Projects Under Construction

District 02

    Updated 9 Oct 2026

Districtwide Projects

Jefferson Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 45 Drainage Improvements
H.002267.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Zzzz Weber, Alan Route: LA 45 map
Contractor: Barriere Construction Co., LLC Miles: 1.01
Work Order Date Contract Amount Estimated Completion Date
2012-04-09 $363,642 Summer of 2012


LA 3134 (Intracoastal Canal-La 45)
H.002953.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Zzzz Weber, Alan Route: LA 3134 map
Contractor: Barriere Construction Co., LLC Miles: 6.70
Work Order Date Contract Amount Estimated Completion Date
2013-11-23 $2,967,635 Fall of 2014


Earhart at Dakin
H.002956.6 - Concrete new pavement
Proj. Engr: Hanifa, Khalil Route: LA 3139 map
Contractor: James Construction Group LLC Miles: 0.01
Work Order Date Contract Amount Estimated Completion Date
2026-07-07 $8,512,926 Fall of 2027


Airline at Clearview Intersection Improv
H.004424.6-R1 - Asphalt overlay of asphalt pavement
Proj. Engr: Zzzz Duplantis, Michael Route: US 61 LA 3152 map
Contractor: Magee Excavation & Development Miles: 0.72
Work Order Date Contract Amount Estimated Completion Date
2021-07-30 $6,509,674 Beginning of 2023


La302: Barataria Br Tug Hit
H.009184-R1 - Moveable bridges reconditioned
Proj. Engr: Zzzz Guidry, John Route: LA 302 map
Contractor: Boh Bros. Construction Co., Ll Miles: 0.10
Work Order Date Contract Amount Estimated Completion Date
2011-07-28 $1,065,897 Fall of 2011


LA 49/Williams Blvd Corridor Improvs.
H.010570.6 - Sidewalks/bike paths
Proj. Engr: Rizzo, Kevin Route: LA 49 map
Contractor: Barriere Construction Co., LLC Miles: 1.15
Work Order Date Contract Amount Estimated Completion Date
2023-09-11 $15,200,587 Summer of 2026


LA 541 Embankment Repair
H.010621.6 - Embankment repair
Proj. Engr: Capote, Nelson Route: LA 541 map
Contractor: Hard Rock Construction LLC Miles: 0.15
Work Order Date Contract Amount Estimated Completion Date
2013-01-11 $132,590 Summer of 2013


Control Section 249-01 La 45: Barataria Blvd Beautification
H.010644.6 - Landscaping
Proj. Engr: Capote, Nelson Route: LA 45 map
Contractor: Baton Rouge Turf & Landscape, Miles: 1.80
Work Order Date Contract Amount Estimated Completion Date
2013-02-06 $45,000 Spring of 2013


Jefferson Wb Miss River Mu Path 3b + 3c
H.011805.6 - Sidewalks/bike paths
Proj. Engr: Zeringue, Matthew Route: LA 541 map
Contractor: Kort's Construction Services, Miles: 0.23
Work Order Date Contract Amount Estimated Completion Date
2026-03-16 $1,190,330 Beginning of 2027


LA 23: Intersection Imp @ Gretna Blvd
H.012596.6 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Hollier, Corbett Route: LA 23 map
Contractor: Barber Bros. Contracting Co., Miles: 0.16
Work Order Date Contract Amount Estimated Completion Date
2020-03-23 $74,971 Summer of 2020


LA 466: 5th Street Improvements (Gretna)
H.012885.6-R1 - Sidewalks/bike paths
Proj. Engr: Schenck, Daniel Route: LA 466 map
Contractor: LA Contracting Enterprise, L.L Miles: 0.58
Work Order Date Contract Amount Estimated Completion Date
2025-04-14 $8,457,507 End of 2026


Gretna Downtown Pedestrian Improvements
H.013090.6 - Planning study
Proj. Engr: Branch, Tyler Route: LA 18 map
Contractor: Buck Town Contractors & Co. Miles: 0.05
Work Order Date Contract Amount Estimated Completion Date
2024-02-26 $1,652,347 Fall of 2024


LA 302: Kerner Ferry Bridge Repairs Ph 2
H.014587.6-R1 - Moveable bridges reconditioned
Proj. Engr: Zzzz Morvant, Chris Route: LA 302 map
Contractor: Miles: 0.12
Work Order Date Contract Amount Estimated Completion Date
2021-07-16 $5,193,245 Summer of 2022


