2020-08-01 |
$4,712,968 |
Spring of 2022 |
LA 182: Hollywood Canal Bridge Repair |
H.014290.6 - Embankment repair
|
Proj. Engr: Usey, Brandon |
Route: |
LA 182
map
|
Contractor: |
Miles:
| 0.04 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2020-04-29 |
$261,921 |
Summer of 2020 |
LA 308 Resurfacing Near Mccloud Rd. |
H.014376.6 - Asphalt overlay of asphalt pavement
|
Proj. Engr: Usey, Brandon |
Route: |
LA 308
map
|
Contractor: |
Miles:
| 0.05 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2021-01-14 |
$46,949 |
Summer of 2021 |
Leeville Bridge Curve Barrier Repair |
H.014617.6 - Miscellaneous
|
Proj. Engr: Rogers, Chris |
Route: |
LA 1
map
|
Contractor: |
Miles:
| 0.00 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2021-05-01 |
$29,072 |
Summer of 2021 |
LA 316 Culvert 850' Nw La 316 - La 3087 |
H.014953.6 - Drainage
|
Proj. Engr: Usey, Brandon |
Route: |
LA 316
map
|
Contractor: |
Miles:
| 0.00 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-01-17 |
$107,534 |
Beginning of 2022 |
La1 Toll Facility Electrical Repairs |
H.014972.6 - ITS and emergency operations
|
Proj. Engr: Usey, Brandon |
Route: |
LA 1
map
|
Contractor: Ernest P. Breaux Electrical, L |
Miles:
| 0.02 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-02-22 |
$242,963 |
Spring of 2023 |
La1&657:icww&byu Lafourche Mb Rprs(Hbi) |
H.014998.6 - Moveable bridges reconditioned
|
Proj. Engr: Burgess, Matthew |
Route: |
LA 1 LA 657
map
|
Contractor: C.E.C., Inc. |
Miles:
| 0.44 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-07-03 |
$459,328 |
Spring of 2024 |
LA 1 Toll System O&m |
H.015135.6 - Miscellaneous
|
Proj. Engr: Heraty, Stephen P. |
Route: |
LA 1
map
|
Contractor: Plenary Infrastructure Belle C |
Miles:
| 0.20 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-09-27 |
$9,610,753 |
Beginning of 2028 |
US 90 at La 182 Improvements |
H.015501.6 - Asphalt new pavement-new roadway/new alignments
|
Proj. Engr: Burgess, Matthew |
Route: |
US 90 LA 182
map
|
Contractor: Barriere Construction Co., LLC |
Miles:
| 0.85 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-08-08 |
$4,258,272 |
Spring of 2024 |
Orleans Parish
Note: The estimated completion date is based
on the work order date and the contract
days allowed.
Unavoidable contingencies and unforeseen events
often develop during construction, which may
impact the actual completion date.
I-610: (I-10 to St. Bernard Ave.) |
H.003134.6-R1 - Asphalt overlay of concrete pavement
|
Proj. Engr: Guilbeau, Justin |
Route: |
I-610
map
|
Contractor: Barriere Construction Co., LLC |
Miles:
| 2.58 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2013-05-21 |
$7,355,233 |
Spring of 2014 |
Ihnc and Algiers Cutoff Bridge Rehab |
H.003182.6-R1 - Bridges reconditioned
|
Proj. Engr: Guilbeau, Justin |
Route: |
I-10 LA 407
map
|
Contractor: Gibson & Associates Inc. |
Miles:
| 3.82 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2016-02-26 |
$10,376,224 |
Summer of 2017 |
US 90 Bus: Cccd - Sign Installations |
H.005889.6 - Signing
|
Proj. Engr: Boyle, Scott |
Route: |
I-910
map
|
Contractor: Traffic Solutions, Inc. |
Miles:
| 0.25 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2013-09-27 |
$196,862 |
Spring of 2014 |
I-10: US 90z - I-610 Pavement Markings |
H.009186.6 - Striping and pavement markers
|
Proj. Engr: Hamide, Mahmoud |
Route: |
I-10
map
|
Contractor: Stripe-a-Zone, LLC |
Miles:
| 4.22 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-06-27 |
$1,353,985 |
End of 2023 |
New Orleans Dpw Srts Sidewalk Project |
H.009308.6 - Striping and pavement markers
|
Proj. Engr: Flynn, Mary |
Route: |
US 90
map
|
Contractor: Roubion Roads & Streets LLC |
Miles:
| 0.34 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2021-08-09 |
