Projects Under Construction

District 62

    Updated 29 Apr 2017

Districtwide Projects

Livingston Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

U.S. 190: Roundabout at Eden Church Road
H.000466.6 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Wascom, Kris Route: US 190 map
Contractor: Kcr Contractors, LLC Miles: 0.23
Work Order Date Contract Amount Estimated Completion Date
2015-09-12 $2,396,426 End of 2016


LA 16 @ La 22: Install Roundabout
H.002373.6 - Asphalt widening and overlay
Proj. Engr: Wascom, Kris Route: LA 16 LA 22 map
Contractor: Boone Services LLC Miles: 0.08
Work Order Date Contract Amount Estimated Completion Date
2014-09-15 $1,751,503 Spring of 2017


LA 447 / I-12 Interchange
H.005693.6 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Wascom, Kris Route: LA 447 I-12 map
Contractor: Kort's Construction Services, Miles: 0.69
Work Order Date Contract Amount Estimated Completion Date
2015-12-21 $6,823,782 Summer of 2017


US 190 and La 1032 Intersection Improvements
H.008173.6 - Asphalt widening and overlay
Proj. Engr: Wascom, Kris Route: LA 1032 map
Contractor: Kort's Construction Services, Miles: 0.18
Work Order Date Contract Amount Estimated Completion Date
2015-05-18 $921,746 Spring of 2017


LA 1025: Creek Bridge Near Friendship
H.008190.6 - New location/replacement of bridge
Proj. Engr: Wascom, Kris Route: LA 1025 map
Contractor: Brown Industrial Construction, Miles: 0.26
Work Order Date Contract Amount Estimated Completion Date
2016-10-24 $340,566 Spring of 2017


LA 3002: La 1034/Us 190
H.008193.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Wascom, Kris Route: LA 3002 map
Contractor: Diamond B Construction Co., L. Miles: 2.54
Work Order Date Contract Amount Estimated Completion Date
2015-08-10 $2,362,127 Summer of 2016


LA 1026 at La 1030 Roundabout
H.009140.6 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Wascom, Kris Route: LA 1026 map
Contractor: Kort's Construction Services, Miles: 0.16
Work Order Date Contract Amount Estimated Completion Date
2016-04-06 $1,550,877 Summer of 2017


US 190: E. Baton Rouge Parish Line - W. Jct. La 16
H.009548.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Wascom, Kris Route: US 190 map
Contractor: Barber Bros. Contracting Co., Miles: 2.69
Work Order Date Contract Amount Estimated Completion Date
2016-07-15 $1,921,786 Beginning of 2017


I-12: Livingston Par Approach Slab Rep P2
H.009595.6 - Miscellaneous
Proj. Engr: Wascom, Kris Route: I-12 map
Contractor: Gilchrist Construction Co. LLC Miles: 1.20
Work Order Date Contract Amount Estimated Completion Date
2016-02-22 $16,135,564 Fall of 2017


I-12: Pavement Marking Replacement I
H.012361.6 - Striping and pavement markers
Proj. Engr: Wascom, Kris Route: I-12 map
Contractor: Southern Synergy LLC Miles: 9.81
Work Order Date Contract Amount Estimated Completion Date
2016-08-01 $595,089 Beginning of 2017


Port Vincent Br New Grid Floor
H.971897 - Moveable bridges reconditioned
Proj. Engr: Wascom, Kris Route: map
Contractor: Boh Bros. Construction Co., Ll Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2012-03-23 $473,316 Spring of 2012


Walker Landscaping Project
268-01-0015 - Miscellaneous
Proj. Engr: Zzzz Hollowell, Clay Route: LA 447 I-12 map
Contractor: Twin Shores Lands. & Const Serv I Miles: 1.30
Work Order Date Contract Amount Estimated Completion Date
2009-03-23 $213,013 Summer of 2009


St. Helena Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 43: La 38 - Mississippi State Line
H.002311.6 - Asphalt overlay of asphalt pavement
Proj. Engr: James, Clay Route: LA 43 map
Contractor: Barriere Construction Co., LLC Miles: 5.83
Work Order Date Contract Amount Estimated Completion Date
2015-10-15 $1,536,769 Beginning of 2016