LA 3139: Eb Ramp Over La 3152 Bridge Repair
H.015004.6 - Bridges reconditioned
Proj. Engr: Hanifa, Khalil Route: LA 3139 map
Contractor: C.E.C., Inc. Miles: 0.06
Work Order Date Contract Amount Estimated Completion Date
2025-06-24 $254,486 Fall of 2025


LA 302: Bayou Barataria Mb Repl Phase 1
H.015028.6 - New location/replacement of moveable bridge
Proj. Engr: Wetekamm, Fred Route: LA 302-P LA 302 map
Contractor: Boh Bros. Construction Co., Ll Miles: 0.56
Work Order Date Contract Amount Estimated Completion Date
2023-02-17 $57,940,938 Spring of 2028


LA 3152: Huey P - Airline Dr
H.015780.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Nguyen, VI Route: LA 3152 map
Contractor: Madden Gulf Coast, LLC Miles: 1.70
Work Order Date Contract Amount Estimated Completion Date
2025-04-18 $4,863,929 Summer of 2026


US 61: Causeway - David
H.015781.6 - Asphalt surface treatment
Proj. Engr: Hanifa, Khalil Route: US 61 map
Contractor: Boh Bros. Construction Co., Ll Miles: 3.47
Work Order Date Contract Amount Estimated Completion Date
2025-12-18 $4,339,471 Fall of 2026


LA 49: W Metairie Ave - US 61
H.015818.6 - Asphalt overlay of concrete pavement
Proj. Engr: Nguyen, VI Route: LA 49 map
Contractor: Barber Bros. Contracting Co., Miles: 0.73
Work Order Date Contract Amount Estimated Completion Date
2025-01-22 $2,249,732 Spring of 2026


US 90: Hp Long Bridge (No) - Joint Repairs
H.015910.6 - Bridges reconditioned
Proj. Engr: Hanifa, Khalil Route: US 90 map
Contractor: C.E.C., Inc. Miles: 0.45
Work Order Date Contract Amount Estimated Completion Date
2025-06-05 $486,169 Beginning of 2026


LA 18: US 90 - St Charles P/L
H.016222.6 - Asphalt surface treatment
Proj. Engr: Troendle, Shane Route: LA 18 map
Contractor: Alonso LLC Miles: 8.17
Work Order Date Contract Amount Estimated Completion Date
2026-05-26 $351,350 Fall of 2026


LA 23/428 Franklin St Patching
H.016337.6 - Concrete pavement rehab-grinding/dowell retrofit/should drain install
Proj. Engr: Schenck, Daniel Route: LA 23 LA 428 map
Contractor: Miles: 1.26
Work Order Date Contract Amount Estimated Completion Date
2025-03-31 $365,266 Spring of 2025


US 90: Avondale Ped Impr
H.016366.6 - Sidewalks/bike paths
Proj. Engr: Troendle, Shane Route: US 90 map
Contractor: Kass Bros. Inc. Miles: 1.46
Work Order Date Contract Amount Estimated Completion Date
2026-04-13 $1,376,325 Spring of 2027


District 02: Pavement Markers Repl
H.016443.6 - Striping and pavement markers
Proj. Engr: Troendle, Shane Route: I-10 I-910 map
Contractor: Southern Synergy LLC Miles: 107.34
Work Order Date Contract Amount Estimated Completion Date
2025-11-10 $4,318,295 Summer of 2028


LA 1: Plum Ln - Caminada Bay Bridge
H.016602.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Usey, Brandon Route: LA 1 map
Contractor: Huey P. Stockstill, LLC Miles: 2.24
Work Order Date Contract Amount Estimated Completion Date
2026-04-20 $3,394,676 Fall of 2026


4th St. - US 90b & Weyer Ave. - La 560-2
062-01-0031-R1 - Asphalt overlay of asphalt pavement
Proj. Engr: Capote, Nelson Route: LA 18 map
Contractor: Barriere Construction Co., LLC Miles: 0.50
Work Order Date Contract Amount Estimated Completion Date
2011-02-07 $1,960,756 Summer of 2011


Lafourche Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

Canal Street Bridge Pedestrian Crossing
H.001486.6 - Sidewalks/bike paths
Proj. Engr: Zzzz Badeaux, Al Route: LA 20 map
Contractor: Sealevel Construction Inc. Miles: 0.07
Work Order Date Contract Amount Estimated Completion Date
2013-05-23 $563,415 Spring of 2014