$1,594,645 |
Beginning of 2023 |
I-10: No Terminal R/R Br Painting & Cleaning |
H.009393.6 - Bridge painting
|
Proj. Engr: Guilbeau, Justin |
Route: |
I-10
map
|
Contractor: Astron General Contracting, In |
Miles:
| 0.01 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2012-09-27 |
$921,128 |
Spring of 2013 |
LA 47: I-10 N. Service Rd. - Bullard Ave. |
H.009663.6 - Concrete pavement rehab-grinding/dowell retrofit/should drain install
|
Proj. Engr: Guilbeau, Justin |
Route: |
LA 47
map
|
Contractor: Roubion Roads & Streets LLC |
Miles:
| 2.89 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2017-06-05 |
$2,273,814 |
Summer of 2018 |
I-10: No East Drain Canal Bridge Replace |
H.010018.6 - Bridges reconditioned
|
Proj. Engr: Hamide, Mahmoud |
Route: |
I-10
map
|
Contractor: Brown Industrial Construction, |
Miles:
| 2.60 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2020-05-18 |
$28,862,077 |
Spring of 2023 |
LA 1253: Downman Rd - I-10 Frontage Rd |
H.010414.6 - Concrete pavement rehab-grinding/dowell retrofit/should drain install
|
Proj. Engr: Hamide, Mahmoud |
Route: |
LA 1253
map
|
Contractor: Command Construction Industrie |
Miles:
| 0.54 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2021-03-05 |
$539,011 |
Summer of 2021 |
Us90z (Bodenger Blvd - Stumpf Blvd) |
H.010634.6-R2 - Signing
|
Proj. Engr: Hollier, Corbett |
Route: |
I-910
map
|
Contractor: C.E.C., Inc. |
Miles:
| 2.96 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2021-10-18 |
$9,984,269 |
Summer of 2023 |
I-10: Cbd 2 Carrollton - Lafitte Ave |
H.011220.6 - Signing
|
Proj. Engr: Hamide, Mahmoud |
Route: |
I-10
map
|
Contractor: C.E.C., Inc. |
Miles:
| 2.86 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2019-06-13 |
$11,232,830 |
Fall of 2021 |
I-10: N.O. Cbd 5 (I-510 to End of Twin Span) |
H.011223.6 - Signing
|
Proj. Engr: Hamide, Mahmoud |
Route: |
I-10
map
|
Contractor: Traffic Commander, LLC |
Miles:
| 14.07 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-01-23 |
$4,303,604 |
Summer of 2024 |
I-10 E at I-510 Mm 247 Emergency Barrier Wall Repair |
H.011712.6 - Bridges reconditioned
|
Proj. Engr: Guilbeau, Justin |
Route: |
I-10
map
|
Contractor: D. O'brian Construction, LLC |
Miles:
| 0.10 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2015-04-02 |
$315,993 |
Summer of 2015 |
LA 47: Iwgo Bridge Rehabilitation (Hbi) |
H.011965.6 - Bridge painting
|
Proj. Engr: Thomas, Tim |
Route: |
LA 47
map
|
Contractor: Vimas Painting Company Inc. |
Miles:
| 1.28 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-12-05 |
$44,896,796 |
Spring of 2027 |
US 90: Press to Majestic Oaks |
H.012312.6 - Planning study
|
Proj. Engr: Robert, Joseph |
Route: |
US 90
map
|
Contractor: Boh Bros. Construction Co., Ll |
Miles:
| 1.04 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-08-30 |
$4,424,654 |
Spring of 2023 |
I-510: S End of Intracoastal Br I-10 |
H.012590.6 - Asphalt overlay of asphalt pavement
|
Proj. Engr: Guilbeau, Justin |
Route: |
I-510 LA 47
map
|
Contractor: Barriere Construction Co., LLC |
Miles:
| 4.70 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2018-09-24 |
$5,457,945 |
Fall of 2019 |
I-10: Paris Rd - Lake Pontchartrain |
H.012591.6 - Asphalt overlay of concrete pavement
|
Proj. Engr: Robert, Joseph |
Route: |
I-10
map
|
Contractor: Madden Gulf Coast, LLC |
Miles:
| 8.18 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-06-01 |
$16,385,112 |
Summer of 2024 |
I-10 Ramps @ La 3019 Int Imp |
H.012676.6-R1 - Traffic flow improvements - formerly turn lanes
|
Proj. Engr: Hamide, Mahmoud |
Route: |
LA 3019 I-10
map
|
Contractor: Barriere Construction Co., LLC |
Miles:
| 0.42 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-03-14 |
