Districtwide Projects
Caldwell Parish
Note: The estimated completion date is based
on the work order date and the contract
days allowed.
Unavoidable contingencies and unforeseen events
often develop during construction, which may
impact the actual completion date.
US 165 & US 84 PCCP Patching |
H.015756.6 - Portland Cement Pavement patch
|
Proj. Engr: Moon, Andy |
Route: |
US 165 US 84
map
|
Contractor: Forby Contracting, Inc. |
Miles:
| 13.34 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2024-11-21 |
$1,516,625 |
Spring of 2025 |
Catahoula Parish
Note: The estimated completion date is based
on the work order date and the contract
days allowed.
Unavoidable contingencies and unforeseen events
often develop during construction, which may
impact the actual completion date.
LA 8: Ouachita River Bridge Scour Repair |
H.013273.6-R1 - Bridges reconditioned
|
Proj. Engr: Mcglothlin, Ralston |
Route: |
LA 8
map
|
Contractor: Luhr Crosby, LLC |
Miles:
| 0.09 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-12-01 |
$3,307,832 |
Fall of 2024 |
Dist. 58 Ast: Catahoula, Concordia, Lasalle |
H.015589.6 - Asphalt surface treatment
|
Proj. Engr: Moon, Andy |
Route: |
LA 3101 LA 921
map
|
Contractor: Dreher Contracting, LLC |
Miles:
| 36.77 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2024-01-26 |
$2,700,648 |
Summer of 2024 |
Concordia Parish
Note: The estimated completion date is based
on the work order date and the contract
days allowed.
Unavoidable contingencies and unforeseen events
often develop during construction, which may
impact the actual completion date.
LA 900: La 568 - US 65 |
H.014118.6 - Asphalt overlay of asphalt pavement
|
Proj. Engr: Moon, Andy |
Route: |
LA 900
map
|
Contractor: D & J Construction Co., LLC |
Miles:
| 4.28 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2024-09-27 |
$2,815,372 |
Spring of 2025 |
LA 565: La 129 - La 15 |
H.014798.6 - Asphalt overlay of asphalt pavement
|
Proj. Engr: Moon, Andy |
Route: |
LA 565
map
|
Contractor: D & J Construction Co., LLC |
Miles:
| 8.49 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2024-12-02 |
$8,589,008 |
Summer of 2025 |
Franklin Parish
Note: The estimated completion date is based
on the work order date and the contract
days allowed.
Unavoidable contingencies and unforeseen events
often develop during construction, which may
impact the actual completion date.
LA 857: La 15 - La 132 |
H.011564.6 - Asphalt overlay of asphalt pavement
|
Proj. Engr: Moon, Andy |
Route: |
LA 857
map
|
Contractor: Diamond B Construction Co., L. |
Miles:
| 4.81 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2024-08-26 |
$2,784,327 |
Beginning of 2025 |
LaSalle Parish
Note: The estimated completion date is based
on the work order date and the contract
days allowed.
Unavoidable contingencies and unforeseen events
often develop during construction, which may
impact the actual completion date.
Jena: Multi-Modal Connectivity |
H.009765.6 - Sidewalks/bike paths
|
Proj. Engr: Capdepon, Keith |
Route: |
|
Contractor: Progressive Construction Co., |
Miles:
| 0.00 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2018-11-13 |
$1,274,798 |
Summer of 2019 |
US 84 Emergency Diversion Bridge |
H.015718.6 - New location/replacement of bridge
|
Proj. Engr: Mcglothlin, Ralston |
Route: |
US 84
map
|
Contractor: C.E.C., Inc. |
Miles:
| 0.03 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2024-01-10 |
$5,875,000 |
Spring of 2025 |
District 58
No districtwide projects.