Projects Under Construction

District 62

    Updated 9 Nov 2019

Districtwide Projects

Livingston Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

US 190 & La 1026 (Roundabout)
H.000464.6 - Asphalt widening and overlay
Proj. Engr: Zzzz Wascom, Kris Route: LA 1026 US 190 map
Contractor: Kort's Construction Services, Miles: 0.48
Work Order Date Contract Amount Estimated Completion Date
2018-04-11 $6,249,971 End of 2019


Juban Rd Widening (I-12 to US 190)
H.004634.6 - Concrete new pavement
Proj. Engr: Berner, Darrick Route: LA 1026 map
Contractor: Kcr Contractors, LLC Miles: 0.86
Work Order Date Contract Amount Estimated Completion Date
2019-09-11 $6,405,430 Beginning of 2021


LA 16: Roundabout @ La 447
H.010124.6 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Berner, Darrick Route: LA 16 LA 447 map
Contractor: Command Construction Industrie Miles: 0.35
Work Order Date Contract Amount Estimated Completion Date
2019-04-20 $1,289,718 Fall of 2019


I-12: Median Cable Barrier
H.011278.6 - Guardrails
Proj. Engr: Berner, Darrick Route: I-12 map
Contractor: Magee Excavation & Development Miles: 13.01
Work Order Date Contract Amount Estimated Completion Date
2019-09-01 $4,305,356 Fall of 2020


District 62 -Districtwide Bridge Repairs
H.012650.6 - Bridges reconditioned
Proj. Engr: Woods, Derek Route: I-12 I-55 map
Contractor: Brown Industrial Construction, Miles: 6.45
Work Order Date Contract Amount Estimated Completion Date
2019-10-06 $1,837,628 Spring of 2020


I-12: La 1026 (Juban Rd) Interchange Lighting
H.012875.6 - Roadway lighting
Proj. Engr: Berner, Darrick Route: I-12 map
Contractor: Jack B. Harper Electrical LLC Miles: 1.00
Work Order Date Contract Amount Estimated Completion Date
2019-07-24 $1,168,755 Fall of 2020


LA 1064: Little Natalbany Br Replacement
H.013179.6 - New location/replacement of bridge
Proj. Engr: Berner, Darrick Route: LA 1064 map
Contractor: Jb James Construction LLC Miles: 0.14
Work Order Date Contract Amount Estimated Completion Date
2019-01-20 $2,486,893 Fall of 2019


LA 16: Colton Creek - La 64
H.013230.6 - Portland Cement Pavement patch
Proj. Engr: Berner, Darrick Route: LA 16 map
Contractor: Command Construction Industrie Miles: 1.45
Work Order Date Contract Amount Estimated Completion Date
2019-05-23 $1,020,257 Fall of 2019


LA 64: La 1019- La 16
H.013246.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Berner, Darrick Route: LA 64 map
Contractor: Barriere Construction Co., LLC Miles: 1.12
Work Order Date Contract Amount Estimated Completion Date
2019-01-20 $931,976 Spring of 2019


Port Vincent Br New Grid Floor
H.971897 - Moveable bridges reconditioned
Proj. Engr: Zzzz Wascom, Kris Route: map
Contractor: Boh Bros. Construction Co., Ll Miles: 0.07
Work Order Date Contract Amount Estimated Completion Date
2012-03-23 $473,316 Spring of 2012


Walker Landscaping Project
268-01-0015 - Miscellaneous
Proj. Engr: Zzzz Hollowell, Clay Route: LA 447 I-12 map
Contractor: Twin Shores Lands. & Const Serv I Miles: 1.30
Work Order Date Contract Amount Estimated Completion Date
2009-03-23 $213,013 Summer of 2009


St. Helena Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 63: Pigeon Creek Bridge
H.002407.6 - New location/replacement of bridge
Proj. Engr: Berner, Darrick Route: LA 63 map
Contractor: Brown Industrial Construction, Miles: 0.30
Work Order Date Contract Amount Estimated Completion Date
2019-07-29 $2,593,772 Summer of 2020