$1,656,353 |
Beginning of 2023 |
Pedestrian Crosswalk Enh. (No Ph 2) |
H.012682.6 - Signalization
|
Proj. Engr: Foley, John |
Route: |
I-910 US 90
map
|
Contractor: Jb Group of La, LLC Dba Infras |
Miles:
| 10.92 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2021-11-16 |
$2,619,459 |
Beginning of 2023 |
I-10 N Service Rd: Dwyer Rd - Paris Rd |
H.012742.6 - Asphalt overlay of asphalt pavement
|
Proj. Engr: Guilbeau, Justin |
Route: |
I-10
map
|
Contractor: Barber Bros. Contracting Co., |
Miles:
| 5.39 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2018-08-13 |
$1,907,661 |
Spring of 2019 |
I-10 S Service Rd: Morrison Rd-Paris Rd |
H.012743.6 - Asphalt overlay of asphalt pavement
|
Proj. Engr: Guilbeau, Justin |
Route: |
I-10
map
|
Contractor: Boh Bros. Construction Co., Ll |
Miles:
| 5.04 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2019-04-05 |
$1,460,824 |
Fall of 2019 |
US-90z (I-10 to Magnolia Street) |
H.012876.6 - Signing
|
Proj. Engr: Hamide, Mahmoud |
Route: |
I-910 US 90
map
|
Contractor: C.E.C., Inc. |
Miles:
| 1.89 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2019-06-13 |
$8,749,797 |
Spring of 2021 |
US 90z (Magnolia Street-Bodenger Blvd) |
H.012901.6 - Signing
|
Proj. Engr: Hamide, Mahmoud |
Route: |
I-910
map
|
Contractor: C.E.C., Inc. |
Miles:
| 2.51 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2019-08-28 |
$8,404,027 |
Beginning of 2021 |
LA 39: Judge Seeber Br Mech Rehab (Hbi) |
H.012956.6 - Moveable bridges reconditioned
|
Proj. Engr: Hamide, Mahmoud |
Route: |
LA 39
map
|
Contractor: C.E.C., Inc. |
Miles:
| 0.24 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2020-04-27 |
$1,370,627 |
Beginning of 2021 |
I-610 E Br Rail Near Mp 4.6 Emerg Repair |
H.013167.6-R1 - Guardrails
|
Proj. Engr: Guilbeau, Justin |
Route: |
I-610
map
|
Contractor: Gibson & Associates Inc. |
Miles:
| 0.07 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2018-01-08 |
$69,655 |
Beginning of 2018 |
LA 46: La 39 - St. Bernard P/L |
H.013211.6 - Asphalt overlay of asphalt pavement
|
Proj. Engr: Robert, Joseph |
Route: |
LA 46
map
|
Contractor: Barriere Construction Co., LLC |
Miles:
| 3.51 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2021-01-01 |
$7,753,666 |
Spring of 2024 |
D02 Drop Inlet Cleaning |
H.013419.6 - Drainage
|
Proj. Engr: Hamide, Mahmoud |
Route: |
I-10 I-610
map
|
Contractor: |
Miles:
| 14.64 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2018-09-04 |
$330,740 |
Beginning of 2019 |
I-10: Crowder Blvd Interstate Lighting |
H.013442.6 - Roadway lighting
|
Proj. Engr: Hamide, Mahmoud |
Route: |
I-10
map
|
Contractor: Jack B. Harper Electrical LLC |
Miles:
| 1.06 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2020-06-22 |
$1,249,577 |
Summer of 2022 |
US 90-Z Wb Expwy Curtain Wall Repair |
H.013530.6-R1 - Miscellaneous
|
Proj. Engr: Hollier, Corbett |
Route: |
I-910
map
|
Contractor: |
Miles:
| 0.00 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2018-09-10 |
$88,911 |
Fall of 2018 |
Remove and Replace Damaged Portions of Concrete Bridge Rails |
H.013536.6 - Miscellaneous
|
Proj. Engr: Hollier, Corbett |
Route: |
I-910
map
|
Contractor: |
Miles:
| 0.00 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2018-07-12 |
$49,997 |
Summer of 2018 |
I-10: Canal St - St. Philip St |
H.013586.6 - Asphalt surface treatment
|
Proj. Engr: Guilbeau, Justin |
Route: |
I-10
map
|
Contractor: The Truesdell Corporation |
Miles:
| 0.69 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2019-09-16 |
$1,958,610 |
Spring of 2020 |
I-10 @ Morrison Rd |
H.013587.6-R1 - Asphalt surface treatment
|
Proj. Engr: Robert, Joseph |
Route: |
I-10
map
|
Contractor: Barriere Construction Co., LLC |
Miles:
