Projects Under Construction

District 62

    Updated 9 Oct 2024

Districtwide Projects

Livingston Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

US 190 & La 1026 (Roundabout)
H.000464.6 - Asphalt widening and overlay
Proj. Engr: Delee, Glenn Route: LA 1026 US 190 map
Contractor: Kort's Construction Services, Miles: 0.48
Work Order Date Contract Amount Estimated Completion Date
2018-04-11 $6,610,414 End of 2019


Juban Rd Widening (I-12 to US 190)
H.000464.6A - Asphalt widening and overlay
Proj. Engr: Delee, Glenn Route: LA 1026 US 190 map
Contractor: Kort's Construction Services, Miles: 0.48
Work Order Date Contract Amount Estimated Completion Date
2024-02-07 $15,642,499 Fall of 2026


Amite R. Br. Near French Settlement
H.002375.6 - New location/replacement of bridge
Proj. Engr: Watson, Christopher Route: LA 16 map
Contractor: Tl Hawk, LLC Miles: 0.87
Work Order Date Contract Amount Estimated Completion Date
2020-02-08 $20,461,673 Spring of 2023


I-12: La 63 - Tangipahoa Parish Line
H.003425.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Watson, Christopher Route: I-12 map
Contractor: Barriere Construction Co., LLC Miles: 16.46
Work Order Date Contract Amount Estimated Completion Date
2021-04-15 $22,279,522 End of 2022


Juban Rd Widening (I-12 to US 190)
H.004634.6 - Concrete new pavement
Proj. Engr: Delee, Glenn Route: LA 1026 map
Contractor: Kcr Contractors, LLC Miles: 0.86
Work Order Date Contract Amount Estimated Completion Date
2019-09-11 $15,287,043 Fall of 2025


LA 1024 Creek Brs. Near Friendship
H.008170.6 - New location/replacement of bridge
Proj. Engr: Watson, Christopher Route: LA 1024 map
Contractor: Hendrick Construction, Inc. Miles: 0.15
Work Order Date Contract Amount Estimated Completion Date
2023-12-31 $1,894,171 Summer of 2024


LA 3002: Access Management
H.011645.6-R1 - Engineering
Proj. Engr: Watson, Christopher Route: LA 3002 map
Contractor: Triumph Construction, LLC Miles: 1.16
Work Order Date Contract Amount Estimated Completion Date
2022-06-16 $4,592,507 Summer of 2023


LA 1026: Roundabout at Buddy Ellis Rd
H.011824.6 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Berner, Darrick Route: LA 1026 map
Contractor: Magee Excavation & Development Miles: 0.29
Work Order Date Contract Amount Estimated Completion Date
2020-02-19 $3,314,066 Fall of 2020


Cook Road Imp: La 16 to Juban Crossing
H.012308.6 - Concrete new pavement
Proj. Engr: Brown, Kresten Route: LA 16 map
Contractor: Richard Price Contracting Co, Miles: 0.91
Work Order Date Contract Amount Estimated Completion Date
2022-05-01 $16,644,219 Summer of 2025


LA 1026: Roundabout @ Eden Church Road
H.012348.6 - Asphalt new pavement-new roadway/new alignments
Proj. Engr: Watson, Christopher Route: LA 1026 map
Contractor: Omega Foundation Services Miles: 0.24
Work Order Date Contract Amount Estimated Completion Date
2023-12-21 $3,061,380 Summer of 2024


LA 16: US 190 - La 1019
H.014482.6 - Concrete pavement rehab-grinding/dowell retrofit/should drain install
Proj. Engr: Berner, Darrick Route: LA 16 map
Contractor: Barber Bros. Contracting Co., Miles: 6.37
Work Order Date Contract Amount Estimated Completion Date
2023-08-18 $15,059,635 Spring of 2026


LA 1019: La 16 - La 447
H.014784.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Berner, Darrick Route: LA 1019 map
Contractor: R.J. Daigle & Sons Contractors Miles: 5.57
Work Order Date Contract Amount Estimated Completion Date
2023-09-21 $8,499,467 Summer of 2024


Dist 62: Raised Rumble Strips Evaluation
H.015690.6 - Striping and pavement markers
Proj. Engr: Watson, Christopher Route: LA 16 LA 1026 map
Contractor: Highway Graphics LLC Miles: 23.25
Work Order Date Contract Amount Estimated Completion Date
2024-08-15 $1,049,975 End of 2024