LA 3126: La 10 - End of Control
H.010627.6 - Asphalt new pavement-new roadway/new alignments
Proj. Engr: Wascom, Kris Route: map
Contractor: Barber Bros. Contracting Co., Miles: 0.39
Work Order Date Contract Amount Estimated Completion Date
2014-02-03 $342,076 Summer of 2014


LA 10: Amite River Scour Repair
H.011934.6 - Embankment repair
Proj. Engr: Wascom, Kris Route: LA 10 map
Contractor: Barriere Construction Co., LLC Miles: 0.50
Work Order Date Contract Amount Estimated Completion Date
2017-01-23 $1,478,655 Spring of 2017


LA-10 Beaver Creek Bridge
H.012699.6 - Bridges reconditioned
Proj. Engr: Wascom, Kris Route: LA 10 map
Contractor: Miles: 0.18
Work Order Date Contract Amount Estimated Completion Date
2017-02-23 $2,028,166 Beginning of 2018


St. John Baptist Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

US 61 @ Hemlock Street
H.000326.6 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Perilloux, Steve Route: LA 3224 map
Contractor: Kcr Contractors, LLC Miles: 0.09
Work Order Date Contract Amount Estimated Completion Date
2015-09-17 $700,351 Summer of 2016


LA 637: Port of S. Louisiana Connector
H.008322.6 - Asphalt widening and overlay
Proj. Engr: Perilloux, Steve Route: LA 637 map
Contractor: Durr Heavy Construction L.L.C. Miles: 1.49
Work Order Date Contract Amount Estimated Completion Date
2015-01-15 $7,371,217 Fall of 2016


LA 3188 Drainage Improvements
H.009391.6 - Drainage
Proj. Engr: Perilloux, Steve Route: LA 3188 map
Contractor: Kcr Contractors, LLC Miles: 0.42
Work Order Date Contract Amount Estimated Completion Date
2016-10-09 $1,178,587 Spring of 2017


I-10, I-12, I-55, I-59: D62 Interstate Rep.
H.009593.6 - Miscellaneous
Proj. Engr: James, Clay Route: I-10 map
Contractor: Forby Contracting, Inc. Miles: 0.01
Work Order Date Contract Amount Estimated Completion Date
2016-02-01 $6,557,705 Beginning of 2018


I-10 ITS Fire Damage Repair
H.011470.6 - ITS and emergency operations
Proj. Engr: Perilloux, Steve Route: I-10 map
Contractor: Diamond Electrical Co., Inc. Miles: 1.93
Work Order Date Contract Amount Estimated Completion Date
2015-05-08 $210,419 Summer of 2015


I-55 Emergency Crossings
H.011477.6 - ITS and emergency operations
Proj. Engr: Perilloux, Steve Route: I-55 map
Contractor: Diamond Electrical Co., Inc. Miles: 13.53
Work Order Date Contract Amount Estimated Completion Date
2016-05-20 $516,200 Beginning of 2017


LA 44: Right Turn Lane @ US 61
H.012065.6 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Perilloux, Steve Route: LA 44 map
Contractor: Brown Industrial Construction, Miles: 0.06
Work Order Date Contract Amount Estimated Completion Date
2016-10-03 $104,745 Beginning of 2017


St. Tammany Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

Boston Street Beautification
H.000486.6 - Sidewalks/bike paths
Proj. Engr: Harper, Daniel Route: US 190-X map
Contractor: Kass Bros. Inc. Miles: 0.47
Work Order Date Contract Amount Estimated Completion Date
2012-09-17 $550,353 Fall of 2013


I-12 @ Us-11 Interchange Lighting
H.000687.6 - Roadway lighting
Proj. Engr: Dearmas, Seth Route: I-12 map
Contractor: Diamond Electrical Co., Inc. Miles: 0.39
Work Order Date Contract Amount Estimated Completion Date
2016-02-29 $909,909 Spring of 2017


LA 21: La 41 - La 16
H.001006.6 - Asphaltic concrete overlay of rubblized pavement
Proj. Engr: Hickman, Tommy Jr. Route: LA 21 map
Contractor: Barriere Construction Co., LLC Miles: 2.06
Work Order Date Contract Amount Estimated Completion Date
2017-03-01 $3,326,427 Beginning of 2018


