Projects Under Construction

District 07

    Updated 18 Apr 2025

Districtwide Projects

Allen Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

Town of Oberlin Sidewalks
H.009298.6 - Miscellaneous
Proj. Engr: Guidry, Blake Route: LA 26 LA 1151 map
Contractor: Cape Construction, LLC Miles: 0.67
Work Order Date Contract Amount Estimated Completion Date
2024-03-01 $769,163 Beginning of 2025


Calcasieu Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

I-10: Texas State Line - E. of Coone Gullly
H.003184.6 - Concrete new pavement
Proj. Engr: Ponthieux, Vicki Route: I-10 map
Contractor: Johnson Bros. Corp. a Southlan Miles: 10.55
Work Order Date Contract Amount Estimated Completion Date
2020-08-17 $153,997,480 End of 2025


Calcasieu River Bridge (Hbi)
H.003931.6 - New location/replacement of bridge
Proj. Engr: Buckel, Brian Route: I-10 LA 378 map
Contractor: Calcasieu Bridge Partners LLC Miles: 7.68
Work Order Date Contract Amount Estimated Completion Date
2024-08-15 $1,096,274,027 Spring of 2033


Nelson Road Extension and Bridge
H.005967.6-R1 - New location/replacement of bridge
Proj. Engr: Thevis, Tyson Route: LA 1138-1 map
Contractor: Johnson Bros. Corp. a Southlan Miles: 1.00
Work Order Date Contract Amount Estimated Completion Date
2023-03-01 $102,057,110 Beginning of 2027


LA 14: Power Center Pkwy - US 90
H.014485.6 - Asphalt overlay of concrete pavement
Proj. Engr: Thevis, Tyson Route: LA 14 US 171 map
Contractor: Progressive Construction Co., Miles: 3.31
Work Order Date Contract Amount Estimated Completion Date
2024-09-06 $11,250,383 Spring of 2026


LA 3059: Goos Ferry Rd - Red Marceaux Rd
H.014815.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Dyke, Clint Route: LA 3059 map
Contractor: Prairie Contractors LLC Miles: 3.95
Work Order Date Contract Amount Estimated Completion Date
2025-02-14 $2,177,851 Spring of 2025


LA 397: US 90 - 400' N Lebleu Cemetery Rd
H.015278.6-R1 - Asphalt overlay of concrete pavement
Proj. Engr: Thevis, Tyson Route: LA 397 map
Contractor: Siema Construction, LLC Miles: 1.26
Work Order Date Contract Amount Estimated Completion Date
2025-02-03 $2,170,931 Fall of 2025


LA 397: Gayle Rd - La 27
H.015286.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Thevis, Tyson Route: LA 397 map
Contractor: R. E. Heidt Construction Co., Miles: 3.92
Work Order Date Contract Amount Estimated Completion Date
2024-11-22 $3,262,706 Spring of 2025


I-210 Hurricane Laura Lighting Repairs
H.015598.6 - Roadway lighting
Proj. Engr: Thevis, Tyson Route: I-210 map
Contractor: Kiewit Louisiana Co. Miles: 3.31
Work Order Date Contract Amount Estimated Completion Date
2024-10-10 $8,093,335 Fall of 2025


Cameron Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 717: Klondike Canal and Bayou Bridges
H.013970.6 - New location/replacement of bridge
Proj. Engr: Thevis, Tyson Route: LA 717 map
Contractor: Guinn Construction, LLC Miles: 0.26
Work Order Date Contract Amount Estimated Completion Date
2023-12-15 $5,577,249 Fall of 2025


LA 82: G Chenier & Superior Mb Rep (Hbi)
H.014549.6 - Moveable bridges reconditioned
Proj. Engr: Schultz, Konrad Route: LA 82 map
Contractor: C.E.C., Inc. Miles: 0.34
Work Order Date Contract Amount Estimated Completion Date
2022-12-03 $2,232,164 Spring of 2025


LA 82: Dyson Rd - 0.9 Mi E of N Island Rd
H.014809.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Thevis, Tyson Route: LA 82 map
Contractor: R. E. Heidt Construction Co., Miles: 10.00
Work Order Date Contract Amount Estimated Completion Date
2024-09-05 $8,291,904 Beginning of 2026


LA 1143: La 27 - Muria Rd
H.014870.6 - Asphalt widening and overlay
Proj. Engr: Thevis, Tyson Route: LA 1143 map
Contractor: Prairie Contractors LLC Miles: 7.10
Work Order Date Contract Amount Estimated Completion Date
2025-04-15 $4,197,730 Fall of 2025


Jefferson Davis Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

I-10 Overpass Over US 165 & Mp R.R
H.002980.6-R1 - New location/replacement of bridge
Proj. Engr: Schultz, Konrad Route: I-10 map
Contractor: Gilchrist Construction Company Miles: 2.15
Work Order Date Contract Amount Estimated Completion Date
2022-08-14 $76,171,828 Beginning of 2026


LA 26: Left Turn Lanes @ S. Frontage Rd.
H.013826.6 - Planning study
Proj. Engr: Schultz, Konrad Route: LA 26 map
Contractor: Siema Construction, LLC Miles: 0.16
Work Order Date Contract Amount Estimated Completion Date
2023-09-10 $858,460 Spring of 2025


I-10: La 97 (Jennings) Intchg Lighting
H.014272.6 - Roadway lighting
Proj. Engr: Schultz, Konrad Route: I-10 map
Contractor: Ernest P. Breaux Electrical, L Miles: 1.00
Work Order Date Contract Amount Estimated Completion Date
2024-02-14 $1,746,589 Beginning of 2026


I-10: La 26 (Jennings) Intchg Lighting
H.014286.6 - Roadway lighting
Proj. Engr: Schultz, Konrad Route: I-10 map
Contractor: Jb Group of La, LLC Dba Infras Miles: 0.96
Work Order Date Contract Amount Estimated Completion Date
2023-08-11 $1,832,951 Beginning of 2026


I-10: La 99 (Welsh) Intchg Lighting
H.014287.6 - Roadway lighting
Proj. Engr: Schultz, Konrad Route: I-10 map
Contractor: Ernest P. Breaux Electrical, L Miles: 0.80
Work Order Date Contract Amount Estimated Completion Date
2024-08-20 $1,525,649 Summer of 2026


LA 3166: La 1126 - Castex Landing
H.015287.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Schultz, Konrad Route: LA 3166 map
Contractor: R. E. Heidt Construction Co., Miles: 1.82
Work Order Date Contract Amount Estimated Completion Date
2025-01-22 $727,354 Spring of 2025


US 90 & La 97: Asphalt Overlays
H.015358.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Schultz, Konrad Route: US 90 map
Contractor: Prairie Contractors LLC Miles: 1.83
Work Order Date Contract Amount Estimated Completion Date
2024-08-06 $2,308,134 Summer of 2025


District 07

No districtwide projects.