Projects Under Construction

District 62

    Updated 18 Oct 2017

Districtwide Projects

Livingston Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

U.S. 190: Roundabout at Eden Church Road
H.000466.6 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Wascom, Kris Route: US 190 map
Contractor: Kcr Contractors, LLC Miles: 0.23
Work Order Date Contract Amount Estimated Completion Date
2015-09-12 $2,525,730 Summer of 2017


LA 16 @ La 22: Install Roundabout
H.002373.6 - Asphalt widening and overlay
Proj. Engr: Wascom, Kris Route: LA 16 LA 22 map
Contractor: Boone Services LLC Miles: 0.08
Work Order Date Contract Amount Estimated Completion Date
2014-09-15 $1,823,123 Summer of 2017


LA 447 / I-12 Interchange
H.005693.6 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Wascom, Kris Route: LA 447 I-12 map
Contractor: Kort's Construction Services, Miles: 0.69
Work Order Date Contract Amount Estimated Completion Date
2015-12-21 $6,823,782 End of 2017


LA 1026 at La 1030 Roundabout
H.009140.6 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Wascom, Kris Route: LA 1026 map
Contractor: Kort's Construction Services, Miles: 0.16
Work Order Date Contract Amount Estimated Completion Date
2016-04-06 $1,561,934 Spring of 2018


US 190: W. Jct. La 16 - Jct. La 447
H.009549.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Wascom, Kris Route: US 190 map
Contractor: Miles: 5.67
Work Order Date Contract Amount Estimated Completion Date
2017-10-02 $3,269,397 Summer of 2018


I-12: Livingston Par Approach Slab Rep P2
H.009595.6 - Miscellaneous
Proj. Engr: Wascom, Kris Route: I-12 map
Contractor: Gilchrist Construction Co. LLC Miles: 1.20
Work Order Date Contract Amount Estimated Completion Date
2016-02-22 $16,135,564 Fall of 2017


Walker Sidewalk, Ph 3
H.009749.6-R1 - Sidewalks/bike paths
Proj. Engr: Bacas, Chad Route: LA 447 map
Contractor: Kort's Construction Services, Miles: 0.07
Work Order Date Contract Amount Estimated Completion Date
2017-06-14 $396,408 Fall of 2017


I-12 Wdn: .5 M W Satsuma-Satsuma Ramps
H.010558.6 - Asphalt widening and overlay
Proj. Engr: Wascom, Kris Route: I-12 map
Contractor: Coastal Bridge Co., L.L.C. Miles: 2.55
Work Order Date Contract Amount Estimated Completion Date
2017-05-01 $9,935,570 Spring of 2018


LA 447: La 1029 - Westcoll Rd Turn Lanes
H.011687.6 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Wascom, Kris Route: LA 447 map
Contractor: Barber Bros. Contracting Co., Miles: 0.37
Work Order Date Contract Amount Estimated Completion Date
2017-09-18 $465,796 Beginning of 2018


Port Vincent Br Wedge Conv-Hyd Repair
H.012178.6 - Moveable bridges reconditioned
Proj. Engr: Wascom, Kris Route: LA 42 map
Contractor: Coastal Bridge Co., L.L.C. Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2017-08-28 $1,176,000 Fall of 2018


I-12: Pavement Marking Replacement I
H.012361.6 - Striping and pavement markers
Proj. Engr: Wascom, Kris Route: I-12 map
Contractor: Southern Synergy LLC Miles: 9.81
Work Order Date Contract Amount Estimated Completion Date
2016-08-01 $564,787 Beginning of 2017


LA - 22: Audible Thermoplastic Test
H.012443.6 - Striping and pavement markers
Proj. Engr: Wascom, Kris Route: LA 22 map
Contractor: Miles: 6.26
Work Order Date Contract Amount Estimated Completion Date
2017-09-11 $224,000 End of 2017


Port Vincent Br New Grid Floor
H.971897 - Moveable bridges reconditioned
Proj. Engr: Wascom, Kris Route: map
Contractor: Boh Bros. Construction Co., Ll Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2012-03-23 $473,316 Spring of 2012


Walker Landscaping Project
268-01-0015 - Miscellaneous
Proj. Engr: Zzzz Hollowell, Clay Route: LA 447 I-12 map
Contractor: Twin Shores Lands. & Const Serv I Miles: 1.30
Work Order Date Contract Amount Estimated Completion Date
2009-03-23 $213,013 Summer of 2009