LA 1: Leeville to Golden Meadow (Phase 2)
H.008145.6 - New location/replacement of bridge
Proj. Engr: Gisclair, Gary Route: LA 1 LA 3235 map
Contractor: James Construction Group LLC Miles: 8.70
Work Order Date Contract Amount Estimated Completion Date
2022-02-08 $465,926,408 Spring of 2028


LA 1 Toll Plaza Improvements (Electrical)
H.009858.6 - Miscellaneous
Proj. Engr: Zzzz Gisclair, Gary Route: LA 1
Contractor: Ernest P. Breaux Electrical, I Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2012-03-19 $429,065 Spring of 2012


Airport Connector Road and Bridge
H.011915.6 - Concrete new pavement
Proj. Engr: Picciola, Joe Route: LA 3235 LA 1 map
Contractor: Sealevel Construction Inc. Miles: 1.13
Work Order Date Contract Amount Estimated Completion Date
2021-08-08 $31,110,991 Fall of 2025


LA 308 Resurfacing Near Mccloud Rd.
H.014376.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Usey, Brandon Route: LA 308 map
Contractor: Miles: 0.05
Work Order Date Contract Amount Estimated Completion Date
2021-01-14 $46,949 Summer of 2021


La316&la24:mill,Ovrly,Grade Raising,Hfst
H.014802.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Usey, Brandon Route: LA 316 map
Contractor: Barriere Construction Co., LLC Miles: 7.75
Work Order Date Contract Amount Estimated Completion Date
2025-08-18 $9,146,439 Spring of 2027


La1 Toll Facility Electrical Repairs
H.014972.6 - ITS and emergency operations
Proj. Engr: Usey, Brandon Route: LA 1 map
Contractor: Enfra Ep Breaux, LLC Miles: 0.02
Work Order Date Contract Amount Estimated Completion Date
2023-02-22 $242,963 Spring of 2023


La1&657:icww&byu Lafourche Mb Rprs(Hbi)
H.014998.6 - Moveable bridges reconditioned
Proj. Engr: Burgess, Matthew Route: LA 1 LA 657 map
Contractor: C.E.C., Inc. Miles: 0.44
Work Order Date Contract Amount Estimated Completion Date
2023-07-03 $1,774,741 Summer of 2024


LA 1, La 182, La 654, La 655 Mb Rprs (Hbi)
H.015032.6 - Moveable bridges reconditioned
Proj. Engr: Usey, Brandon Route: LA 182 LA 1 map
Contractor: C.E.C., Inc. Miles: 0.21
Work Order Date Contract Amount Estimated Completion Date
2023-10-30 $559,887 Fall of 2024


La308 & 3162 Mb Rprs (Gldn Mdw & Gall) (Hbi)
H.015034.6 - Moveable bridges reconditioned
Proj. Engr: Usey, Brandon Route: LA 308 LA 3162 map
Contractor: Reliant Industrial Solutions L Miles: 0.09
Work Order Date Contract Amount Estimated Completion Date
2023-10-25 $1,962,911 Spring of 2025


LA 1 Toll System O&m
H.015135.6 - Miscellaneous
Proj. Engr: Heraty, Stephen P. Route: LA 1 map
Contractor: Plenary Infrastructure Belle C Miles: 0.20
Work Order Date Contract Amount Estimated Completion Date
2022-09-27 $9,610,753 Beginning of 2028


LA 1 Culvert Repair at Log Mile 2.344
H.015751 -
Proj. Engr: Usey, Brandon Route: LA 1 map
Contractor: Byron E. Talbot Contractor, In Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2024-01-29 $68,205 Beginning of 2024


D02 Painted Traffic Striping 2023
H.015770 - Striping and pavement markers
Proj. Engr: Usey, Brandon Route: LA 316 LA 3087 map
Contractor: Southern Synergy LLC Miles: 4.95
Work Order Date Contract Amount Estimated Completion Date
2024-05-06 $107,980 Spring of 2024


LA 3185: La 1 - La 20
H.016137.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Usey, Brandon Route: LA 3185 map
Contractor: Huey P. Stockstill, LLC Miles: 5.32
Work Order Date Contract Amount Estimated Completion Date
2026-02-23 $2,741,956 Beginning of 2027