LA 441: La 16 - La 10
H.010382.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Zzzz Wascom, Kris Route: LA 441 map
Contractor: Diamond B Construction Co., L. Miles: 9.94
Work Order Date Contract Amount Estimated Completion Date
2018-06-07 $3,266,959 Spring of 2019


St. John Baptist Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

St. John Eb Miss River Trail, Phase 4
H.011845.6 - Sidewalks/bike paths
Proj. Engr: Oustalet, Randy Route: LA 44 map
Contractor: Magee Excavation & Development Miles: 1.14
Work Order Date Contract Amount Estimated Completion Date
2019-04-16 $2,315,583 Fall of 2019


St. Tammany Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

Boston Street Beautification
H.000486.6 - Sidewalks/bike paths
Proj. Engr: Harper, Daniel Route: US 190-X map
Contractor: Kass Bros. Inc. Miles: 0.47
Work Order Date Contract Amount Estimated Completion Date
2012-09-17 $550,353 Fall of 2013


LA 22 (Dalwill Dr - US 190)
H.000506.6 - Asphalt widening and overlay
Proj. Engr: Adams, Kevin Route: LA 22 map
Contractor: Magee Excavation & Development Miles: 0.75
Work Order Date Contract Amount Estimated Completion Date
2019-02-11 $2,651,139 Fall of 2019


LA 40: Tchefuncte River Bridge
H.002446.6 - New location/replacement of bridge
Proj. Engr: Mccaskill, Lacey Route: LA 40 map
Contractor: Tl Hawk, LLC Miles: 0.38
Work Order Date Contract Amount Estimated Completion Date
2019-07-06 $4,919,639 Beginning of 2021


Tammany Trace Camp Salmen Connector
H.006599.6 - Sidewalks/bike paths
Proj. Engr: Sharp, Sara Route: US 190 map
Contractor: Gulf States Contractors LLC Miles: 0.74
Work Order Date Contract Amount Estimated Completion Date
2018-04-25 $635,201 Spring of 2019


LA 59: Curve Realign and Tunnel at Trace
H.010184.6 - Sidewalks/bike paths
Proj. Engr: Adams, Kevin Route: LA 59 map
Contractor: Hard Rock Construction LLC Miles: 0.55
Work Order Date Contract Amount Estimated Completion Date
2019-05-16 $3,507,167 Fall of 2020


LA 25: Folsom City Limit - Hay Hollow Rd
H.010982.6 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Hickman, Tommy Jr. Route: LA 25 LA 40 map
Contractor: Barriere Construction Co., LLC Miles: 1.39
Work Order Date Contract Amount Estimated Completion Date
2018-09-01 $2,112,518 Summer of 2019


I-10: Med Protect, Oak Harbor Light / Ramp
H.011024.6 - Drainage
Proj. Engr: Adams, Kevin Route: I-10 map
Contractor: Huey P. Stockstill, LLC Miles: 7.00
Work Order Date Contract Amount Estimated Completion Date
2019-01-18 $15,238,539 Summer of 2020


LA 59: Roundabout @ Lonesome Rd.
H.011030.6 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Adams, Kevin Route: LA 59 map
Contractor: Magee Excavation & Development Miles: 0.32
Work Order Date Contract Amount Estimated Completion Date
2019-02-07 $1,887,146 Spring of 2020


US 190 Median Barrier
H.011933.6 - Guardrails
Proj. Engr: Adams, Kevin Route: US 190 map
Contractor: Magee Excavation & Development Miles: 1.72
Work Order Date Contract Amount Estimated Completion Date
2019-06-28 $613,583 Fall of 2019


I-12: La 59 - Bayou Lacombe
H.012172.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Mccaskill, Lacey Route: I-12 map
Contractor: Barriere Construction Co., LLC Miles: 7.69
Work Order Date Contract Amount Estimated Completion Date
2019-04-01 $7,534,863 Summer of 2019


