Projects Under Construction

District 03

    Updated 22 Sep 2023

Districtwide Projects

Acadia Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

I-10: Cable Barrier (Lafayette/Acadia)
H.010962.6-R1 - Miscellaneous
Proj. Engr: Ronkartz, Michael Route: I-10 map
Contractor: Patriot Construction and Indus Miles: 41.11
Work Order Date Contract Amount Estimated Completion Date
2021-05-27 $14,664,156 Spring of 2023


I-10: Jeff Dav Pl - I-49 (Ogfc/Slab Repair)
H.012174.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Ronkartz, Michael Route: I-10 map
Contractor: Gilchrist Construction Company Miles: 37.21
Work Order Date Contract Amount Estimated Completion Date
2023-09-13 $78,894,247 Spring of 2025


LA 98: La 35 - Llama Rd
H.013790.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Ronkartz, Michael Route: LA 98 map
Contractor: Elliott Construction, LLC Miles: 1.28
Work Order Date Contract Amount Estimated Completion Date
2023-09-01 $1,789,207 Spring of 2024


LA 35: N. Jct. La 98 - La 365
H.015094.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Ronkartz, Michael Route: LA 35 map
Contractor: Glenn Lege Construction LLC Miles: 6.82
Work Order Date Contract Amount Estimated Completion Date
2023-07-13 $8,244,809 Beginning of 2025


LA 13:1.023 Mi N La 92-Local Rd (Lovell)
H.015095.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Ronkartz, Michael Route: LA 13 map
Contractor: Prairie Contractors LLC Miles: 4.08
Work Order Date Contract Amount Estimated Completion Date
2023-04-15 $4,256,279 Fall of 2023


Evangeline Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 1165: La 29 - La 104
H.014488.6 - Asph concrete ovly over in place stabilized/cement treated base course
Proj. Engr: Miller, Sam Route: LA 1165 map
Contractor: Prairie Contractors LLC Miles: 3.80
Work Order Date Contract Amount Estimated Completion Date
2022-07-11 $4,562,247 Spring of 2023


Iberia Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 86: La 3242 - La 347
H.002762.6 - Asph concrete ovly over in place stabilized/cement treated base course
Proj. Engr: Miller, Daniel Route: LA 86 map
Contractor: Prairie Contractors LLC Miles: 5.37
Work Order Date Contract Amount Estimated Completion Date
2023-01-07 $7,542,632 Spring of 2024


LA 88: Realign Curves In Coteau
H.010922.6 - Miscellaneous
Proj. Engr: Miller, Daniel Route: LA 88 map
Contractor: Glenn Lege Construction LLC Miles: 1.48
Work Order Date Contract Amount Estimated Completion Date
2022-06-17 $4,866,508 Summer of 2023


La87: 0.65 Mi Se La3182-0.07 Mi Se La670
H.012991.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Ray, Nicholaus Route: LA 87 map
Contractor: Barriere Construction Co., LLC Miles: 6.35
Work Order Date Contract Amount Estimated Completion Date
2022-04-08 $4,340,132 Summer of 2023


US 90: La 14 - La 83
H.013265.6 - Concrete pavement rehab-grinding/dowell retrofit/should drain install
Proj. Engr: Miller, Daniel Route: US 90 map
Contractor: Siema Construction, LLC Miles: 2.86
Work Order Date Contract Amount Estimated Completion Date
2022-10-04 $30,850,485 Beginning of 2024


Lafayette Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

I-49 S: Amb Caffery/Us 90 Interchange
H.002868.6 - Asphalt new pavement-new roadway/new alignments
Proj. Engr: Ardoin, Zachary Route: US 90 LA 3073 map
Contractor: Jb James Construction LLC Miles: 3.09
Work Order Date Contract Amount Estimated Completion Date
2022-08-15 $137,276,869 Beginning of 2026


I-49 Interch: La 726/La 98/Pont Des Mouton
H.003459.6 - Miscellaneous
Proj. Engr: Descant, Charles Route: I-49 LA 726 map
Contractor: Progressive Construction Co., Miles: 1.23
Work Order Date Contract Amount Estimated Completion Date
2021-09-13 $5,262,021 Spring of 2023