LA 1: La 3162 - Intracoastal Br. & La 657
H.016201.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Usey, Brandon Route: LA 1 map
Contractor: Huey P. Stockstill, LLC Miles: 9.14
Work Order Date Contract Amount Estimated Completion Date
2026-04-27 $6,576,838 Beginning of 2028


Orleans Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

I-610: (I-10 to St. Bernard Ave.)
H.003134.6-R1 - Asphalt overlay of concrete pavement
Proj. Engr: Guilbeau, Justin Route: I-610 map
Contractor: Barriere Construction Co., LLC Miles: 2.58
Work Order Date Contract Amount Estimated Completion Date
2013-05-21 $6,258,848 Spring of 2014


Ihnc and Algiers Cutoff Bridge Rehab
H.003182.6-R1 - Bridges reconditioned
Proj. Engr: Guilbeau, Justin Route: I-10 LA 407 map
Contractor: Gibson & Associates Inc. Miles: 3.82
Work Order Date Contract Amount Estimated Completion Date
2016-02-26 $10,376,224 Summer of 2017


US 90 Bus: Cccd - Sign Installations
H.005889.6 - Signing
Proj. Engr: Zzzz Boyle, Scott Route: I-910 map
Contractor: Traffic Solutions, Inc. Miles: 0.25
Work Order Date Contract Amount Estimated Completion Date
2013-09-27 $196,862 Spring of 2014


I-10: No Terminal R/R Br Painting & Cleaning
H.009393.6 - Bridge painting
Proj. Engr: Guilbeau, Justin Route: I-10 map
Contractor: Astron General Contracting, In Miles: 0.01
Work Order Date Contract Amount Estimated Completion Date
2012-09-27 $921,128 Spring of 2013


LA 47: I-10 N. Service Rd. - Bullard Ave.
H.009663.6 - Concrete pavement rehab-grinding/dowell retrofit/should drain install
Proj. Engr: Guilbeau, Justin Route: LA 47 map
Contractor: Roubion Civil Construction, Ll Miles: 2.89
Work Order Date Contract Amount Estimated Completion Date
2017-06-05 $2,273,814 Summer of 2018


Us90z (Bodenger Blvd - Stumpf Blvd)
H.010634.6-R2 - Signing
Proj. Engr: Hollier, Corbett Route: I-910 map
Contractor: C.E.C., Inc. Miles: 2.96
Work Order Date Contract Amount Estimated Completion Date
2021-10-18 $10,883,000 Beginning of 2025


I-10: Cbd 2 Carrollton - Lafitte Ave
H.011220.6 - Signing
Proj. Engr: Hamide, Mahmoud Route: I-10 map
Contractor: C.E.C., Inc. Miles: 2.86
Work Order Date Contract Amount Estimated Completion Date
2019-06-13 $13,610,030 Beginning of 2024


I-10: N.O. Cbd 5 (I-510 to End of Twin Span)
H.011223.6 - Signing
Proj. Engr: Hamide, Mahmoud Route: I-10 map
Contractor: Traffic Commander, LLC Miles: 14.07
Work Order Date Contract Amount Estimated Completion Date
2023-01-23 $5,258,623 Beginning of 2026


I-10 E at I-510 Mm 247 Emergency Barrier Wall Repair
H.011712.6 - Bridges reconditioned
Proj. Engr: Guilbeau, Justin Route: I-10 map
Contractor: D. O'brian Construction, LLC Miles: 0.10
Work Order Date Contract Amount Estimated Completion Date
2015-04-02 $315,993 Summer of 2015


LA 39: Judge Seeber Br Mech Rehab (Hbi)
H.012956.6 - Moveable bridges reconditioned
Proj. Engr: Hamide, Mahmoud Route: LA 39 map
Contractor: C.E.C., Inc. Miles: 0.24
Work Order Date Contract Amount Estimated Completion Date
2020-04-27 $1,881,701 Beginning of 2021


I-10: I-610e Interchange Lighting
H.013617.6 - Roadway lighting
Proj. Engr: Roberts, Joseph Route: I-10 I-610 map
Contractor: Diamond Electrical Co., Inc. Miles: 1.20
Work Order Date Contract Amount Estimated Completion Date
2022-09-23 $5,060,360 Summer of 2025


