Projects Under Construction

District 61

    Updated 19 Apr 2024

Districtwide Projects

Ascension Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 44: Widening and Roundabout at La 941
H.010909.6 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Lobell, Scott Route: LA 44 LA 941 map
Contractor: Kcr Contractors, LLC Miles: 1.34
Work Order Date Contract Amount Estimated Completion Date
2021-08-29 $6,238,599 Fall of 2022


LA 30 Roundabouts @ Tanger Mall & I-10
H.010960.6-R1 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Dunn, Marc Route: LA 30 I-10 map
Contractor: Barriere Construction Co., LLC Miles: 1.71
Work Order Date Contract Amount Estimated Completion Date
2024-02-01 $28,998,998 Fall of 2026


I-10: US 61 to Laplace ITS Deployment
H.013710.6 - ITS and emergency operations
Proj. Engr: Moore, Tony Route: I-10 map
Contractor: Grady Crawford Const. Co., Inc Miles: 19.87
Work Order Date Contract Amount Estimated Completion Date
2021-08-20 $3,986,855 Beginning of 2023


Ascension Parish Overlay Program
H.014704.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Burst, Jeff Route: LA 939 map
Contractor: R.J. Daigle & Sons Contractors Miles: 9.35
Work Order Date Contract Amount Estimated Completion Date
2023-02-13 $3,884,239 Beginning of 2024


US 61: La 74 - La 42
H.014865.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Dunn, Nicole Route: US 61 map
Contractor: Barriere Construction Co., LLC Miles: 5.31
Work Order Date Contract Amount Estimated Completion Date
2023-12-14 $12,798,121 Summer of 2026


Assumption Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

Napoleonville Linear Park
H.007386.6 - Sidewalks/bike paths
Proj. Engr: Lobell, Scott Route: LA 1 map
Contractor: LA Contracting Enterprise LLC Miles: 0.06
Work Order Date Contract Amount Estimated Completion Date
2021-01-14 $190,194 Fall of 2021


LA 70: La 1 - La 1015-1
H.012575.6-R1 - Asphalt overlay of asphalt pavement
Proj. Engr: Dunn, Nicole Route: LA 70 map
Contractor: Barber Bros. Contracting Co., Miles: 12.64
Work Order Date Contract Amount Estimated Completion Date
2022-12-18 $15,315,312 Summer of 2024


East Baton Rouge Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

Comite River Diversion Bridge
H.000710.6-R2 - New location/replacement of bridge
Proj. Engr: Payne, Roy Route: LA 964
Contractor: Brown Industrial Construction, Miles: 0.42
Work Order Date Contract Amount Estimated Completion Date
2022-06-01 $25,327,090 Spring of 2024


North Sherwood Forest Drive Improvements
H.002301.6 - Concrete new pavement
Proj. Engr: Olson, Mike Route: LA 37 map
Contractor: Command Construction Industrie Miles: 1.68
Work Order Date Contract Amount Estimated Completion Date
2019-11-01 $13,503,859 Spring of 2023


Pecue Lane/I-10 Interchange Phase Iii
H.003047.6 - New location/replacement of bridge
Proj. Engr: Payne, Roy Route: I-10 map
Contractor: Brown Industrial Construction, Miles: 0.87
Work Order Date Contract Amount Estimated Completion Date
2023-03-17 $71,282,527 Summer of 2026


Ebr Computerized Traffic Signal, Ph Vb
H.007160.6 - Signalization
Proj. Engr: Payne, Roy Route: LA 3164 map
Contractor: Ernest P. Breaux Electrical, L Miles: 0.32
Work Order Date Contract Amount Estimated Completion Date
2021-02-08 $5,924,402 Summer of 2022


Blackwater Bayou Bridge
H.007963.6 - New location/replacement of bridge
Proj. Engr: Sam, Desmond Route: LA 410 map
Contractor: Coastal Contractors, LLC Miles: 0.32
Work Order Date Contract Amount Estimated Completion Date
2022-10-01 $5,300,434 Fall of 2023


LA 73: US 61 (Airline) - Essen Lane
H.010652.6 - Portland Cement Pavement patch
Proj. Engr: Sam, Desmond Route: LA 73 map
Contractor: Merrick, LLC Miles: 2.27
Work Order Date Contract Amount Estimated Completion Date
2023-08-26 $19,343,392 Beginning of 2026


D61: Chip & Removal of H. Isaac Veg. Debris
H.010717.6 - Miscellaneous
Proj. Engr: Zzzz Vosburg, Chad Route: US 61 LA 415 map
Contractor: Hensley R. Lee Contracting Inc Miles: 0.04
Work Order Date Contract Amount Estimated Completion Date
2013-07-22 $61,429 Fall of 2013


LA 30: South Blvd to W Chimes St
H.011098.6 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Divittorio, Alanna Route: LA 30 I-10 map
Contractor: Command Construction Industrie Miles: 2.05
Work Order Date Contract Amount Estimated Completion Date
2022-07-05 $18,359,028 Fall of 2024


