Projects Under Construction

District 03

    Updated 28 Jun 2022

Districtwide Projects

Acadia Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

Rayne Sidewalks, Ph. II
H.007369.6 - Sidewalks/bike paths
Proj. Engr: Bayard, Brett Route: US 90 LA 35 map
Contractor: B2b Contractors LLC Miles: 0.16
Work Order Date Contract Amount Estimated Completion Date
2021-06-28 $399,606 Fall of 2023


I-10: Cable Barrier (Lafayette/Acadia)
H.010962.6-R1 - Miscellaneous
Proj. Engr: Ronkartz, Michael Route: I-10 map
Contractor: Patriot Construction and Indus Miles: 41.11
Work Order Date Contract Amount Estimated Completion Date
2021-05-27 $14,600,166 Spring of 2023


Dist. 03 Rumblestrips (North)
H.013822.6 - Striping and pavement markers
Proj. Engr: Miller, Sam Route: US 90 map
Contractor: Highway Graphics LLC Miles: 206.63
Work Order Date Contract Amount Estimated Completion Date
2021-05-10 $3,328,871 Beginning of 2023


LA 1107: La 367 - La 1105
H.014478.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Ronkartz, Michael Route: LA 1107 map
Contractor: Elliott Construction, LLC Miles: 1.05
Work Order Date Contract Amount Estimated Completion Date
2022-05-01 $1,733,389 Fall of 2022


Evangeline Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

US 167: La 13 - Rapides Parish Line
H.014561.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Miller, Sam Route: US 167 map
Contractor: Diamond B Construction Co., L. Miles: 9.22
Work Order Date Contract Amount Estimated Completion Date
2022-02-21 $4,947,211 Fall of 2022


Iberia Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 88: Realign Curves In Coteau
H.010922.6 - Miscellaneous
Proj. Engr: Miller, Daniel Route: LA 88 map
Contractor: Glenn Lege Construction LLC Miles: 1.48
Work Order Date Contract Amount Estimated Completion Date
2022-06-17 $4,843,999 Summer of 2023


US 90: Ramps @ La 88 Roundabouts
H.011495.6 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Arceneaux, Mark Route: LA 88 map
Contractor: Glenn Lege Construction LLC Miles: 1.12
Work Order Date Contract Amount Estimated Completion Date
2021-01-22 $6,979,882 Spring of 2023


La87: 0.65 Mi Se La3182-0.07 Mi Se La670
H.012991.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Miller, Daniel Route: LA 87 map
Contractor: Barriere Construction Co., LLC Miles: 6.35
Work Order Date Contract Amount Estimated Completion Date
2022-04-08 $4,301,258 Summer of 2023


Dist. 03 Rumblestrips (South)
H.013823.6 - Striping and pavement markers
Proj. Engr: Ray, Nicholaus Route: LA 182 LA 89 map
Contractor: Highway Graphics LLC Miles: 183.17
Work Order Date Contract Amount Estimated Completion Date
2022-03-17 $4,160,116 Summer of 2023


LA 14 & La 330: Bridge Repairs
H.014539.6 - Moveable bridges reconditioned
Proj. Engr: Moran, Michael Route: LA 14 LA 330 map
Contractor: Coastal Contractors, LLC Miles: 0.40
Work Order Date Contract Amount Estimated Completion Date
2021-09-10 $565,049 Spring of 2022


LA 86 Daspit Br Hydr Cyl Rehab (Hbi)
H.014597.6 - Moveable bridges reconditioned
Proj. Engr: Miller, Daniel Route: LA 86 map
Contractor: Reliant Industrial Solutions L Miles: 0.06
Work Order Date Contract Amount Estimated Completion Date
2021-09-04 $261,894 Beginning of 2022


Lafayette Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

Bayou Parc Perdu and Creek Bridges
H.002151.6 - New location/replacement of bridge
Proj. Engr: Ledoux, Murphy Route: LA 339-S LA 339 map
Contractor: Diamond B Construction Co., L. Miles: 0.48
Work Order Date Contract Amount Estimated Completion Date
2021-07-21 $2,094,914 Fall of 2022


Bayou Vermilion Bridge
H.002735.6 - New location/replacement of bridge
Proj. Engr: Ardoin, Zachary Route: LA 1252 map
Contractor: Merrick, LLC Miles: 0.40
Work Order Date Contract Amount Estimated Completion Date
2020-12-23 $3,867,009 Fall of 2022