US 61 @ I-10 Eb Off Ramp Ped Impr (No)
H.013719.6 - Planning study
Proj. Engr: Collier, Zachary Route: US 61 map
Contractor: Command Construction Industrie Miles: 0.35
Work Order Date Contract Amount Estimated Completion Date
2025-10-15 $647,836 Spring of 2026


LA 428: Gen Degaulle - Old Behrman
H.013753.6 - Planning study
Proj. Engr: Branch, Tyler Route: LA 428 map
Contractor: Buck Town Contractors & Co. Miles: 0.79
Work Order Date Contract Amount Estimated Completion Date
2026-03-14 $765,432 Fall of 2026


I-10: Franklin Ave - I-510
H.014064.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Hamide, Mahmoud Route: I-10 map
Contractor: Boh Bros. Construction Co., Ll Miles: 8.71
Work Order Date Contract Amount Estimated Completion Date
2025-08-25 $17,245,809 Spring of 2028


I-610: Orleans P/L - Franklin Ave
H.014065.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Robert, Joseph Route: I-610 map
Contractor: Madden Gulf Coast, LLC Miles: 4.88
Work Order Date Contract Amount Estimated Completion Date
2026-03-01 $9,522,008 Beginning of 2028


US 90: Napoleon - US 90b
H.015782.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Hamide, Mahmoud Route: US 90 map
Contractor: Barriere Construction Co., LLC Miles: 1.14
Work Order Date Contract Amount Estimated Completion Date
2025-10-01 $3,506,717 Fall of 2026


LA 3139: Earhart Approach - Monroe St
H.015806.6 - Portland Cement Pavement patch
Proj. Engr: Hamide, Mahmoud Route: LA 3139 map
Contractor: Buck Town Contractors & Co. Miles: 0.37
Work Order Date Contract Amount Estimated Completion Date
2026-03-03 $485,855 Summer of 2026


I-10 @ US 61 Ramp Drainage
H.016155.6 - Drainage
Proj. Engr: Hamide, Mahmoud Route: I-10 map
Contractor: Miles: 0.07
Work Order Date Contract Amount Estimated Completion Date
2026-07-01 $110,000 Fall of 2026


LA 428(Gen Degaulle): Marr & Wall Bl Int
H.016361.6 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Schenck, Daniel Route: LA 428 I-910 map
Contractor: Command Construction Industrie Miles: 0.49
Work Order Date Contract Amount Estimated Completion Date
2026-03-14 $912,322 Spring of 2027


I-510: I-10 - Paris Rd Br Pave Mkgs
H.016430.6 - Striping and pavement markers
Proj. Engr: Robert, Joseph Route: I-510 map
Contractor: Southern Synergy LLC Miles: 3.43
Work Order Date Contract Amount Estimated Completion Date
2025-12-20 $471,943 Spring of 2026


US 90: Gno No. 2 Bridge Repair
H.016475.6 - Bridges reconditioned
Proj. Engr: Hamide, Mahmoud Route: I-910 map
Contractor: Southern Road & Bridge, LLC Miles: 2.26
Work Order Date Contract Amount Estimated Completion Date
2026-08-18 $6,545,211 Fall of 2028


Judge Seeber Bridge Repairs
046-31-0053 - Moveable bridges reconditioned
Proj. Engr: Zzzz Guidry, John Route: LA 39 map
Contractor: Boh Bros. Construction Co., LLC. Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2009-06-26 $8,936,932 Fall of 2010


Leveling Approach Slabs and Improvements
409-02-0018 - Asphalt overlay of asphalt pavement
Proj. Engr: Capote, Nelson Route: LA 406 map
Contractor: Barriere Construction Co., LLC Miles: 0.41
Work Order Date Contract Amount Estimated Completion Date
2011-08-11 $568,388 Fall of 2011


Pontchartrain Pump Station Repairs Due to Hurricane Katrina
450-90-0210 - Drainage
Proj. Engr: Zzzz Wetekamm, Fred Route: I-10
Contractor: Industrial & Mechanical Contr. Ll Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2008-08-04 $1,597,784 End of 2009


Drainage Improvements on I-10
450-90-0242 - Drainage
Proj. Engr: Zzzz Zeringue, Kirk Route: I-10 map
Contractor: Rcs Contractors, Inc. Miles: 5.00
Work Order Date Contract Amount Estimated Completion Date
2011-08-12 $267,345 Summer of 2011