Port Vincent Br New Grid Floor
H.971897 - Moveable bridges reconditioned
Proj. Engr: Wascom, Kris Route: map
Contractor: Boh Bros. Construction Co., Ll Miles: 0.07
Work Order Date Contract Amount Estimated Completion Date
2012-03-23 $473,316 Spring of 2012


Walker Landscaping Project
268-01-0015 - Miscellaneous
Proj. Engr: Zzzz Hollowell, Clay Route: LA 447 I-12 map
Contractor: Twin Shores Lands. & Const Serv I Miles: 1.30
Work Order Date Contract Amount Estimated Completion Date
2009-03-23 $213,013 Summer of 2009


St. Helena Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 1043: La 10 - La 43
H.014123.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Watson, Christopher Route: LA 1043 map
Contractor: Madden Gulf Coast, LLC Miles: 7.46
Work Order Date Contract Amount Estimated Completion Date
2024-09-01 $5,123,327 Spring of 2025


LA 16: Mcdaniel Rd - Tangipahoa P/L
H.015361.6 - Asph concrete ovly over in place stabilized/cement treated base course
Proj. Engr: Watson, Christopher Route: LA 16 map
Contractor: R.J. Daigle & Sons Contractors Miles: 0.85
Work Order Date Contract Amount Estimated Completion Date
2024-09-05 $1,170,469 End of 2024


St. John Baptist Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

St. John Eb Miss River Trail, Phase 4
H.011845.6 - Sidewalks/bike paths
Proj. Engr: Oustalet, Randy Route: LA 44 map
Contractor: Magee Excavation & Development Miles: 1.14
Work Order Date Contract Amount Estimated Completion Date
2019-04-16 $2,587,920 End of 2022


US 61: Airport Rd - St James P/L
H.014111.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Boutte, Christian Route: US 61 map
Contractor: Madden Gulf Coast, LLC Miles: 5.20
Work Order Date Contract Amount Estimated Completion Date
2024-10-01 $11,469,369 Summer of 2025


St. Tammany Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

Boston Street Beautification
H.000486.6 - Sidewalks/bike paths
Proj. Engr: Zzzz Harper, Daniel Route: US 190-X map
Contractor: Kass Bros. Inc. Miles: 0.47
Work Order Date Contract Amount Estimated Completion Date
2012-09-17 $550,353 Fall of 2013


US 190: La 437 - US 190 Bus (Ph1)
H.001344.6 - Asphalt new pavement-new roadway/new alignments
Proj. Engr: Adams, Kevin Route: US 190 LA 437 map
Contractor: Boh Bros. Construction Co., Ll Miles: 1.18
Work Order Date Contract Amount Estimated Completion Date
2022-06-01 $29,902,776 Beginning of 2024


LA 3241: La 36 to La 435
H.004435.6 - Asphalt new pavement-new roadway/new alignments
Proj. Engr: Hickman, Tommy Jr. Route: LA 3241 map
Contractor: James Construction Group LLC Miles: 8.16
Work Order Date Contract Amount Estimated Completion Date
2021-12-06 $68,170,847 Fall of 2024


Black Bayou Br Near Madisonville
H.008358.6-R1 - New location/replacement of bridge
Proj. Engr: Faucheux, Cody Route: LA 1077 map
Contractor: Shavers-Whittle Construction L Miles: 0.18
Work Order Date Contract Amount Estimated Completion Date
2023-09-18 $4,291,489 Fall of 2024


Abita Springs Town Ctr Sidewalk Lighting
H.009934.6 - Sidewalks/bike paths
Proj. Engr: Martin, David Route:
Contractor: Ernest P. Breaux Electrical, L Miles: 0.69
Work Order Date Contract Amount Estimated Completion Date
2023-12-11 $668,550 Beginning of 2025


I-12: La 1077 to La 21
H.011137.6 - Asphalt widening and overlay
Proj. Engr: Faucheux, Cody Route: I-12 LA 21 map
Contractor: James Construction Group LLC Miles: 3.65
Work Order Date Contract Amount Estimated Completion Date
2023-07-01 $56,877,604 Spring of 2026


US 190/La 22 Improvements
H.011721.6 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Ledet, Arthur Route: LA 22 US 190 map
Contractor: Boh Bros. Construction Co., Ll Miles: 0.71
Work Order Date Contract Amount Estimated Completion Date
2022-12-30 $10,798,596 Beginning of 2024