I-10: East Jct. I-49 to La 328
H.003003.6-R1 - Asphaltic concrete overlay of rubblized pavement
Proj. Engr: Buckel, Brian Route: I-10 map
Contractor: James Construction Group LLC Miles: 7.11
Work Order Date Contract Amount Estimated Completion Date
2017-04-01 $143,689,895 Beginning of 2023


I-49 Interch: La 726/La 98/Pont Des Mouton
H.003459.6 - Miscellaneous
Proj. Engr: Fontenot, John B. Route: I-49 LA 726 map
Contractor: Progressive Construction Co., Miles: 1.23
Work Order Date Contract Amount Estimated Completion Date
2021-09-13 $4,810,971 End of 2022


US 90: Cameron St. Overlay
H.011832.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Ronkartz, Michael Route: US 90 map
Contractor: Glenn Lege Construction LLC Miles: 3.35
Work Order Date Contract Amount Estimated Completion Date
2021-08-15 $4,516,183 Fall of 2022


LA 98: Roundabout at Mills Street
H.012393.6 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Guidry, Blake Route: LA 98 map
Contractor: Progressive Construction Co., Miles: 0.38
Work Order Date Contract Amount Estimated Completion Date
2022-03-10 $3,115,061 Spring of 2023


LA 182: 1.8 Mi N La 723 - 0.4 Mi S La 98
H.012915.6 - Asphalt widening and overlay
Proj. Engr: Ardoin, Zachary Route: LA 182 map
Contractor: Glenn Lege Construction LLC Miles: 0.95
Work Order Date Contract Amount Estimated Completion Date
2021-08-17 $3,064,409 Beginning of 2022


LA 3073: US 167 - Kaliste Saloom Road
H.012980.6 - Concrete pavement rehab-grinding/dowell retrofit/should drain install
Proj. Engr: Ardoin, Zachary Route: LA 3073 map
Contractor: Siema Construction, LLC Miles: 2.17
Work Order Date Contract Amount Estimated Completion Date
2020-08-02 $7,052,651 Beginning of 2023


I-10 ITS Scott to Lake Charles
H.013256.6 - ITS and emergency operations
Proj. Engr: Smith, Doug Route: I-10 map
Contractor: Ozark Traffic Management, LLC Miles: 57.13
Work Order Date Contract Amount Estimated Completion Date
2022-05-20 $2,596,055 Fall of 2023


LA 93: US 90 - Benoit Patin Rd
H.013360.6 - Asphalt widening and overlay
Proj. Engr: Ardoin, Zachary Route: LA 93 map
Contractor: Siema Construction, LLC Miles: 0.54
Work Order Date Contract Amount Estimated Completion Date
2022-05-23 $2,582,099 Beginning of 2023


St. Landry Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 360: Rouge Bayou Bridge Replacement
H.008332.6-R1 - New location/replacement of bridge
Proj. Engr: Fontenot, John B. Route: LA 360 map
Contractor: Merrick, LLC Miles: 0.21
Work Order Date Contract Amount Estimated Completion Date
2021-03-15 $2,651,928 Beginning of 2022


US-190 ITS Deployment
H.011511.6 - ITS and emergency operations
Proj. Engr: Moore, Tony Route: US 190 map
Contractor: Grady Crawford Const. Co., Inc Miles: 42.97
Work Order Date Contract Amount Estimated Completion Date
2019-02-04 $2,867,646 Spring of 2020


LA 10: Palmetto Company Canal Br
H.011808.6 - New location/replacement of bridge
Proj. Engr: Fontenot, John B. Route: LA 10 map
Contractor: Tl Hawk, LLC Miles: 0.34
Work Order Date Contract Amount Estimated Completion Date
2021-09-10 $4,993,947 Beginning of 2023


US 190 Eb & Wb: Wallior St - La 742
H.013198.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Fontenot, John B. Route: US 190 map
Contractor: Prairie Contractors LLC Miles: 6.22
Work Order Date Contract Amount Estimated Completion Date
2020-12-22 $10,002,838 Fall of 2022


LA 91/13:0.3 Mi W Acad Pl-0.5mi N Acad Pl
H.014202.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Fontenot, John B. Route: LA 91 map
Contractor: Prairie Contractors LLC Miles: 3.41
Work Order Date Contract Amount Estimated Completion Date
2021-05-14 $2,484,881 Beginning of 2022