Administration Building Expansion
610-01-0022 - Buildings and grounds excluding rest areas
Proj. Engr: Skoien, Richard W. Route:
Contractor: Jaroy Construction, Inc. Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2008-02-11 $3,799,661 End of 2009


Plaquemines Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

Judge Perez Br. Wirerope Repl., Gearbox & Mach. House Repair
H.001390.6 - Moveable bridges reconditioned
Proj. Engr: Capote, Nelson Route: LA 23 map
Contractor: C.E.C., Inc. Miles: 0.01
Work Order Date Contract Amount Estimated Completion Date
2011-10-24 $968,252 Beginning of 2012


LA 406: Roundabout at Fe Hebert
H.008220.6 - Asphalt widening and overlay
Proj. Engr: Collier, Zachary Route: LA 406 map
Contractor: Kort's Construction Services, Miles: 0.37
Work Order Date Contract Amount Estimated Completion Date
2026-05-25 $3,191,956 Spring of 2027


LA 23: Diamond Rd - 665 Ft S Martin La
H.009223.6-R1 - Concrete pavement rehab-grinding/dowell retrofit/should drain install
Proj. Engr: Capote, Nelson Route: LA 23 map
Contractor: Barriere Construction Co., LLC Miles: 0.71
Work Order Date Contract Amount Estimated Completion Date
2012-10-25 $329,535 Beginning of 2013


LA 23: Russell Dr - Highway 11
H.014844.6 - Portland Cement Pavement patch
Proj. Engr: Hollier, Corbett Route: LA 23 map
Contractor: Boh Bros. Construction Co., Ll Miles: 4.35
Work Order Date Contract Amount Estimated Completion Date
2024-04-15 $149,409 Beginning of 2026


LA 39 Raising: White Ditch to Phoenix
H.016371.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Gomez, Alana Route: LA 39 map
Contractor: Madden Gulf Coast, LLC Miles: 5.06
Work Order Date Contract Amount Estimated Completion Date
2026-05-08 $3,839,837 Spring of 2027


LA 23: Russell Drive - Hwy 11
H.016464.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Schenck, Daniel Route: LA 23 map
Contractor: Boh Bros. Construction Co., Ll Miles: 4.35
Work Order Date Contract Amount Estimated Completion Date
2026-01-19 $7,175,265 Beginning of 2028


Emergency Dredging of Ostrica Canal
704-38-0011 - Miscellaneous
Proj. Engr: Capote, Nelson Route:
Contractor: Grillot Construction LLC Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2008-02-11 $1,058,050 Beginning of 2009


St. Bernard Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 46: Orleans P/L - Paris Rd
H.010406.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Guilbeau, Justin Route: LA 46 map
Contractor: Barber Bros. Contracting Co., Miles: 2.90
Work Order Date Contract Amount Estimated Completion Date
2016-02-15 $3,870,157 Summer of 2017


LA 39: X-Drain Repair @ Debouchel Canal
H.012292.6 - Drainage
Proj. Engr: Guilbeau, Justin Route: LA 39 map
Contractor: Cheniere Construction, Inc. Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2016-02-16 $48,861 Spring of 2016


LA 39 and La 46 Crossdrain Replacements
H.012804.6-R1 - Drainage
Proj. Engr: Guilbeau, Justin Route: LA 46 LA 39 map
Contractor: Boh Bros. Construction Co., Ll Miles: 0.01
Work Order Date Contract Amount Estimated Completion Date
2017-03-06 $579,631 Summer of 2017


LA 39: W. Judge Perez Dr. Enhancements
H.014643.6 - Sidewalks/bike paths
Proj. Engr: O'Brien, Alec Carter Route: LA 39 map
Contractor: Beverly Construction Co. LLC Miles: 1.07
Work Order Date Contract Amount Estimated Completion Date
2026-04-10 $1,093,835 Summer of 2027


LA 39 Patching: Norton Ave - Paris Rd
H.015809.6 - Concrete pavement rehab-grinding/dowell retrofit/should drain install
Proj. Engr: Robert, Joseph Route: LA 39 map
Contractor: Triumph Construction, LLC Miles: 2.02
Work Order Date Contract Amount Estimated Completion Date
2026-01-09 $1,561,319 Beginning of 2027


LA 39: 155' S. La 46 - Floodwall
H.015881.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Robert, Joseph Route: LA 39 map
Contractor: Madden Gulf Coast, LLC Miles: 1.34
Work Order Date Contract Amount Estimated Completion Date
2025-11-14 $1,002,705 Spring of 2026


