Districtwide Projects
Beauregard Parish
Note: The estimated completion date is based
on the work order date and the contract
days allowed.
Unavoidable contingencies and unforeseen events
often develop during construction, which may
impact the actual completion date.
LA 389: Monroe Whitman Rd - Blackmon Ln |
H.010245.6 - Asphalt widening and overlay
|
Proj. Engr: Dyke, Clint |
Route: |
LA 389
map
|
Contractor: Prairie Contractors LLC |
Miles:
| 12.07 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-10-09 |
$7,845,158 |
Summer of 2023 |
LA 112: La 399 - La 113 |
H.010246.6 - Asphalt widening and overlay
|
Proj. Engr: Dyke, Clint |
Route: |
LA 112
map
|
Contractor: Prairie Contractors LLC |
Miles:
| 4.65 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-08-13 |
$3,754,042 |
Spring of 2023 |
Calcasieu Parish
Note: The estimated completion date is based
on the work order date and the contract
days allowed.
Unavoidable contingencies and unforeseen events
often develop during construction, which may
impact the actual completion date.
LA 12 Bridges |
H.000428.6 - New location/replacement of bridge
|
Proj. Engr: Dyke, Clint |
Route: |
LA 12
map
|
Contractor: Gilchrist Construction Company |
Miles:
| 2.11 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2018-09-22 |
$24,686,278 |
Spring of 2023 |
I-10: Texas State Line - E. of Coone Gullly |
H.003184.6 - Concrete new pavement
|
Proj. Engr: Ponthieux, Vicki |
Route: |
I-10
map
|
Contractor: Johnson Bros. Corp. a Southlan |
Miles:
| 10.55 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2020-08-17 |
$153,600,383 |
Spring of 2025 |
I-210: Ryan St Intg - E Jct I-10 |
H.010865.6 - Miscellaneous
|
Proj. Engr: Thevis, Tyson |
Route: |
I-210
map
|
Contractor: Prairie Contractors LLC |
Miles:
| 6.20 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2021-10-04 |
$10,149,443 |
Spring of 2023 |
LA 108: La 1256 - I-10 |
H.012589.6 - Asphalt overlay of asphalt pavement
|
Proj. Engr: Ponthieux, Vicki |
Route: |
LA 27 LA 108
map
|
Contractor: R. E. Heidt Construction Co., |
Miles:
| 5.00 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-02-14 |
$5,307,513 |
Spring of 2023 |
LA 14 @ La 397 Roundabout |
H.013344.6 - Traffic flow improvements - formerly turn lanes
|
Proj. Engr: Schultz, Konrad |
Route: |
LA 14
map
|
Contractor: Siema Construction, LLC |
Miles:
| 0.46 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-03-14 |
$3,745,704 |
Summer of 2023 |
LA 109: La 12 - Beauregard P/L |
H.014484.6 - Asphalt widening and overlay
|
Proj. Engr: Ponthieux, Vicki |
Route: |
LA 109
map
|
Contractor: R. E. Heidt Construction Co., |
Miles:
| 5.84 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-05-16 |
$3,598,078 |
Summer of 2023 |
LA 378:calcasieu Rvr West Fork Mb Re(Hbi) |
H.014544.6 - Moveable bridges reconditioned
|
Proj. Engr: Thevis, Tyson |
Route: |
LA 378
map
|
Contractor: C.E.C., Inc. |
Miles:
| 0.30 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2021-08-11 |
$330,000 |
Summer of 2022 |
I-10 / I-210: Fence Repair |
H.014974.6 - Fencing
|
Proj. Engr: Ponthieux, Vicki |
Route: |
I-10 I-210
map
|
Contractor: Southern Style Services LLC |
Miles:
| 26.47 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-12-05 |
$988,259 |
Summer of 2023 |
I-10 & I-210 Laura Sign Replacement |
H.015037.6 - Signing
|
Proj. Engr: Thevis, Tyson |
Route: |
I-210 I-10
map
|
Contractor: Tlp Construction Co. LLC |
Miles:
| 1.75 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-12-22 |
$846,864 |
Summer of 2024 |
Hurricane Laura Signal Upgrade |
H.015038.6 - Signalization
|
Proj. Engr: Thevis, Tyson |
Route: |
LA 14
map
|
Contractor: Ernest P. Breaux Electrical, L |
Miles:
| 0.59 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-02-13 |
$933,343 |
Fall of 2023 |
Cameron Parish
Note: The estimated completion date is based
on the work order date and the contract
days allowed.
Unavoidable contingencies and unforeseen events
often develop during construction, which may
impact the actual completion date.
LA 384: Canal Bridge |
H.013963.6 - New location/replacement of bridge
|
Proj. Engr: Thevis, Tyson |
Route: |
LA 384
map
|
Contractor: Guinn Construction, LLC |
Miles:
| 0.06 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-11-28 |
$849,950 |
Spring of 2023 |
LA 82: G Chenier & Superior Mb Rep (Hbi) |
H.014549.6 - Moveable bridges reconditioned
|
Proj. Engr: Schultz, Konrad |
Route: |
LA 82
map
|
Contractor: C.E.C., Inc. |
Miles:
| 0.34 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-12-03 |
$1,956,116 |
Beginning of 2024 |
Jefferson Davis Parish
Note: The estimated completion date is based
on the work order date and the contract
days allowed.
Unavoidable contingencies and unforeseen events
often develop during construction, which may
impact the actual completion date.
I-10 Overpass Over US 165 & Mp R.R |
H.002980.6-R1 - New location/replacement of bridge
|
Proj. Engr: Schultz, Konrad |
Route: |
I-10
map
|
Contractor: Gilchrist Construction Company |
Miles:
| 2.15 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-08-14 |
$75,817,922 |
Summer of 2025 |
US 165: 0.85 Mi N I-10 - Allen P/L |
H.013255.6 - Asphalt overlay of asphalt pavement
|
Proj. Engr: Schultz, Konrad |
Route: |
US 165
map
|
Contractor: Prairie Contractors LLC |
Miles:
| 13.63 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-02-05 |
$10,213,823 |
Summer of 2024 |
District 07