Lafayette Consolidated Govt Sidewalks
H.006538.6 - Miscellaneous
Proj. Engr: Lacy, Barry Route:
Contractor: Progressive Construction Co., Miles: 1.26
Work Order Date Contract Amount Estimated Completion Date
2023-01-17 $1,609,700 Spring of 2024


US 90: RR Jct - Pinhook, La 92 - La 88
H.009629.6 - Concrete pavement rehab-grinding/dowell retrofit/should drain install
Proj. Engr: Ardoin, Zachary Route: US 167 US 90 map
Contractor: Progressive Construction Co., Miles: 4.63
Work Order Date Contract Amount Estimated Completion Date
2023-08-07 $21,093,972 Spring of 2025


US 90: Cameron St. Overlay
H.011832.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Ronkartz, Michael Route: US 90 map
Contractor: Glenn Lege Construction LLC Miles: 3.35
Work Order Date Contract Amount Estimated Completion Date
2021-08-15 $4,435,543 Fall of 2022


Univ Av Ph1:100 S Rr-500 S 1-10 Eb Rmp
H.013025.6 - Planning study
Proj. Engr: Guidry, Blake Route:
Contractor: Progressive Construction Co., Miles: 1.04
Work Order Date Contract Amount Estimated Completion Date
2023-05-15 $8,665,773 Spring of 2025


I-10 ITS Scott to Lake Charles
H.013256.6 - ITS and emergency operations
Proj. Engr: Robinson, Ronnie Route: I-10 map
Contractor: Ozark Traffic Management, LLC Miles: 57.13
Work Order Date Contract Amount Estimated Completion Date
2022-05-20 $2,596,055 Fall of 2023


LA 93: US 90 - Benoit Patin Rd
H.013360.6 - Asphalt widening and overlay
Proj. Engr: Ardoin, Zachary Route: LA 93 map
Contractor: Siema Construction, LLC Miles: 0.54
Work Order Date Contract Amount Estimated Completion Date
2022-05-23 $2,784,987 Summer of 2023


St. Landry Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 360: Rouge Bayou Bridge Replacement
H.008332.6-R1 - New location/replacement of bridge
Proj. Engr: Fontenot, John B. Route: LA 360 map
Contractor: Merrick, LLC Miles: 0.21
Work Order Date Contract Amount Estimated Completion Date
2021-03-15 $2,645,456 Beginning of 2022


US-190 ITS Deployment
H.011511.6 - ITS and emergency operations
Proj. Engr: Moore, Tony Route: US 190 map
Contractor: Grady Crawford Const. Co., Inc Miles: 42.97
Work Order Date Contract Amount Estimated Completion Date
2019-02-04 $2,867,646 Spring of 2020


LA 10: Palmetto Company Canal Br
H.011808.6 - New location/replacement of bridge
Proj. Engr: Descant, Charles Route: LA 10 map
Contractor: Tl Hawk, LLC Miles: 0.34
Work Order Date Contract Amount Estimated Completion Date
2021-09-10 $4,993,947 Beginning of 2023


U.S. 190: Market - Court, Sidewalks
H.011844.6-R1 - Sidewalks/bike paths
Proj. Engr: Jarrell III, William Route: US 190 map
Contractor: Briggs Brothers Enterprises Co Miles: 0.08
Work Order Date Contract Amount Estimated Completion Date
2023-06-05 $512,683 Fall of 2023


US 190 Eb & Wb: Wallior St - La 742
H.013198.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Descant, Charles Route: US 190 map
Contractor: Prairie Contractors LLC Miles: 6.22
Work Order Date Contract Amount Estimated Completion Date
2020-12-22 $11,433,683 Spring of 2023


LA 358: La 357 - La 182
H.014832.6 - Asph concrete ovly over in place stabilized/cement treated base course
Proj. Engr: Descant, Charles Route: LA 358 map
Contractor: Elliott Construction, LLC Miles: 3.46
Work Order Date Contract Amount Estimated Completion Date
2023-06-23 $6,459,338 Summer of 2024


St. Martin Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

I-10: La 328 to La 347
H.010601.6 - Asphaltic concrete overlay of rubblized pavement
Proj. Engr: Dore, Haley Route: I-10 map
Contractor: Gilchrist Construction Company Miles: 5.37
Work Order Date Contract Amount Estimated Completion Date
2019-10-07 $89,096,268 Summer of 2024