Yscloskey Bridge Rehabilitation- Hurricane Katrina
284-02-0035 - Moveable bridges reconditioned
Proj. Engr: Zzzz Wetekamm, Fred Route: map
Contractor: Coastal Bridge Co., L.L.C. Miles: 0.34
Work Order Date Contract Amount Estimated Completion Date
2007-01-22 $2,724,013 Spring of 2008


St. Charles Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 3127 Eb: 0.52 Mi W La 3141 - I-310
H.010416.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Troendle, Shane Route: LA 3127 map
Contractor: Barriere Construction Co., LLC Miles: 7.75
Work Order Date Contract Amount Estimated Completion Date
2025-11-03 $6,171,226 Fall of 2026


D02 Bridge Rail Repair 2023
H.015771 - Miscellaneous
Proj. Engr: Zzzz Herrington, Benny Route: LA 631 US 90 map
Contractor: Tlp Construction Co. LLC Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2024-03-25 $117,497 Spring of 2024


I-310 N.B., S.B. & Ramp Bearing Pad & Joint Seal Replacement
450-36-0035 - Bridges reconditioned
Proj. Engr: Zzzz Weber, Alan Route:
Contractor: Gibson & Associates Inc. Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2011-07-17 $1,356,720 Spring of 2012


Terrebonne Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 24 & La 316: Company Canal Bridge
H.001498.6 - New location/replacement of bridge
Proj. Engr: Hunt, Dalton Route: LA 24 LA 316 map
Contractor: James Construction Group LLC Miles: 0.26
Work Order Date Contract Amount Estimated Completion Date
2020-11-04 $31,150,446 Spring of 2027


Bayou Terrebonne Eastside Sidewalk Project
H.007604.6 - Sidewalks/bike paths
Proj. Engr: Zzzz Caillouet, Melani Route: LA 24 map
Contractor: Hard Rock Construction LLC Miles: 0.38
Work Order Date Contract Amount Estimated Completion Date
2012-03-29 $192,087 Summer of 2012


LA 24: Terrebonne P/L - Downtown Ct
H.010411.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Burgess, Matthew Route: LA 24 map
Contractor: Huey P. Stockstill, LLC Miles: 9.10
Work Order Date Contract Amount Estimated Completion Date
2025-07-14 $6,836,797 Beginning of 2027


La56&57:boudreaux C. & Byu Dulac Mb Rprs
H.014999.6 - Moveable bridges reconditioned
Proj. Engr: Burgess, Matthew Route: LA 57 LA 56 map
Contractor: Coastal Contractors, LLC Miles: 0.11
Work Order Date Contract Amount Estimated Completion Date
2023-10-30 $1,605,742 Beginning of 2025


LA 315 & La 661 Mb Rprs(Hbi)
H.015031.6 - Moveable bridges reconditioned
Proj. Engr: Burgess, Matthew Route: LA 315 LA 661 map
Contractor: Reliant Industrial Solutions L Miles: 0.54
Work Order Date Contract Amount Estimated Completion Date
2024-01-29 $1,241,148 Beginning of 2025


LA 24: La 24 Over Intracoastal Waterway Steel Girder Repairs
H.015115.6 - Bridges reconditioned
Proj. Engr: Burgess, Matthew Route: LA 24 map
Contractor: Tlp Construction Co. LLC Miles: 0.73
Work Order Date Contract Amount Estimated Completion Date
2026-01-16 $1,195,654 Summer of 2026


LA 182: La 311 - La 24
H.015801.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Burgess, Matthew Route: LA 182 map
Contractor: Huey P. Stockstill, LLC Miles: 1.28
Work Order Date Contract Amount Estimated Completion Date
2026-02-23 $1,764,899 Fall of 2026


LA 315: Theriot Water Twr - Tommy Darcey Br
H.015805.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Burgess, Matthew Route: LA 315 map
Contractor: Huey P. Stockstill, LLC Miles: 4.06
Work Order Date Contract Amount Estimated Completion Date
2026-01-05 $1,846,580 Fall of 2026


LA 3040: La 661 - 600' S Hollywood
H.015819.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Burgess, Matthew Route: LA 3040 map
Contractor: Gulf States Services, LLC Miles: 3.60
Work Order Date Contract Amount Estimated Completion Date
2026-03-23 $4,150,545 Spring of 2027


District 02

No districtwide projects.