Projects Under Construction

District 58

    Updated 18 Apr 2024

Districtwide Projects

Caldwell Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

District 58 Ast: Caldwell, Franklin, Tensas
H.015588.6 - Asphalt surface treatment
Proj. Engr: Moon, Andy Route: LA 846 LA 844 map
Contractor: Dreher Contracting, LLC Miles: 39.87
Work Order Date Contract Amount Estimated Completion Date
2024-01-26 $2,377,876 Summer of 2024


Catahoula Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 3102: La 124 - End Log Mile 7.50
H.007946.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Moon, Andy Route: LA 3102 map
Contractor: D & J Construction Co., LLC Miles: 7.50
Work Order Date Contract Amount Estimated Completion Date
2023-08-28 $7,162,551 Spring of 2024


LA 923: La 126 - La 124 & 1018-1, 1018-2, 1018-3
H.014862.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Mcglothlin, Ralston Route: LA 923 LA 1018-1 map
Contractor: D & J Construction Co., LLC Miles: 4.78
Work Order Date Contract Amount Estimated Completion Date
2024-03-01 $2,376,290 Spring of 2024


Dist. 58 Ast: Catahoula, Concordia, Lasalle
H.015589.6 - Asphalt surface treatment
Proj. Engr: Moon, Andy Route: LA 3101 LA 921 map
Contractor: Dreher Contracting, LLC Miles: 36.77
Work Order Date Contract Amount Estimated Completion Date
2024-01-26 $2,621,235 Summer of 2024


Concordia Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 15: Slocum - Deer Park
H.013919.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Moon, Andy Route: LA 15 map
Contractor: D & J Construction Co., LLC Miles: 9.62
Work Order Date Contract Amount Estimated Completion Date
2023-12-15 $5,545,482 Summer of 2024


LA 568: La 569 - US 65
H.014806.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Moon, Andy Route: LA 568 map
Contractor: D & J Construction Co., LLC Miles: 6.19
Work Order Date Contract Amount Estimated Completion Date
2024-04-05 $3,385,104 Fall of 2024


Franklin Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

US 425: Baskin - Richland P/L
H.014877.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Moon, Andy Route: US 425 map
Contractor: Diamond B Construction Co., L. Miles: 3.75
Work Order Date Contract Amount Estimated Completion Date
2023-11-03 $3,358,896 Spring of 2024


LaSalle Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

Jena: Multi-Modal Connectivity
H.009765.6 - Sidewalks/bike paths
Proj. Engr: Capdepon, Keith Route:
Contractor: Progressive Construction Co., Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2018-11-13 $1,274,798 Summer of 2019


US 84 Emergency Diversion Bridge
H.015718.6 - New location/replacement of bridge
Proj. Engr: Mcglothlin, Ralston Route: US 84 map
Contractor: C.E.C., Inc. Miles: 0.03
Work Order Date Contract Amount Estimated Completion Date
2024-01-10 $5,875,000 Spring of 2025


Tensas Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 3252: La 573 - La 892
H.014875.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Moon, Andy Route: LA 3252 map
Contractor: Diamond B Construction Co., L. Miles: 6.68
Work Order Date Contract Amount Estimated Completion Date
2024-03-18 $3,294,131 Summer of 2024


District 58

No districtwide projects.