LA 336-1: Bayou Teche Bridge Rehab (Hbi)
H.011485.6 - Bridges reconditioned
Proj. Engr: Dore, Haley Route: LA 336-1 map
Contractor: Coastal Contractors, LLC Miles: 0.23
Work Order Date Contract Amount Estimated Completion Date
2020-06-15 $5,147,970 Beginning of 2022


LA 353: La 94 to Cypress Island Hwy
H.013516.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Dore, Haley Route: LA 353 map
Contractor: Prairie Contractors LLC Miles: 6.57
Work Order Date Contract Amount Estimated Completion Date
2023-01-25 $11,221,472 Spring of 2024


LA 352 Drainage Improvement
H.014415.6 - Drainage
Proj. Engr: Dore, Haley Route: LA 352 I-10 map
Contractor: Merrick, LLC Miles: 1.31
Work Order Date Contract Amount Estimated Completion Date
2023-07-25 $5,844,668 Summer of 2024


LA 347: La 350 - La 351
H.014492.6 - Asph concrete ovly over in place stabilized/cement treated base course
Proj. Engr: Dore, Haley Route: LA 347 LA 321 map
Contractor: Glenn Lege Construction LLC Miles: 4.27
Work Order Date Contract Amount Estimated Completion Date
2023-09-14 $11,955,837 Beginning of 2026


LA 31: 0.899 Mi S La 92-0.15 Mi N of N La 96
H.014576.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Dore, Haley Route: LA 31 map
Contractor: Glenn Lege Construction LLC Miles: 3.04
Work Order Date Contract Amount Estimated Completion Date
2022-07-25 $5,278,802 Summer of 2023


I-10: Atch Basin Speed Enforcement Ph 2
H.015217.6 - Signing
Proj. Engr: Dore, Haley Route: I-10 map
Contractor: Superior Traffic Control, LLC Miles: 17.85
Work Order Date Contract Amount Estimated Completion Date
2023-08-10 $591,040 Spring of 2024


St. Mary Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

Bayou Teche Bridge (Oaklawn)
H.002798.6 - New location/replacement of bridge
Proj. Engr: Ray, Nicholaus Route: LA 323 map
Contractor: Shavers-Whittle Construction L Miles: 0.06
Work Order Date Contract Amount Estimated Completion Date
2016-10-17 $11,400,854 Fall of 2020


LA 182: Berwick Bay Bridge Rehab (Hbi)
H.011487.6-R1 - Bridges reconditioned
Proj. Engr: Ray, Nicholaus Route: LA 182 map
Contractor: Southern Road & Bridge, LLC Miles: 0.71
Work Order Date Contract Amount Estimated Completion Date
2022-10-22 $25,969,337 Beginning of 2025


LA 318: 0.341 Mi Ne of US 90 - La 182
H.015225.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Ray, Nicholaus Route: LA 318 map
Contractor: Glenn Lege Construction LLC Miles: 1.63
Work Order Date Contract Amount Estimated Completion Date
2023-07-06 $1,839,965 Fall of 2023


Vermilion Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

US 167: Access Management (Lft Turn Lns)
H.010353.6 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Moran, Michael Route: US 167 map
Contractor: Glenn Lege Construction LLC Miles: 5.35
Work Order Date Contract Amount Estimated Completion Date
2019-09-09 $18,216,641 Summer of 2024


LA 92: Pavement Preservation
H.013515.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Moran, Michael Route: LA 92 map
Contractor: Glenn Lege Construction LLC Miles: 2.92
Work Order Date Contract Amount Estimated Completion Date
2022-01-17 $4,411,550 Beginning of 2023


LA 330: 1.33 Mi W La 689 - La 331
H.014812.6 - Asph concrete ovly over in place stabilized/cement treated base course
Proj. Engr: Moran, Michael Route: LA 330 map
Contractor: Glenn Lege Construction LLC Miles: 2.75
Work Order Date Contract Amount Estimated Completion Date
2023-06-04 $2,963,004 Fall of 2023


District 03

No districtwide projects.