US 190b: Hoover Drive to US 190
H.013237.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Mccaskill, Lacey Route: US 190-Y US 190 map
Contractor: Barriere Construction Co., LLC Miles: 1.74
Work Order Date Contract Amount Estimated Completion Date
2019-04-01 $1,325,480 Fall of 2019


Tangipahoa Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

I-12: Livingston P/L - US 51 Bus Opass
H.010991.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Boutte, Christian Route: I-12 US 51-X map
Contractor: Barriere Construction Co., LLC Miles: 6.13
Work Order Date Contract Amount Estimated Completion Date
2018-07-15 $8,199,189 Beginning of 2019


LA 22 Yellow Water River I-55
H.011439.6 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Boutte, Christian Route: LA 22 map
Contractor: Barriere Construction Co., LLC Miles: 2.23
Work Order Date Contract Amount Estimated Completion Date
2018-07-09 $2,029,432 Beginning of 2019


LA 1061: La 440 - Spring Creek Bridge
H.011573.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Woods, Derek Route: LA 1061 map
Contractor: Diamond B Construction Co., L. Miles: 4.33
Work Order Date Contract Amount Estimated Completion Date
2018-01-12 $617,217 Spring of 2018


LA 38: US 51 - La 1054
H.012154.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Woods, Derek Route: LA 38 map
Contractor: Diamond B Construction Co., L. Miles: 3.80
Work Order Date Contract Amount Estimated Completion Date
2019-04-15 $1,965,609 Fall of 2019


US 51b Near Cm Fagan Dr Signal Perf Meas
H.012670.6 - Signalization
Proj. Engr: Boutte, Christian Route: US 51-X map
Contractor: Jack B. Harper Electrical LLC Miles: 0.45
Work Order Date Contract Amount Estimated Completion Date
2019-08-01 $153,734 Beginning of 2020


I-55: La 22 Interstate Lighting
H.012874.6 - Roadway lighting
Proj. Engr: Boutte, Christian Route: I-55 map
Contractor: Diamond Electrical Co., Inc. Miles: 0.94
Work Order Date Contract Amount Estimated Completion Date
2019-06-12 $2,040,229 Beginning of 2021


LA 442: Tangipahoa River Bridge Replacement
H.013052.6 - New location/replacement of bridge
Proj. Engr: Boutte, Christian Route: LA 442 map
Contractor: Gilchrist Construction Co. LLC Miles: 0.20
Work Order Date Contract Amount Estimated Completion Date
2018-06-19 $3,498,198 Summer of 2019


LA 16: Tangipahoa River Br Replacement
H.013183.6 - New location/replacement of bridge
Proj. Engr: Woods, Derek Route: LA 16 map
Contractor: Jb James Construction LLC Miles: 0.31
Work Order Date Contract Amount Estimated Completion Date
2019-02-19 $7,005,625 Spring of 2021


I-55: .2 Mile S US 190 Ovp Slope Repair
H.013260.6 - Embankment repair
Proj. Engr: Boutte, Christian Route: I-55 map
Contractor: Hendrick Construction, Inc. Miles: 0.10
Work Order Date Contract Amount Estimated Completion Date
2019-07-19 $1,943,793 Spring of 2020


Washington Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 436: Monroe Creek Rd - N. Jct. La 21
H.010381.6 - Asph concrete ovly over in place stabilized/cement treated base course
Proj. Engr: Hickman, Tommy Jr. Route: LA 436 map
Contractor: Barriere Construction Co., LLC Miles: 5.87
Work Order Date Contract Amount Estimated Completion Date
2019-02-01 $3,232,421 Fall of 2019


LA 436: Burch Creek - Monroe Creek Rd.
H.013067.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Hickman, Tommy Jr. Route: LA 436 map
Contractor: Barriere Construction Co., LLC Miles: 12.48
Work Order Date Contract Amount Estimated Completion Date
2019-11-01 $6,693,772 Spring of 2021


District 62

No districtwide projects.