St. Martin Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

I-10: La 328 to La 347
H.010601.6 - Asphaltic concrete overlay of rubblized pavement
Proj. Engr: Chavez, Christopher Route: I-10 map
Contractor: Gilchrist Construction Company Miles: 5.37
Work Order Date Contract Amount Estimated Completion Date
2019-10-07 $86,976,705 Spring of 2024


LA 336-1: Bayou Teche Bridge Rehab (Hbi)
H.011485.6 - Bridges reconditioned
Proj. Engr: Chavez, Christopher Route: LA 336-1 map
Contractor: Coastal Contractors, LLC Miles: 0.23
Work Order Date Contract Amount Estimated Completion Date
2020-06-15 $5,089,072 Beginning of 2022


I-10: Atchafalaya Brs Navig Light Repl
H.014212.6-R1 - Bridges reconditioned
Proj. Engr: Chavez, Christopher Route: I-10 map
Contractor: Energy Solutions Technology, L Miles: 1.55
Work Order Date Contract Amount Estimated Completion Date
2022-01-25 $1,729,781 Summer of 2022


LA 352 Slide Repair
H.014572.6 - Asph concrete ovly over in place stabilized/cement treated base course
Proj. Engr: Chavez, Christopher Route: LA 352 map
Contractor: Womack and Sons Constr. Group Miles: 1.81
Work Order Date Contract Amount Estimated Completion Date
2022-02-01 $2,729,757 End of 2022


St. Mary Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

Bayou Teche Bridge (Oaklawn)
H.002798.6 - New location/replacement of bridge
Proj. Engr: Ray, Nicholaus Route: LA 323 map
Contractor: Shavers-Whittle Construction L Miles: 0.06
Work Order Date Contract Amount Estimated Completion Date
2016-10-17 $11,370,896 Fall of 2020


US 90: Atchafalaya River Bridge Rehabilitation
H.011494.6-R1 - Bridges reconditioned
Proj. Engr: Moran, Michael Route: US 90 map
Contractor: Seminole Equipment, Inc. Miles: 0.35
Work Order Date Contract Amount Estimated Completion Date
2019-04-05 $13,434,378 Spring of 2023


US 90: Cable Barrier In Assump & St Mary
H.011937.6 - Crash devices
Proj. Engr: Ray, Nicholaus Route: US 90 map
Contractor: Simmons Erosion Control, Inc. Miles: 7.14
Work Order Date Contract Amount Estimated Completion Date
2021-08-23 $857,089 Beginning of 2022


LA 182: 0.45 Mi S La 3069 - La 317
H.012990.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Ray, Nicholaus Route: LA 182 map
Contractor: Huey P. Stockstill, LLC Miles: 4.82
Work Order Date Contract Amount Estimated Completion Date
2021-11-19 $3,081,513 Summer of 2022


Vermilion Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

US 167: Access Management (Lft Turn Lns)
H.010353.6 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Moran, Michael Route: US 167 map
Contractor: Glenn Lege Construction LLC Miles: 5.35
Work Order Date Contract Amount Estimated Completion Date
2019-09-09 $17,974,927 Spring of 2024


LA 13: 2.7 Mi N La 14 - 0.2 Mi N Acadia P/L
H.012099.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Moran, Michael Route: LA 13 map
Contractor: Prairie Contractors LLC Miles: 4.57
Work Order Date Contract Amount Estimated Completion Date
2021-08-30 $2,807,630 Spring of 2022


LA 92: Pavement Preservation
H.013515.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Moran, Michael Route: LA 92 map
Contractor: Glenn Lege Construction LLC Miles: 2.92
Work Order Date Contract Amount Estimated Completion Date
2022-01-17 $3,995,432 Fall of 2022


LA 35: La 82 - La 335
H.014499.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Moran, Michael Route: LA 35 map
Contractor: Glenn Lege Construction LLC Miles: 8.13
Work Order Date Contract Amount Estimated Completion Date
2022-06-10 $1,980,991 Fall of 2022


LA 3147, 319, 1246: Fema Bridge Repairs
H.014540.6 - Moveable bridges reconditioned
Proj. Engr: Moran, Michael Route: LA 3147 LA 319 map
Contractor: Coastal Contractors, LLC Miles: 1.75
Work Order Date Contract Amount Estimated Completion Date
2021-09-10 $502,517 Spring of 2022


District 03

No districtwide projects.