| 0.68 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2020-05-18 |
$3,337,264 |
Beginning of 2021 |
I-10: I-610e Interchange Lighting |
H.013617.6 - Roadway lighting
|
Proj. Engr: Roberts, Joseph |
Route: |
I-10 I-610
map
|
Contractor: Diamond Electrical Co., Inc. |
Miles:
| 1.20 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-09-23 |
$4,725,093 |
Summer of 2025 |
US 90/ I-10 Service Rd/ La 39 Overlay |
H.013746.6 - Asphalt overlay of asphalt pavement
|
Proj. Engr: Hamide, Mahmoud |
Route: |
I-10 US 90
map
|
Contractor: Barber Bros. Contracting Co., |
Miles:
| 3.97 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2020-10-08 |
$6,969,328 |
Beginning of 2023 |
I-10 Pipe Repairs Near Metairie Rd |
H.013961.6 - Drainage
|
Proj. Engr: Hamide, Mahmoud |
Route: |
I-10
map
|
Contractor: |
Miles:
| 0.01 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2019-12-09 |
$307,882 |
Beginning of 2020 |
LA 3021: La 39 - US 90 |
H.014097.6 - Asphalt overlay of asphalt pavement
|
Proj. Engr: Robert, Joseph |
Route: |
LA 3021
map
|
Contractor: Boh Bros. Construction Co., Ll |
Miles:
| 1.80 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-09-26 |
$6,505,172 |
Summer of 2024 |
US 90b @ Claiborne Exit Ramp |
H.014134.6 - Drainage
|
Proj. Engr: Hamide, Mahmoud |
Route: |
I-910
map
|
Contractor: Command Construction Industrie |
Miles:
| 0.15 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2020-08-28 |
$466,565 |
Fall of 2020 |
I-10: Concrete Barrier @ Chef Ramp |
H.014155.6 - Miscellaneous
|
Proj. Engr: Robert, Joseph |
Route: |
I-10
map
|
Contractor: |
Miles:
| 0.04 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2020-01-24 |
$58,765 |
Beginning of 2020 |
I-10 Bridge Rail Repair at Downman Exit |
H.014172.6 - Miscellaneous
|
Proj. Engr: Hamide, Mahmoud |
Route: |
I-10
map
|
Contractor: |
Miles:
| 0.04 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2020-01-27 |
$251,097 |
Spring of 2020 |
I-10: Ihnc Br - Twin Spans Bridge (Rpms) |
H.014296.6 - Striping and pavement markers
|
Proj. Engr: Robert, Joseph |
Route: |
I-10
map
|
Contractor: Southern Synergy LLC |
Miles:
| 15.77 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2021-03-05 |
$428,815 |
Summer of 2021 |
US 90b:la 428 Overpass (Level Appr Slab) |
H.014360.6 - Bridges reconditioned
|
Proj. Engr: Hollier, Corbett |
Route: |
I-910
map
|
Contractor: Barriere Construction Co., LLC |
Miles:
| 0.02 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2021-07-29 |
$149,902 |
Summer of 2021 |
US 90b Attenuator Repairs |
H.014365.6 - Miscellaneous
|
Proj. Engr: Hollier, Corbett |
Route: |
I-910
map
|
Contractor: |
Miles:
| 0.03 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2021-02-08 |
$107,879 |
Spring of 2021 |
US 90z: I-10 - Terry Pkwy Exit Pave Mkgs |
H.014383.6 - Striping and pavement markers
|
Proj. Engr: Hollier, Corbett |
Route: |
I-910
map
|
Contractor: Southern Synergy LLC |
Miles:
| 4.51 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2021-07-04 |
$2,079,731 |
Beginning of 2022 |
I-10 Bridge Rail Near Franklin |
H.014437.6 - Miscellaneous
|
Proj. Engr: Robert, Joseph |
Route: |
I-10
map
|
Contractor: |
Miles:
| 0.00 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2020-11-05 |
$41,311 |
End of 2020 |
I-10 Barriers: Chef Menteur Hwy-I-510 |
H.014585.6 - Miscellaneous
|
Proj. Engr: Robert, Joseph |
Route: |
I-10
map
|
Contractor: Command Construction Industrie |
Miles:
| 5.58 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-06-10 |
$9,215,358 |
Summer of 2023 |
I-10 Bridge Rail Repair @ St. Roch Ave. |
H.014665.6 - Miscellaneous
|
Proj. Engr: Robert, Joseph |
Route: |
I-10
map
|
Contractor: |
Miles:
| 0.00 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2021-07-27 |
$119,750 |