St. Helena Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 3126: La 10 - End of Control
H.010627.6 - Asphalt new pavement-new roadway/new alignments
Proj. Engr: Wascom, Kris Route: map
Contractor: Barber Bros. Contracting Co., Miles: 0.39
Work Order Date Contract Amount Estimated Completion Date
2014-02-03 $342,076 Summer of 2014


LA 10: Amite River Scour Repair
H.011934.6 - Embankment repair
Proj. Engr: Wascom, Kris Route: LA 10 map
Contractor: Barriere Construction Co., LLC Miles: 0.50
Work Order Date Contract Amount Estimated Completion Date
2017-01-23 $1,478,655 Spring of 2017


LA-10 Beaver Creek Bridge
H.012699.6 - Bridges reconditioned
Proj. Engr: Wascom, Kris Route: LA 10 map
Contractor: Miles: 0.18
Work Order Date Contract Amount Estimated Completion Date
2017-02-23 $2,028,166 Fall of 2017


St. John Baptist Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

US 61 @ Hemlock Street
H.000326.6 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Perilloux, Steve Route: LA 3224 map
Contractor: Kcr Contractors, LLC Miles: 0.09
Work Order Date Contract Amount Estimated Completion Date
2015-09-17 $705,752 Summer of 2016


LA 637: Port of S. Louisiana Connector
H.008322.6 - Asphalt widening and overlay
Proj. Engr: Perilloux, Steve Route: LA 637 map
Contractor: Durr Heavy Construction L.L.C. Miles: 1.49
Work Order Date Contract Amount Estimated Completion Date
2015-01-15 $7,643,180 Fall of 2016


LA 3188 Drainage Improvements
H.009391.6 - Drainage
Proj. Engr: Perilloux, Steve Route: LA 3188 map
Contractor: Kcr Contractors, LLC Miles: 0.42
Work Order Date Contract Amount Estimated Completion Date
2016-10-09 $1,246,480 Spring of 2017


I-10, I-12, I-55, I-59: D62 Interstate Rep.
H.009593.6 - Miscellaneous
Proj. Engr: James, Clay Route: I-10 map
Contractor: Forby Contracting, Inc. Miles: 0.01
Work Order Date Contract Amount Estimated Completion Date
2016-02-01 $6,606,229 Beginning of 2018


Grade Raising I-10 Ramps @ La 3188 Int.
H.010257.6 - Drainage
Proj. Engr: Perilloux, Steve Route: I-10 LA 3188 map
Contractor: Barber Bros. Contracting Co., Miles: 0.78
Work Order Date Contract Amount Estimated Completion Date
2017-08-21 $2,992,647 Spring of 2018


I-55 Emergency Crossings
H.011477.6 - ITS and emergency operations
Proj. Engr: Perilloux, Steve Route: I-55 map
Contractor: Diamond Electrical Co., Inc. Miles: 13.53
Work Order Date Contract Amount Estimated Completion Date
2016-05-20 $527,804 Beginning of 2017


St. Tammany Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

Boston Street Beautification
H.000486.6 - Sidewalks/bike paths
Proj. Engr: Harper, Daniel Route: US 190-X map
Contractor: Kass Bros. Inc. Miles: 0.47
Work Order Date Contract Amount Estimated Completion Date
2012-09-17 $550,353 Fall of 2013


Ns (Slidell) - US 11
H.000683.6 - Concrete pavement rehab-grinding/dowell retrofit/should drain install
Proj. Engr: Adams, Kevin Route: US 11 map
Contractor: The Three C's Properties Inc Miles: 0.60
Work Order Date Contract Amount Estimated Completion Date
2017-06-01 $63,402 Summer of 2017


I-12 @ Us-11 Interchange Lighting
H.000687.6 - Roadway lighting
Proj. Engr: Adams, Kevin Route: I-12 map
Contractor: Diamond Electrical Co., Inc. Miles: 0.39
Work Order Date Contract Amount Estimated Completion Date
2016-02-29 $913,764 Summer of 2017