LA 21 Widening (Bootlegger Rd - 11th Ave)
H.001340.6 - New location/replacement of bridge
Proj. Engr: Mccaskill, Lacey Route: LA 21 map
Contractor: Jb James Construction LLC Miles: 1.46
Work Order Date Contract Amount Estimated Completion Date
2014-05-30 $17,893,914 Spring of 2017


I-12 @ La 434 Interchange Lighting
H.003451.6 - Roadway lighting
Proj. Engr: Dearmas, Seth Route: I-12 LA 434 map
Contractor: Ernest P. Breaux Electrical, L Miles: 0.80
Work Order Date Contract Amount Estimated Completion Date
2016-09-06 $820,218 Fall of 2017


I-12 @ Northshore Blvd. Interchange Lighting
H.003452.6 - Roadway lighting
Proj. Engr: Dearmas, Seth Route: I-12 map
Contractor: Jack B. Harper Electrical LLC Miles: 0.78
Work Order Date Contract Amount Estimated Completion Date
2016-02-08 $883,218 Spring of 2017


US 11 at Cleo Road
H.008369.6 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Dearmas, Seth Route: US 11 map
Contractor: Hard Rock Construction LLC Miles: 0.18
Work Order Date Contract Amount Estimated Completion Date
2017-02-17 $1,042,289 Spring of 2017


LA 1085 & La 1077: Roundabout
H.009341.6 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Dearmas, Seth Route: LA 1085 LA 1077 map
Contractor: Kort's Construction Services, Miles: 0.32
Work Order Date Contract Amount Estimated Completion Date
2015-06-01 $3,672,733 Spring of 2017


East Pearl River Swing Bridge Permanent Repairs
H.010619.6 - Moveable bridges reconditioned
Proj. Engr: Dearmas, Seth Route: US 90 map
Contractor: Boh Bros. Construction Co., Ll Miles: 0.18
Work Order Date Contract Amount Estimated Completion Date
2014-03-03 $1,272,796 Spring of 2017


I-12: La 1088 Intchg Lighting
H.010720.6 - Roadway lighting
Proj. Engr: Dearmas, Seth Route: I-12 map
Contractor: Jack B. Harper Electrical LLC Miles: 0.92
Work Order Date Contract Amount Estimated Completion Date
2016-11-01 $773,946 Beginning of 2018


US 11 Improvements at Schneider Canal
H.011435.6 - Asphalt new pavement-new roadway/new alignments
Proj. Engr: Dearmas, Seth Route: US 11 map
Contractor: Hard Rock Construction LLC Miles: 0.32
Work Order Date Contract Amount Estimated Completion Date
2017-02-17 $4,932,810 Fall of 2017


I-10 Middle Pearl River Bent Repairs
H.012440.6 - Bridges reconditioned
Proj. Engr: Dearmas, Seth Route: I-10 map
Contractor: James Construction Group LLC Miles: 0.75
Work Order Date Contract Amount Estimated Completion Date
2016-06-27 $1,255,247 Spring of 2017


Tangipahoa Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 1061: La 10 - La 440
H.002474.6 - Asph concrete ovly over in place stabilized/cement treated base course
Proj. Engr: James, Clay Route: LA 1061 map
Contractor: Diamond B Construction Co., L. Miles: 4.54
Work Order Date Contract Amount Estimated Completion Date
2016-08-15 $1,967,237 Spring of 2017


Interchange Improvements @ I-12 & U.S. 51 Bus.
H.003432.6 - Concrete new pavement
Proj. Engr: Perilloux, Steve Route: US 51-X I-12 map
Contractor: Barriere Construction Co., LLC Miles: 0.59
Work Order Date Contract Amount Estimated Completion Date
2015-01-17 $7,627,590 Summer of 2016


LA 445: Jct US 190 - S. Jct La 40
H.009547.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Perilloux, Steve Route: LA 445 map
Contractor: Barriere Construction Co., LLC Miles: 7.71
Work Order Date Contract Amount Estimated Completion Date
2016-08-01 $3,145,427 Summer of 2017


I-55: End of Elevated Roadway - US 51
H.009598.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Perilloux, Steve Route: I-55 map
Contractor: Diamond B Construction Co., L. Miles: 5.30
Work Order Date Contract Amount Estimated Completion Date
2015-08-31 $5,766,637 Summer of 2016