Quail Dr: Turn Lane at Perkins (La 427)
H.011496.6 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Cheng, Guangziang Route: map
Contractor: Industrial Enterprises, Inc. Miles: 0.01
Work Order Date Contract Amount Estimated Completion Date
2021-04-12 $397,400 Beginning of 2022


I-10 (Constitution/Bunker Hill): Curve
H.011757 - Miscellaneous
Proj. Engr: Zzzz Chatelain, Jeff Route: I-10 map
Contractor: Barber Bros. Contracting Co., Miles: 0.06
Work Order Date Contract Amount Estimated Completion Date
2015-08-08 $119,767 Fall of 2015


LA 3064 to Bluebonnet Blvd. Phase II
H.012232.6 - Asphalt new pavement-new roadway/new alignments
Proj. Engr: Branch, David Route: I-10 map
Contractor: Boone Services LLC Miles: 0.49
Work Order Date Contract Amount Estimated Completion Date
2023-09-18 $17,048,770 Summer of 2025


LA 3064 to La 1248 Phase I Dijon Drive Extension
H.012233.6 - Asphalt new pavement-new roadway/new alignments
Proj. Engr: Zzzz Guidry, Blake Route: LA 3064 map
Contractor: Brown Industrial Construction, Miles: 0.10
Work Order Date Contract Amount Estimated Completion Date
2018-07-23 $8,079,765 Fall of 2020


I-110 ITS Deployment
H.013261.6 - ITS and emergency operations
Proj. Engr: Divittorio, Alanna Route: I-110 map
Contractor: Ozark Traffic Management, LLC Miles: 9.06
Work Order Date Contract Amount Estimated Completion Date
2020-08-26 $1,331,184 Fall of 2022


Pecue Lane/I-10 Interchange Phase Ii: Bridges Over I-10
H.013579.6 - New location/replacement of bridge
Proj. Engr: Collier, Zachary Route: I-10 map
Contractor: James Construction Group LLC Miles: 1.22
Work Order Date Contract Amount Estimated Completion Date
2019-06-02 $16,933,599 Summer of 2022


I-10 & I-12 College Dr Flyover Ramp
H.013897.6 - New location/replacement of bridge
Proj. Engr: Nelson, Gordon Route: I-10 I-12 map
Contractor: Boh Bros. Construction Co., Ll Miles: 2.61
Work Order Date Contract Amount Estimated Completion Date
2020-08-25 $61,319,183 Fall of 2024


LA 408: I-110 - End of Concrete Section
H.014100.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Sam, Desmond Route: LA 408 map
Contractor: Hard Rock Construction LLC Miles: 5.24
Work Order Date Contract Amount Estimated Completion Date
2023-04-03 $10,487,268 Beginning of 2025


I-10 Mississippi River Bridge Fender Repair (Pier 6)
H.014323.6 - Bridges reconditioned
Proj. Engr: Divittorio, Alanna Route: I-10 map
Contractor: Southern Road & Bridge, LLC Miles: 0.86
Work Order Date Contract Amount Estimated Completion Date
2022-05-14 $2,071,498 Beginning of 2024


I-10 Wb Off Ramp: Lt Turn Lane at Siegen
H.014506.6 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Sam, Desmond Route: I-10 map
Contractor: Gulf States Services, LLC Miles: 0.25
Work Order Date Contract Amount Estimated Completion Date
2023-05-01 $1,588,938 Fall of 2023


US 61: Int. Improvements at Alco Ave
H.015111.6 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Sam, Desmond Route: US 61 map
Contractor: Barber Bros. Contracting Co., Miles: 0.38
Work Order Date Contract Amount Estimated Completion Date
2023-09-18 $805,830 Beginning of 2024


East Feliciana Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

G.R. Repair Dist 02, 61, 62 (Hurric Ida)
H.015029.6 - Guardrails
Proj. Engr: Woods, Derek Route: LA 63 map
Contractor: Traffic Commander, LLC Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2023-08-10 $354,033 Beginning of 2024


Iberville Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 75: Bayou Breaux Bridge
H.009484.6 - New location/replacement of bridge
Proj. Engr: Dunn, Nicole Route: LA 75 map
Contractor: Tl Hawk, LLC Miles: 0.40
Work Order Date Contract Amount Estimated Completion Date
2021-04-08 $2,530,303 Beginning of 2022


LA 75: Restriping and Signs
H.010908.6 - Striping and pavement markers
Proj. Engr: Zzzz Thomas, Timothy Route: LA 75 map
Contractor: Jack B. Harper Contractor, LLC Miles: 1.93
Work Order Date Contract Amount Estimated Completion Date
2014-06-01 $49,990 Summer of 2014