LA 433: Salt Bayou Bridge
H.000689.6 - New location/replacement of bridge
Proj. Engr: Adams, Kevin Route: LA 433 map
Contractor: Baker Pile Driving and Site Wo Miles: 0.22
Work Order Date Contract Amount Estimated Completion Date
2017-06-15 $4,795,688 Summer of 2018


LA 21: La 41 - La 16
H.001006.6 - Asphaltic concrete overlay of rubblized pavement
Proj. Engr: Hickman, Tommy Jr. Route: LA 21 map
Contractor: Barriere Construction Co., LLC Miles: 2.06
Work Order Date Contract Amount Estimated Completion Date
2017-03-01 $3,490,335 Beginning of 2018


LA 21 Widening (Bootlegger Rd - 11th Ave)
H.001340.6 - New location/replacement of bridge
Proj. Engr: Mccaskill, Lacey Route: LA 21 map
Contractor: Jb James Construction LLC Miles: 1.46
Work Order Date Contract Amount Estimated Completion Date
2014-05-30 $18,075,449 Fall of 2017


I-12 @ La 434 Interchange Lighting
H.003451.6 - Roadway lighting
Proj. Engr: Adams, Kevin Route: I-12 LA 434 map
Contractor: Ernest P. Breaux Electrical, L Miles: 0.80
Work Order Date Contract Amount Estimated Completion Date
2016-09-06 $897,826 Fall of 2017


I-12 @ Northshore Blvd. Interchange Lighting
H.003452.6 - Roadway lighting
Proj. Engr: Adams, Kevin Route: I-12 map
Contractor: Jack B. Harper Electrical LLC Miles: 0.78
Work Order Date Contract Amount Estimated Completion Date
2016-02-08 $883,218 Spring of 2017


US 11 at Cleo Road
H.008369.6 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Adams, Kevin Route: US 11 map
Contractor: Hard Rock Construction LLC Miles: 0.18
Work Order Date Contract Amount Estimated Completion Date
2017-02-17 $1,293,766 Summer of 2017


LA 1085 & La 1077: Roundabout
H.009341.6 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Adams, Kevin Route: LA 1085 LA 1077 map
Contractor: Kort's Construction Services, Miles: 0.32
Work Order Date Contract Amount Estimated Completion Date
2015-06-01 $3,863,539 Spring of 2017


I-12: La 1088 Intchg Lighting
H.010720.6 - Roadway lighting
Proj. Engr: Adams, Kevin Route: I-12 map
Contractor: Jack B. Harper Electrical LLC Miles: 0.92
Work Order Date Contract Amount Estimated Completion Date
2016-11-01 $773,946 Beginning of 2018


US 11 Improvements at Schneider Canal
H.011435.6 - Asphalt new pavement-new roadway/new alignments
Proj. Engr: Adams, Kevin Route: US 11 map
Contractor: Hard Rock Construction LLC Miles: 0.32
Work Order Date Contract Amount Estimated Completion Date
2017-02-17 $5,006,357 Fall of 2017


LA 3228: US 190 - N. Causeway Blvd.
H.012379.6 - Asphalt widening and overlay
Proj. Engr: Adams, Kevin Route: LA 3228 map
Contractor: Barber Bros. Contracting Co., Miles: 0.65
Work Order Date Contract Amount Estimated Completion Date
2017-05-05 $998,249 Summer of 2017


LA 433: Voters Rd - US 11
H.012425.6 - Portland Cement Pavement patch
Proj. Engr: Adams, Kevin Route: LA 433 map
Contractor: Forby Contracting, Inc. Miles: 1.70
Work Order Date Contract Amount Estimated Completion Date
2017-05-26 $559,809 Fall of 2017


Tangipahoa Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

US 51 Bridge Rehabilitation
H.000673.6 -
Proj. Engr: Perilloux, Steve Route: US 51 map
Contractor: Waskey Services LLC Miles: 0.04
Work Order Date Contract Amount Estimated Completion Date
2017-05-23 $152,655 Summer of 2017


Interchange Improvements @ I-12 & U.S. 51 Bus.
H.003432.6 - Concrete new pavement
Proj. Engr: Perilloux, Steve Route: US 51-X I-12 map
Contractor: Barriere Construction Co., LLC Miles: 0.59
Work Order Date Contract Amount Estimated Completion Date
2015-01-17 $7,627,590 Summer of 2016