LA 38: La 1054 - Washington P/L
H.010378.6 - Asphalt overlay of asphalt pavement
Proj. Engr: James, Clay Route: LA 38 map
Contractor: Barriere Construction Co., LLC Miles: 6.17
Work Order Date Contract Amount Estimated Completion Date
2017-02-01 $3,080,470 Beginning of 2018


LA 40: N. Jct. La 445 - St. Tammany P/L
H.010379.6 - Asphalt overlay of asphalt pavement
Proj. Engr: James, Clay Route: LA 40 map
Contractor: Barriere Construction Co., LLC Miles: 3.93
Work Order Date Contract Amount Estimated Completion Date
2016-07-01 $1,669,199 End of 2016


I-55: Exit 28 Emergency Truss Replacement
H.010583.6 - Signing
Proj. Engr: Perilloux, Steve Route: I-55 map
Contractor: Traffic Solutions, Inc. Miles: 0.01
Work Order Date Contract Amount Estimated Completion Date
2013-07-15 $49,962 End of 2013


I-55: Median Cable Barrier
H.010683.6 - Miscellaneous
Proj. Engr: Perilloux, Steve Route: I-55 map
Contractor: Command Construction Industrie Miles: 37.52
Work Order Date Contract Amount Estimated Completion Date
2016-07-01 $7,303,606 Summer of 2017


I-55 Cn R/R & I-12 US 51 Slope Failure
H.010790.6 - Embankment
Proj. Engr: Perilloux, Steve Route: I-55 I-12 map
Contractor: Cycle Construction Co. L.L.C. Miles: 0.31
Work Order Date Contract Amount Estimated Completion Date
2015-03-12 $4,435,796 Fall of 2016


I-55: La 38 (Kentwood) Interchange Lighting
H.011393.6 - Roadway lighting
Proj. Engr: James, Clay Route: I-55 map
Contractor: Jack B. Harper Electrical LLC Miles: 0.91
Work Order Date Contract Amount Estimated Completion Date
2016-07-11 $902,349 Summer of 2017


LA 440: S. Jct. La 1054 - La 1057
H.011400.6 - Asph concrete ovly over in place stabilized/cement treated base course
Proj. Engr: James, Clay Route: LA 440 map
Contractor: Barriere Construction Co., LLC Miles: 5.44
Work Order Date Contract Amount Estimated Completion Date
2015-04-01 $5,066,968 Summer of 2016


I-55 Signing: US 51 to I-12
H.011883.6 - Signing
Proj. Engr: Perilloux, Steve Route: I-55 I-12 map
Contractor: Command Construction Industrie Miles: 1.30
Work Order Date Contract Amount Estimated Completion Date
2016-09-20 $1,584,792 Fall of 2017


LA 1065: E. Michigan to La 442
H.012111.6 - Asph concrete ovly over in place stabilized/cement treated base course
Proj. Engr: Perilloux, Steve Route: LA 1065 map
Contractor: Diamond B Construction Co., L. Miles: 2.79
Work Order Date Contract Amount Estimated Completion Date
2017-01-18 $1,862,779 Summer of 2017


LA 1054 at Big Creek Bridge Replacement
H.012411.6 - New location/replacement of bridge
Proj. Engr: James, Clay Route: LA 1054 map
Contractor: Brown Industrial Construction, Miles: 0.22
Work Order Date Contract Amount Estimated Completion Date
2017-04-01 $2,103,836 Fall of 2018


LA 443 Tangipahoa River Bridge Replacement
H.012728.6 - New location/replacement of bridge
Proj. Engr: Perilloux, Steve Route: LA 443 map
Contractor: Miles: 0.07
Work Order Date Contract Amount Estimated Completion Date
2017-02-02 $2,894,102 Beginning of 2018


Washington Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 438: La 21 - Old Columbia Rd.
H.011782.6 - Asph concrete ovly over in place stabilized/cement treated base course
Proj. Engr: Hickman, Tommy Jr. Route: LA 438 map
Contractor: Huey P. Stockstill, LLC Miles: 2.58
Work Order Date Contract Amount Estimated Completion Date
2016-12-07 $1,162,386 Spring of 2017


District 62

No districtwide projects.