Districtwide Projects
Allen Parish
Note: The estimated completion date is based
on the work order date and the contract
days allowed.
Unavoidable contingencies and unforeseen events
often develop during construction, which may
impact the actual completion date.
LA 372: Creek Bridge |
H.012039.6 - New location/replacement of bridge
|
Proj. Engr: Schultz, Konrad |
Route: |
LA 372
map
|
Contractor: Siema Construction, LLC |
Miles:
| 0.21 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-10-17 |
$1,417,793 |
Spring of 2024 |
US 190: La 113 - Calcasieu River Br |
H.014757.6 - Asphalt overlay of asphalt pavement
|
Proj. Engr: Dyke, Clint |
Route: |
US 190
map
|
Contractor: Prairie Contractors LLC |
Miles:
| 7.84 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-07-03 |
$5,460,632 |
Beginning of 2024 |
Beauregard Parish
Note: The estimated completion date is based
on the work order date and the contract
days allowed.
Unavoidable contingencies and unforeseen events
often develop during construction, which may
impact the actual completion date.
LA 389: Monroe Whitman Rd - Blackmon Ln |
H.010245.6 - Asphalt widening and overlay
|
Proj. Engr: Dyke, Clint |
Route: |
LA 389
map
|
Contractor: Prairie Contractors LLC |
Miles:
| 12.07 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-10-09 |
$7,316,418 |
Fall of 2023 |
Calcasieu Parish
Note: The estimated completion date is based
on the work order date and the contract
days allowed.
Unavoidable contingencies and unforeseen events
often develop during construction, which may
impact the actual completion date.
LA 12 Bridges |
H.000428.6 - New location/replacement of bridge
|
Proj. Engr: Dyke, Clint |
Route: |
LA 12
map
|
Contractor: Gilchrist Construction Company |
Miles:
| 2.11 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2018-09-22 |
$24,668,257 |
End of 2023 |
I-10: Texas State Line - E. of Coone Gullly |
H.003184.6 - Concrete new pavement
|
Proj. Engr: Ponthieux, Vicki |
Route: |
I-10
map
|
Contractor: Johnson Bros. Corp. a Southlan |
Miles:
| 10.55 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2020-08-17 |
$152,675,014 |
Spring of 2025 |
Nelson Road Extension and Bridge |
H.005967.6-R1 - New location/replacement of bridge
|
Proj. Engr: Thevis, Tyson |
Route: |
LA 1138-1
map
|
Contractor: Johnson Bros. Corp. a Southlan |
Miles:
| 1.00 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-03-01 |
$101,919,847 |
Beginning of 2027 |
Cameron Parish
Note: The estimated completion date is based
on the work order date and the contract
days allowed.
Unavoidable contingencies and unforeseen events
often develop during construction, which may
impact the actual completion date.
LA 384: Canal Bridge |
H.013963.6 - New location/replacement of bridge
|
Proj. Engr: Thevis, Tyson |
Route: |
LA 384
map
|
Contractor: Guinn Construction, LLC |
Miles:
| 0.06 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-11-28 |
$909,979 |
Summer of 2023 |
LA 27: Kelso & Ellender Mb Repairs |
H.014545.6-R2 - Moveable bridges reconditioned
|
Proj. Engr: Ponthieux, Vicki |
Route: |
LA 27
map
|
Contractor: C.E.C., Inc. |
Miles:
| 1.00 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-04-04 |
$4,145,668 |
Fall of 2024 |
LA 82: G Chenier & Superior Mb Rep (Hbi) |
H.014549.6 - Moveable bridges reconditioned
|
Proj. Engr: Schultz, Konrad |
Route: |
LA 82
map
|
Contractor: C.E.C., Inc. |
Miles:
| 0.34 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-12-03 |
$2,065,978 |
Beginning of 2024 |
Jefferson Davis Parish
Note: The estimated completion date is based
on the work order date and the contract
days allowed.
Unavoidable contingencies and unforeseen events
often develop during construction, which may
impact the actual completion date.
I-10 Overpass Over US 165 & Mp R.R |
H.002980.6-R1 - New location/replacement of bridge
|
Proj. Engr: Schultz, Konrad |
Route: |
I-10
map
|
Contractor: Gilchrist Construction Company |
Miles:
| 2.15 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-08-14 |
$76,120,146 |
Spring of 2025 |
US 165: 0.85 Mi N I-10 - Allen P/L |
H.013255.6 - Asphalt overlay of asphalt pavement
|
Proj. Engr: Schultz, Konrad |
Route: |
US 165
map
|
Contractor: Prairie Contractors LLC |
Miles:
| 13.63 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-02-05 |
$10,230,611 |
Spring of 2024 |
LA 26: Left Turn Lanes @ S. Frontage Rd. |
H.013826.6 - Planning study
|
Proj. Engr: Schultz, Konrad |
Route: |
LA 26
map
|
Contractor: Siema Construction, LLC |
Miles:
| 0.16 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-09-10 |
$854,402 |
Beginning of 2024 |
I-10: La 26 (Jennings) Intchg Lighting |
H.014286.6 - Roadway lighting
|
Proj. Engr: Schultz, Konrad |
Route: |
I-10
map
|
Contractor: Jb Group of La, LLC Dba Infras |
Miles:
| 0.96 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-08-11 |
$1,832,951 |
Fall of 2024 |
District 07
No districtwide projects.