Summer of 2021 |
US 61: Turn Lanes @ S Clark and Johnson |
H.014753.6 - Traffic flow improvements - formerly turn lanes
|
Proj. Engr: Hamide, Mahmoud |
Route: |
US 61 US 90
map
|
Contractor: Barber Bros. Contracting Co., |
Miles:
| 0.11 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-09-19 |
$393,143 |
Beginning of 2023 |
US 90 B @ Simon Bolivar Drain Repair |
H.014955.6 - Drainage
|
Proj. Engr: Roberts, Joseph |
Route: |
I-910
map
|
Contractor: |
Miles:
| 0.00 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-03-07 |
$70,682 |
Spring of 2022 |
Districtwide Painted Traffic Striping |
H.014957.6-R1 - Striping and pavement markers
|
Proj. Engr: Robert, Joseph |
Route: |
US 90
map
|
Contractor: |
Miles:
| 14.28 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-06-08 |
$179,030 |
Spring of 2022 |
I-10 Wb @ I-610 Wb Improvements |
H.015113.6 - Miscellaneous
|
Proj. Engr: Hamide, Mahmoud |
Route: |
I-10 I-610
map
|
Contractor: The Truesdell Corporation |
Miles:
| 0.43 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-06-30 |
$618,618 |
Fall of 2023 |
I-610 Fence Repairs (Ida) |
H.015364.6 - Fencing
|
Proj. Engr: Hamide, Mahmoud |
Route: |
I-610
map
|
Contractor: Construction Management Enterp |
Miles:
| 0.85 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-05-22 |
$650,000 |
Beginning of 2024 |
I-610 Bridge Rail Repair |
H.015564.6 - Miscellaneous
|
Proj. Engr: Robert, Joseph |
Route: |
I-610
map
|
Contractor: |
Miles:
| 0.00 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-07-24 |
$53,400 |
Fall of 2023 |
I-10 Bridge Rail Repair |
H.015565.6 - Miscellaneous
|
Proj. Engr: Robert, Joseph |
Route: |
I-10
map
|
Contractor: |
Miles:
| 1.20 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-07-01 |
$149,850 |
Summer of 2023 |
Judge Seeber Bridge Repairs |
046-31-0053 - Moveable bridges reconditioned
|
Proj. Engr: Zzzz Guidry, John |
Route: |
LA 39
map
|
Contractor: Boh Bros. Construction Co., LLC. |
Miles:
| 0.00 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2009-06-26 |
$8,936,932 |
Fall of 2010 |
Leveling Approach Slabs and Improvements |
409-02-0018 - Asphalt overlay of asphalt pavement
|
Proj. Engr: Capote, Nelson |
Route: |
LA 406
map
|
Contractor: Barriere Construction Co., LLC |
Miles:
| 0.41 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2011-08-11 |
$568,388 |
Fall of 2011 |
Pontchartrain Pump Station Repairs Due to Hurricane Katrina |
450-90-0210 - Drainage
|
Proj. Engr: Zzzz Wetekamm, Fred |
Route: |
I-10
|
Contractor: Industrial & Mechanical Contr. Ll |
Miles:
| 0.00 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2008-08-04 |
$1,597,784 |
End of 2009 |
Drainage Improvements on I-10 |
450-90-0242 - Drainage
|
Proj. Engr: Zzzz Zeringue, Kirk |
Route: |
I-10
map
|
Contractor: Rcs Contractors, Inc. |
Miles:
| 5.00 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2011-08-12 |
$267,345 |
Summer of 2011 |
Administration Building Expansion |
610-01-0022 - Buildings and grounds excluding rest areas
|
Proj. Engr: Skoien, Richard W. |
Route: |
|
Contractor: Jaroy Construction, Inc. |
Miles:
| 0.00 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2008-02-11 |
$3,799,661 |
End of 2009 |
Algiers Cut Off Canal Bridge Lighting Installation |
836-08-0072 - Roadway lighting
|
Proj. Engr: Capote, Nelson |
Route: |
LA 407
map
|
Contractor: Jack B. Harper Contractor, Inc. |
Miles:
| 1.19 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2008-02-01 |
$876,032 |
Fall of 2008 |
Plaquemines Parish
Note: The estimated completion date is based
on the work order date and the contract
days allowed.
Unavoidable contingencies and unforeseen events
often develop during construction, which may
impact the actual completion date.
