Projects Under Construction

District 07

    Updated 24 Mar 2023

Districtwide Projects

Beauregard Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 389: Monroe Whitman Rd - Blackmon Ln
H.010245.6 - Asphalt widening and overlay
Proj. Engr: Dyke, Clint Route: LA 389 map
Contractor: Prairie Contractors LLC Miles: 12.07
Work Order Date Contract Amount Estimated Completion Date
2022-10-09 $7,845,158 Summer of 2023


LA 112: La 399 - La 113
H.010246.6 - Asphalt widening and overlay
Proj. Engr: Dyke, Clint Route: LA 112 map
Contractor: Prairie Contractors LLC Miles: 4.65
Work Order Date Contract Amount Estimated Completion Date
2022-08-13 $3,754,042 Spring of 2023


Calcasieu Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 12 Bridges
H.000428.6 - New location/replacement of bridge
Proj. Engr: Dyke, Clint Route: LA 12 map
Contractor: Gilchrist Construction Company Miles: 2.11
Work Order Date Contract Amount Estimated Completion Date
2018-09-22 $24,686,278 Spring of 2023


I-10: Texas State Line - E. of Coone Gullly
H.003184.6 - Concrete new pavement
Proj. Engr: Ponthieux, Vicki Route: I-10 map
Contractor: Johnson Bros. Corp. a Southlan Miles: 10.55
Work Order Date Contract Amount Estimated Completion Date
2020-08-17 $153,600,383 Spring of 2025


I-210: Ryan St Intg - E Jct I-10
H.010865.6 - Miscellaneous
Proj. Engr: Thevis, Tyson Route: I-210 map
Contractor: Prairie Contractors LLC Miles: 6.20
Work Order Date Contract Amount Estimated Completion Date
2021-10-04 $10,149,443 Spring of 2023


LA 108: La 1256 - I-10
H.012589.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Ponthieux, Vicki Route: LA 27 LA 108 map
Contractor: R. E. Heidt Construction Co., Miles: 5.00
Work Order Date Contract Amount Estimated Completion Date
2022-02-14 $5,307,513 Spring of 2023


LA 14 @ La 397 Roundabout
H.013344.6 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Schultz, Konrad Route: LA 14 map
Contractor: Siema Construction, LLC Miles: 0.46
Work Order Date Contract Amount Estimated Completion Date
2022-03-14 $3,745,704 Summer of 2023


LA 109: La 12 - Beauregard P/L
H.014484.6 - Asphalt widening and overlay
Proj. Engr: Ponthieux, Vicki Route: LA 109 map
Contractor: R. E. Heidt Construction Co., Miles: 5.84
Work Order Date Contract Amount Estimated Completion Date
2022-05-16 $3,598,078 Summer of 2023


LA 378:calcasieu Rvr West Fork Mb Re(Hbi)
H.014544.6 - Moveable bridges reconditioned
Proj. Engr: Thevis, Tyson Route: LA 378 map
Contractor: C.E.C., Inc. Miles: 0.30
Work Order Date Contract Amount Estimated Completion Date
2021-08-11 $330,000 Summer of 2022


I-10 / I-210: Fence Repair
H.014974.6 - Fencing
Proj. Engr: Ponthieux, Vicki Route: I-10 I-210 map
Contractor: Southern Style Services LLC Miles: 26.47
Work Order Date Contract Amount Estimated Completion Date
2022-12-05 $988,259 Summer of 2023


I-10 & I-210 Laura Sign Replacement
H.015037.6 - Signing
Proj. Engr: Thevis, Tyson Route: I-210 I-10 map
Contractor: Tlp Construction Co. LLC Miles: 1.75
Work Order Date Contract Amount Estimated Completion Date
2022-12-22 $846,864 Summer of 2024


Hurricane Laura Signal Upgrade
H.015038.6 - Signalization
Proj. Engr: Thevis, Tyson Route: LA 14 map
Contractor: Ernest P. Breaux Electrical, L Miles: 0.59
Work Order Date Contract Amount Estimated Completion Date
2023-02-13 $933,343 Fall of 2023


Cameron Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 384: Canal Bridge
H.013963.6 - New location/replacement of bridge
Proj. Engr: Thevis, Tyson Route: LA 384 map
Contractor: Guinn Construction, LLC Miles: 0.06
Work Order Date Contract Amount Estimated Completion Date
2022-11-28 $849,950 Spring of 2023


LA 82: G Chenier & Superior Mb Rep (Hbi)
H.014549.6 - Moveable bridges reconditioned
Proj. Engr: Schultz, Konrad Route: LA 82 map
Contractor: C.E.C., Inc. Miles: 0.34
Work Order Date Contract Amount Estimated Completion Date
2022-12-03 $1,956,116 Beginning of 2024


Jefferson Davis Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

I-10 Overpass Over US 165 & Mp R.R
H.002980.6-R1 - New location/replacement of bridge
Proj. Engr: Schultz, Konrad Route: I-10 map
Contractor: Gilchrist Construction Company Miles: 2.15
Work Order Date Contract Amount Estimated Completion Date
2022-08-14 $75,817,922 Summer of 2025


US 165: 0.85 Mi N I-10 - Allen P/L
H.013255.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Schultz, Konrad Route: US 165 map
Contractor: Prairie Contractors LLC Miles: 13.63
Work Order Date Contract Amount Estimated Completion Date
2023-02-05 $10,213,823 Summer of 2024


District 07

No districtwide projects.