LA 445: Jct US 190 - S. Jct La 40
H.009547.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Perilloux, Steve Route: LA 445 map
Contractor: Barriere Construction Co., LLC Miles: 7.71
Work Order Date Contract Amount Estimated Completion Date
2016-08-01 $3,188,920 Summer of 2017


LA 38: La 1054 - Washington P/L
H.010378.6 - Asphalt overlay of asphalt pavement
Proj. Engr: James, Clay Route: LA 38 map
Contractor: Barriere Construction Co., LLC Miles: 6.17
Work Order Date Contract Amount Estimated Completion Date
2017-02-01 $3,225,241 Beginning of 2018


LA 40: N. Jct. La 445 - St. Tammany P/L
H.010379.6 - Asphalt overlay of asphalt pavement
Proj. Engr: James, Clay Route: LA 40 map
Contractor: Barriere Construction Co., LLC Miles: 3.93
Work Order Date Contract Amount Estimated Completion Date
2016-07-01 $1,819,096 End of 2016


I-55: Exit 28 Emergency Truss Replacement
H.010583.6 - Signing
Proj. Engr: Perilloux, Steve Route: I-55 map
Contractor: Traffic Solutions, Inc. Miles: 0.01
Work Order Date Contract Amount Estimated Completion Date
2013-07-15 $49,962 End of 2013


I-55: Median Cable Barrier
H.010683.6 - Miscellaneous
Proj. Engr: Perilloux, Steve Route: I-55 map
Contractor: Command Construction Industrie Miles: 37.52
Work Order Date Contract Amount Estimated Completion Date
2016-07-01 $7,303,606 Summer of 2017


I-55 Cn R/R & I-12 US 51 Slope Failure
H.010790.6 - Embankment
Proj. Engr: Perilloux, Steve Route: I-55 I-12 map
Contractor: Cycle Construction Co. L.L.C. Miles: 0.31
Work Order Date Contract Amount Estimated Completion Date
2015-03-12 $4,837,810 Fall of 2016


I-55: La 38 (Kentwood) Interchange Lighting
H.011393.6 - Roadway lighting
Proj. Engr: James, Clay Route: I-55 map
Contractor: Jack B. Harper Electrical LLC Miles: 0.91
Work Order Date Contract Amount Estimated Completion Date
2016-07-11 $916,226 Summer of 2017


I-55 Signing: US 51 to I-12
H.011883.6 - Signing
Proj. Engr: Perilloux, Steve Route: I-55 I-12 map
Contractor: Command Construction Industrie Miles: 1.30
Work Order Date Contract Amount Estimated Completion Date
2016-09-20 $1,908,568 Fall of 2017


LA 1065: E. Michigan to La 442
H.012111.6 - Asph concrete ovly over in place stabilized/cement treated base course
Proj. Engr: Perilloux, Steve Route: LA 1065 map
Contractor: Diamond B Construction Co., L. Miles: 2.79
Work Order Date Contract Amount Estimated Completion Date
2017-01-18 $1,869,817 Summer of 2017


LA 1054 at Big Creek Bridge Replacement
H.012411.6 - New location/replacement of bridge
Proj. Engr: James, Clay Route: LA 1054 map
Contractor: Brown Industrial Construction, Miles: 0.22
Work Order Date Contract Amount Estimated Completion Date
2017-04-01 $2,103,836 Fall of 2018


District 62 Truss Replacement
H.012628.6 - Signing
Proj. Engr: Perilloux, Steve Route: I-55 map
Contractor: Traffic Solutions, Inc. Miles: 0.01
Work Order Date Contract Amount Estimated Completion Date
2017-07-07 $163,098 Beginning of 2018


LA 443 Tangipahoa River Bridge Replacement
H.012728.6 - New location/replacement of bridge
Proj. Engr: Perilloux, Steve Route: LA 443 map
Contractor: Miles: 0.07
Work Order Date Contract Amount Estimated Completion Date
2017-02-02 $2,894,102 Beginning of 2018


Washington Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 62: La 438 - Ms State Line
H.012582.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Hickman, Tommy Jr. Route: LA 62 map
Contractor: Miles: 1.73
Work Order Date Contract Amount Estimated Completion Date
2017-10-16 $241,315 Beginning of 2018


District 62

No districtwide projects.