Judge Perez Br. Wirerope Repl., Gearbox & Mach. House Repair |
H.001390.6 - Moveable bridges reconditioned
|
Proj. Engr: Capote, Nelson |
Route: |
LA 23
map
|
Contractor: C.E.C., Inc. |
Miles:
| 0.01 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2011-10-24 |
$968,252 |
Beginning of 2012 |
LA 23: Belle Chasse Bridge & Tunnel (Hbi) |
H.004791.6 - Engineering
|
Proj. Engr: Heraty, Stephen P. |
Route: |
LA 23
map
|
Contractor: Plenary Infrastructure Belle C |
Miles:
| 0.81 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2019-12-20 |
$180,858,162 |
Spring of 2026 |
LA 23: Diamond Rd - 665 Ft S Martin La |
H.009223.6-R1 - Concrete pavement rehab-grinding/dowell retrofit/should drain install
|
Proj. Engr: Capote, Nelson |
Route: |
LA 23
map
|
Contractor: Barriere Construction Co., LLC |
Miles:
| 0.71 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2012-10-25 |
$329,535 |
Beginning of 2013 |
LA 23: Tunnel - Russell Dr |
H.012560.6 - Asphalt overlay of asphalt pavement
|
Proj. Engr: Hollier, Corbett |
Route: |
LA 23
map
|
Contractor: Barriere Construction Co., LLC |
Miles:
| 4.30 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2021-02-01 |
$5,082,163 |
Fall of 2022 |
La23: Ravenna Rd - Lm 4.040 |
H.012987.6 - Asphalt overlay of asphalt pavement
|
Proj. Engr: Hollier, Corbett |
Route: |
LA 23
map
|
Contractor: |
Miles:
| 5.68 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-01-24 |
$205,286 |
Beginning of 2022 |
LA 406: Lt. Turn Lane at Green Trails Dr |
H.014487.6 - Asphalt widening and overlay
|
Proj. Engr: Hollier, Corbett |
Route: |
LA 406
map
|
Contractor: Buck Town Contractors & Co. |
Miles:
| 0.31 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2021-10-11 |
$1,699,578 |
Beginning of 2022 |
LA 39: Braithwaite Drainage Repair |
H.014569.6 - Drainage
|
Proj. Engr: Robert, Joseph |
Route: |
LA 39
map
|
Contractor: |
Miles:
| 0.00 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2021-03-16 |
$79,513 |
Spring of 2021 |
LA 23: Empire Drainage Repair |
H.014570.6 - Drainage
|
Proj. Engr: Capote, Nelson |
Route: |
LA 23
map
|
Contractor: |
Miles:
| 0.00 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2021-02-09 |
$412,028 |
Spring of 2021 |
LA 23 Crossdrain 600' S Parish Rd 11 |
H.014911.6 - Drainage
|
Proj. Engr: Hollier, Corbett |
Route: |
LA 23
map
|
Contractor: |
Miles:
| 0.00 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-02-07 |
$458,912 |
Beginning of 2022 |
Emergency Dredging of Ostrica Canal |
704-38-0011 - Miscellaneous
|
Proj. Engr: Capote, Nelson |
Route: |
|
Contractor: Grillot Construction LLC |
Miles:
| 0.00 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2008-02-11 |
$1,058,050 |
Beginning of 2009 |
St. Bernard Parish
Note: The estimated completion date is based
on the work order date and the contract
days allowed.
Unavoidable contingencies and unforeseen events
often develop during construction, which may
impact the actual completion date.
Bayou La Loutre Bridge Rehabilitation |
H.002562.6 - New location/replacement of bridge
|
Proj. Engr: Guilbeau, Justin |
Route: |
LA 46
map
|
Contractor: C.E.C., Inc. |
Miles:
| 0.04 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2016-10-31 |
$6,046,006 |
Spring of 2019 |
LA 46: Orleans P/L - Paris Rd |
H.010406.6 - Asphalt overlay of asphalt pavement
|
Proj. Engr: Guilbeau, Justin |
Route: |
LA 46
map
|
Contractor: Barber Bros. Contracting Co., |
Miles:
| 2.90 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2016-02-15 |
$3,870,157 |
Summer of 2017 |
LA 39: X-Drain Repair @ Debouchel Canal |
H.012292.6 - Drainage
|
Proj. Engr: Guilbeau, Justin |
Route: |
LA 39
map
|
Contractor: Cheniere Construction, Inc. |
Miles:
| 0.00 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2016-02-16 |
$48,861 |
Spring of 2016 |
LA 39 and La 46 Crossdrain Replacements |
H.012804.6-R1 - Drainage
|
Proj. Engr: Guilbeau, Justin |
Route: |
LA 46 LA 39
map
|
Contractor: Boh Bros. Construction Co., Ll |
Miles:
| 0.01 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2017-03-06 |
$579,631 |
Summer of 2017 |
St. Bernard Parish 40 Arpent Trail, Ph 1 |
H.013525.6 - Sidewalks/bike paths
|
