Projects Under Construction

District 07

    Updated 4 Jul 2022

Districtwide Projects

Calcasieu Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 12 Bridges
H.000428.6 - New location/replacement of bridge
Proj. Engr: Dyke, Clint Route: LA 12 map
Contractor: Gilchrist Construction Company Miles: 2.11
Work Order Date Contract Amount Estimated Completion Date
2018-09-22 $24,570,448 Beginning of 2023


I-10: Texas State Line - E. of Coone Gullly
H.003184.6 - Concrete new pavement
Proj. Engr: Ponthieux, Vicki Route: I-10 map
Contractor: Johnson Bros. Corp. a Southlan Miles: 10.55
Work Order Date Contract Amount Estimated Completion Date
2020-08-17 $152,227,800 Spring of 2025


US 171: Calcasieu River Bridge Repairs (Hbi)
H.010000.6 - Bridge painting
Proj. Engr: Thevis, Tyson Route: US 171 map
Contractor: Seminole Equipment, Inc. Miles: 1.09
Work Order Date Contract Amount Estimated Completion Date
2021-10-11 $4,814,697 Beginning of 2023


I-210: Ryan St Intg - E Jct I-10
H.010865.6 - Miscellaneous
Proj. Engr: Thevis, Tyson Route: I-210 map
Contractor: Prairie Contractors LLC Miles: 6.20
Work Order Date Contract Amount Estimated Completion Date
2021-10-04 $10,142,293 Beginning of 2023


LA 108: La 1256 - I-10
H.012589.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Ponthieux, Vicki Route: LA 27 LA 108 map
Contractor: R. E. Heidt Construction Co., Miles: 5.00
Work Order Date Contract Amount Estimated Completion Date
2022-02-14 $4,914,417 Fall of 2022


LA 14 @ La 397 Roundabout
H.013344.6 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Schultz, Konrad Route: LA 14 map
Contractor: Siema Construction, LLC Miles: 0.46
Work Order Date Contract Amount Estimated Completion Date
2022-03-14 $3,650,000 Fall of 2022


LA 109: La 12 - Beauregard P/L
H.014484.6 - Asphalt widening and overlay
Proj. Engr: Ponthieux, Vicki Route: LA 109 map
Contractor: R. E. Heidt Construction Co., Miles: 5.84
Work Order Date Contract Amount Estimated Completion Date
2022-05-16 $3,598,078 Spring of 2023


LA 378:calcasieu Rvr West Fork Mb Re(Hbi)
H.014544.6 - Moveable bridges reconditioned
Proj. Engr: Thevis, Tyson Route: LA 378 map
Contractor: C.E.C., Inc. Miles: 0.30
Work Order Date Contract Amount Estimated Completion Date
2021-08-11 $330,000 Summer of 2022


Cameron Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 384: La 1144 - Calcasieu P/L
H.014147.6 - Microsurfacing
Proj. Engr: Schultz, Konrad Route: LA 384 map
Contractor: Vance Brothers Inc. Miles: 4.18
Work Order Date Contract Amount Estimated Completion Date
2022-05-09 $485,901 Summer of 2022


LA 384: Icww Mb Repair (Grand Lake)(Hbi)
H.014550.6 - Moveable bridges reconditioned
Proj. Engr: Thevis, Tyson Route: LA 384 map
Contractor: Guinn Construction, LLC Miles: 0.30
Work Order Date Contract Amount Estimated Completion Date
2021-12-13 $519,405 Spring of 2022


LA 27: Cameron Ferry Landing Repairs
H.014551.6 - Ferries/ferry landings
Proj. Engr: Thevis, Tyson Route: LA 27 map
Contractor: C.E.C., Inc. Miles: 0.50
Work Order Date Contract Amount Estimated Completion Date
2021-07-08 $1,283,670 Summer of 2022


Jefferson Davis Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

US 90: Bayou Bridge
H.009486.6-R1 - New location/replacement of bridge
Proj. Engr: Schultz, Konrad Route: US 90 map
Contractor: Brown Industrial Construction, Miles: 0.17
Work Order Date Contract Amount Estimated Completion Date
2022-03-01 $2,194,095 Fall of 2022


LA 99 & La 102: W La 102 - La 26
H.014114.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Schultz, Konrad Route: LA 99 LA 102 map
Contractor: R. E. Heidt Construction Co., Miles: 10.28
Work Order Date Contract Amount Estimated Completion Date
2022-04-16 $5,212,401 Beginning of 2023


District 07

No districtwide projects.