US 11 & US 190 Bicycle & Ped Crossings
H.011775.6 - Striping and pavement markers
Proj. Engr: Hebert, Taylor Route: US 11 US 190-Y map
Contractor: Kort's Construction Services, Miles: 0.23
Work Order Date Contract Amount Estimated Completion Date
2024-04-22 $1,240,005 Fall of 2024


LA 1129: La 40 - La Tung Rd
H.013268.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Adams, Kevin Route: LA 1129 map
Contractor: Madden Gulf Coast, LLC Miles: 5.37
Work Order Date Contract Amount Estimated Completion Date
2024-03-07 $4,748,019 Fall of 2024


Lindberg Drive @ US 190 (Gause Blvd)
H.013381.6 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Zzzz Clancy, Blaine Route:
Contractor: Barriere Construction Co., LLC Miles: 0.15
Work Order Date Contract Amount Estimated Completion Date
2022-04-01 $358,220 Summer of 2022


US 190: Drainage Improvements (Lacombe)
H.014142.6 - Drainage
Proj. Engr: Adams, Kevin Route: US 190 map
Contractor: LA Contracting Enterprise LLC Miles: 0.20
Work Order Date Contract Amount Estimated Completion Date
2024-08-05 $265,675 Fall of 2024


LA 1091: US 190 to Cclub Blvd Sidewalks
H.014363.6 - Sidewalks/bike paths
Proj. Engr: Faucheux, Cody Route: LA 1091 map
Contractor: Micon Services, Inc Miles: 2.10
Work Order Date Contract Amount Estimated Completion Date
2024-03-01 $964,052 Fall of 2024


La22:tchefuncte R. Mb Rprs(Madisonville)
H.014996.6 - Moveable bridges reconditioned
Proj. Engr: Faucheux, Cody Route: LA 22 map
Contractor: Coastal Contractors, LLC Miles: 0.10
Work Order Date Contract Amount Estimated Completion Date
2023-09-01 $582,000 Spring of 2024


La433 & Us90:bonfouca & E. Pearl Mb Rprs
H.015090.6 - Moveable bridges reconditioned
Proj. Engr: Faucheux, Cody Route: LA 433 US 90 map
Contractor: Coastal Contractors, LLC Miles: 0.24
Work Order Date Contract Amount Estimated Completion Date
2024-03-01 $276,000 Spring of 2024


US 190b: US 190 - La 21
H.015575.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Faucheux, Cody Route: US 190-X map
Contractor: Barber Bros. Contracting Co., Miles: 1.69
Work Order Date Contract Amount Estimated Completion Date
2024-07-15 $1,096,325 Fall of 2024


Tangipahoa Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 3234 University Ave Sidewalks
H.013938.6-R2 - Sidewalks/bike paths
Proj. Engr: Boutte, Christian Route: LA 3234 map
Contractor: Gulf States Services, LLC Miles: 1.09
Work Order Date Contract Amount Estimated Completion Date
2024-05-30 $3,103,532 Fall of 2025


I-12: US 51b (Hammond) Intchg Lighting
H.014271.6 - Roadway lighting
Proj. Engr: Boutte, Christian Route: I-12 map
Contractor: Diamond Electrical Co., Inc. Miles: 0.82
Work Order Date Contract Amount Estimated Completion Date
2023-07-14 $914,647 End of 2024


US 51: US 190 - La 3234
H.014822.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Boutte, Christian Route: US 51 map
Contractor: Barriere Construction Co., LLC Miles: 1.26
Work Order Date Contract Amount Estimated Completion Date
2024-05-06 $2,631,026 Beginning of 2025


LA 16: La 445 - Washington P/L
H.015275.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Woods, Derek Route: LA 16 map
Contractor: Barriere Construction Co., LLC Miles: 6.10
Work Order Date Contract Amount Estimated Completion Date
2024-08-30 $5,809,654 Spring of 2025


Washington Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 1070 & La 1073: Overlays
H.014923.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Hickman, Tommy Jr. Route: LA 1070 LA 1073 map
Contractor: Barriere Construction Co., LLC Miles: 4.50
Work Order Date Contract Amount Estimated Completion Date
2024-04-23 $4,304,126 Fall of 2024


District 62

No districtwide projects.