Proj. Engr: Oustalet, Randy |
Route: |
LA 47
map
|
Contractor: Baker Pile Driving and Site Wo |
Miles:
| 0.02 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-10-03 |
$8,108,282 |
Summer of 2023 |
LA 47: La 46 - S End of Intracoastal Br |
H.013560.6 - Asphalt overlay of asphalt pavement
|
Proj. Engr: Robert, Joseph |
Route: |
LA 47
map
|
Contractor: Boh Bros. Construction Co., Ll |
Miles:
| 4.41 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2020-02-21 |
$3,889,254 |
Spring of 2021 |
LA 39: Left Turn Lane at La 47 |
H.013758.6 - Traffic flow improvements - formerly turn lanes
|
Proj. Engr: Robert, Joseph |
Route: |
LA 39 LA 47
map
|
Contractor: Barber Bros. Contracting Co., |
Miles:
| 0.26 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-09-04 |
$781,382 |
End of 2022 |
LA 46: La 47 - 450' East of Webster |
H.014072.6 - Asphalt overlay of asphalt pavement
|
Proj. Engr: Roberts, Joseph |
Route: |
LA 46
map
|
Contractor: Boh Bros. Construction Co., Ll |
Miles:
| 2.69 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2021-09-15 |
$1,582,740 |
Beginning of 2022 |
LA 46: Florissant Hwy Drainage Repair |
H.014568.6 - Drainage
|
Proj. Engr: Roberts, Joseph |
Route: |
LA 46
map
|
Contractor: |
Miles:
| 0.00 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2021-04-08 |
$56,680 |
Spring of 2021 |
LA 39 @ Guerra Dr |
H.014706.6 - Traffic flow improvements - formerly turn lanes
|
Proj. Engr: Robert, Joseph |
Route: |
LA 39
map
|
Contractor: Command Construction Industrie |
Miles:
| 0.16 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-07-08 |
$440,102 |
Fall of 2023 |
LA 39: Orleans P/L - Norton Ave |
H.014847.6 - Asphalt overlay of asphalt pavement
|
Proj. Engr: Robert, Joseph |
Route: |
LA 39
map
|
Contractor: Barriere Construction Co., LLC |
Miles:
| 0.89 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-08-18 |
$2,509,277 |
Spring of 2024 |
Yscloskey Bridge Rehabilitation- Hurricane Katrina |
284-02-0035 - Moveable bridges reconditioned
|
Proj. Engr: Zzzz Wetekamm, Fred |
Route: |
map
|
Contractor: Coastal Bridge Co., L.L.C. |
Miles:
| 0.34 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2007-01-22 |
$2,724,013 |
Spring of 2008 |
St. Charles Parish
Note: The estimated completion date is based
on the work order date and the contract
days allowed.
Unavoidable contingencies and unforeseen events
often develop during construction, which may
impact the actual completion date.
LA 48: Ormond Blvd - Wesco Rd |
H.010413.6 - Asphalt overlay of asphalt pavement
|
Proj. Engr: Keller, Gerald |
Route: |
LA 48
map
|
Contractor: Barriere Construction Co., LLC |
Miles:
| 2.94 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-09-04 |
$1,762,280 |
Beginning of 2024 |
US 90: Floodwall - S Kenner Ave |
H.012051.6 - Asphalt widening and overlay
|
Proj. Engr: Hollier, Corbett |
Route: |
US 90
map
|
Contractor: Barriere Construction Co., LLC |
Miles:
| 1.57 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2020-05-09 |
$1,470,825 |
Fall of 2020 |
LA 18: Left Turn Lane @ La 3060 |
H.012600.6 - Traffic flow improvements - formerly turn lanes
|
Proj. Engr: Herrington, Benny |
Route: |
LA 18
map
|
Contractor: Kcr Contractors, LLC |
Miles:
| 0.17 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2019-08-19 |
$563,450 |
Fall of 2019 |
I-310: I-10 to US 90 |
H.012617.6 - Concrete pavement rehab-grinding/dowell retrofit/should drain install
|
Proj. Engr: Herrington, Benny |
Route: |
I-310
map
|
Contractor: Boh Bros. Construction Co., Ll |
Miles:
| 11.71 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2020-02-24 |
$11,142,439 |
Spring of 2022 |
LA 3127: Right Turn Lane at La 3141 |
H.012836.6 - Traffic flow improvements - formerly turn lanes
|
Proj. Engr: Herrington, Benny |
Route: |
LA 3127
map
|
Contractor: Fleming Construction Co., LLC |
Miles:
| 0.14 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2019-09-18 |
$169,800 |
Beginning of 2020 |
I-310: Concrete Patch at Sb Mm 9 |
H.013432.6 - Concrete new pavement
|
Proj. Engr: Herrington, Benny |
Route: |
I-310
map
|
Contractor: Forby Contracting, Inc. |
Miles:
| 0.02 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2019-01-23 |
$148,762 |
Spring of 2019 |
LA 52 (Ph 1): Blueberry Hill-Angus Dr. |
H.013494.6 - Sidewalks/bike paths
|
Proj. Engr: Herrington, Benny |
Route: |
LA 52
map
|
Contractor: Hard Rock Construction LLC |
Miles:
| 0.88 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-07-13 |
$10,954,325 |
Beginning of 2025 |
US 90: Des Allemands Br - La 52 |
H.014481.6 - Asphalt overlay of asphalt pavement
|
Proj. Engr: Herrington, Benny |
Route: |
US 90
map
|
Contractor: Barriere Construction Co., LLC |
Miles:
| 8.60 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-09-19 |
$11,028,759 |
Spring of 2025 |
I-10 W Mm 220.6 Bridge Rail Repair |
H.014607.6 - Miscellaneous
|
Proj. Engr: Skoien, Richard |
Route: |
I-10
map
|
Contractor: |
Miles:
| 0.00 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2021-05-03 |
$37,071 |
Spring of 2021 |
I-310 Bridge Rail Repair |
H.015567.6 - Miscellaneous
|
Proj. Engr: Keller, Gerald |
Route: |
I-310
map
|
Contractor: |
Miles:
| 3.16 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-07-05 |
$139,270 |
Summer of 2023 |
I-310 N.B., S.B. & Ramp Bearing Pad & Joint Seal Replacement |
450-36-0035 - Bridges reconditioned
|
Proj. Engr: Zzzz Weber, Alan |
Route: |
|
Contractor: Gibson & Associates Inc. |
Miles:
| 0.00 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2011-07-17 |
$1,356,720 |
Spring of 2012 |
Terrebonne Parish
Note: The estimated completion date is based
on the work order date and the contract
days allowed.
Unavoidable contingencies and unforeseen events
often develop during construction, which may
impact the actual completion date.
LA 24 & La 316: Company Canal Bridge |
H.001498.6 - New location/replacement of bridge
|
Proj. Engr: Wetekamm, Fred |
Route: |
LA 24 LA 316
map
|
Contractor: James Construction Group LLC |
Miles:
| 0.26 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2020-11-04 |
$28,190,892 |
Spring of 2025 |
LA 56: Robinson Canal Bridge |
H.002238.6-R1 - New location/replacement of bridge
|
Proj. Engr: Oncale, Jacob |
Route: |
LA 56
map
|
Contractor: Sealevel Construction Inc. |
Miles:
| 0.17 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-07-24 |
$7,198,735 |
Fall of 2024 |
Bayou Terrebonne Eastside Sidewalk Project |
H.007604.6 - Sidewalks/bike paths
|
Proj. Engr: Caillouet, Melanie |
Route: |
LA 24
map
|
Contractor: Hard Rock Construction LLC |
Miles:
| 0.38 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2012-03-29 |
$192,087 |
Summer of 2012 |
Houma Twin Span Br Exp. Joint Rpr |
H.013317.6 - Bridges reconditioned
|
Proj. Engr: Rogers, Chris |
Route: |
LA 24
map
|
Contractor: |
Miles:
| 0.01 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2018-11-21 |
$58,928 |
Beginning of 2019 |
LA 24 Nb: La 664 - St. George Rd. |
H.014070.6 - Asphalt overlay of asphalt pavement
|
Proj. Engr: Oncale, Jacob |
Route: |
LA 24
map
|
Contractor: Huey P. Stockstill, LLC |
Miles:
| 10.61 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-07-05 |
$5,874,838 |
Spring of 2024 |
LA 661: La 315 - La 659 |
H.014085.6 - Asphalt overlay of asphalt pavement
|
Proj. Engr: Oncale, Jacob |
Route: |
LA 661
map
|
Contractor: Huey P. Stockstill, LLC |
Miles:
| 2.61 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-05-01 |
$4,989,246 |
Summer of 2024 |
LA 661: Houma Nav Mb Electrical Repair |
H.014406.6-R1 - Moveable bridges reconditioned
|
Proj. Engr: Oncale, Jacob |
Route: |
LA 661
map
|
Contractor: Walter J. Barnes Electric Co., |
Miles:
| 0.07 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-05-23 |
$634,000 |
Beginning of 2023 |
US 90 @ Gibson Approach Slab |
H.014604.6 - Asphalt overlay of asphalt pavement
|
Proj. Engr: Rogers, Chris |
Route: |
US 90
map
|
Contractor: |
Miles:
| 0.06 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2021-07-01 |
$319,283 |
Summer of 2021 |
LA 58 Mb Rprs (Sarah & Montegut)(Hbi) |
H.015030.6 - Moveable bridges reconditioned
|
Proj. Engr: Burgess, Matthew |
Route: |
LA 58
map
|
Contractor: Reliant Industrial Solutions L |
Miles:
| 0.05 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-09-19 |
$419,800 |
Summer of 2024 |
District 02
No districtwide projects.