I-10: Atch Basin Br - W Baton Rouge P/L
H.012588.6 - Asphalt new pavement-new roadway/new alignments
Proj. Engr: Zzzz Palermo, Keith Route: I-10 map
Contractor: Madden Contracting Co., LLC Miles: 6.26
Work Order Date Contract Amount Estimated Completion Date
2021-08-13 $20,915,597 Summer of 2023


LA 1: Bayou Plaquemine Br Strengthening
H.014608.6 - Bridges reconditioned
Proj. Engr: Chatelain, Jeff Route: LA 1 map
Contractor: Reliant Industrial Solutions L Miles: 0.09
Work Order Date Contract Amount Estimated Completion Date
2023-06-09 $294,598 Beginning of 2024


LA 1270: La77 to End of Control Section
H.014670.6 - Asphalt surface treatment
Proj. Engr: Lecoq, Dane Route: LA 1270 map
Contractor: Barber Bros. Contracting Co., Miles: 0.50
Work Order Date Contract Amount Estimated Completion Date
2024-03-01 $1,089,843 Summer of 2024


LA 30 @ La 3115 Traffic Signal
H.015108.6 - Signalization
Proj. Engr: Dunn, Nicole Route: LA 30 map
Contractor: Jack B. Harper Electrical LLC Miles: 0.01
Work Order Date Contract Amount Estimated Completion Date
2023-06-09 $243,686 Beginning of 2024


Pointe Coupee Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

Bayou Chenal & Bayou Discharge Bridges
H.002184.6-R1 - New location/replacement of bridge
Proj. Engr: Fremin, Dustin Route: LA 413 map
Contractor: Jb James Construction LLC Miles: 0.45
Work Order Date Contract Amount Estimated Completion Date
2022-06-16 $7,577,904 Beginning of 2025


LA 15: La 1 - Concordia P/L
H.010434.6 - Asph concrete ovly over in place stabilized/cement treated base course
Proj. Engr: Lecoq, Dane Route: LA 15 map
Contractor: Madden Gulf Coast, LLC Miles: 7.37
Work Order Date Contract Amount Estimated Completion Date
2023-09-05 $13,377,997 Fall of 2024


LA 78: US 190 - La 1
H.012936.6 - Asphalt surface treatment
Proj. Engr: Chatelain, Jeff Route: LA 78 map
Contractor: Barriere Construction Co., LLC Miles: 7.56
Work Order Date Contract Amount Estimated Completion Date
2023-08-14 $5,765,213 Spring of 2024


US 190: 0.5 Mi W of La 978 - La 976
H.013196.6 - Asphalt surface treatment
Proj. Engr: Chatelain, Jeff Route: US 190 map
Contractor: Barriere Construction Co., LLC Miles: 6.10
Work Order Date Contract Amount Estimated Completion Date
2023-05-13 $21,914,522 Summer of 2026


St. James Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 70: Sunshine Bridge - La 22
H.002424.6 - Asphalt new pavement-new roadway/new alignments
Proj. Engr: Dunn, Nicole Route: LA 70 map
Contractor: Gilchrist Construction Company Miles: 5.16
Work Order Date Contract Amount Estimated Completion Date
2023-03-01 $51,457,454 Summer of 2025


LA 20 Bayou Chevreuil Bridge
H.009481.6 - Bridges reconditioned
Proj. Engr: Dunn, Nicole Route: LA 20 map
Contractor: Tl Hawk, LLC Miles: 0.44
Work Order Date Contract Amount Estimated Completion Date
2020-06-15 $11,765,456 Summer of 2022


LA 20 Widen: La 307 - S. Vacherie
H.013116.6 - Asphalt widening and overlay
Proj. Engr: Elisar, Aaron Route: LA 20 map
Contractor: Barber Bros. Contracting Co., Miles: 3.20
Work Order Date Contract Amount Estimated Completion Date
2023-09-21 $19,855,533 Summer of 2026


West Baton Rouge Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 1: Port Allen Canal Br Repl (Ph1)(Hbi)
H.001234.6 - New location/replacement of bridge
Proj. Engr: Payne, Roy Route: LA 1 map
Contractor: Kiewit Louisiana Co. Miles: 2.49
Work Order Date Contract Amount Estimated Completion Date
2021-09-10 $82,642,569 Summer of 2025


Joliet Trail (Brusly)
H.012834.6 - Sidewalks/bike paths
Proj. Engr: Fremin, Dustin Route: LA 988 LA 1 map
Contractor: Industrial Enterprises, Inc. Miles: 1.52
Work Order Date Contract Amount Estimated Completion Date
2022-04-06 $991,986 Beginning of 2023


LA 1: La 75 - Port Allen Canal Br
H.013191.6 - Asphalt overlay of concrete pavement
Proj. Engr: Zzzz Palermo, Keith Route: LA 1 map
Contractor: Barber Bros. Contracting Co., Miles: 11.63
Work Order Date Contract Amount Estimated Completion Date
2020-09-16 $13,314,536 Fall of 2023


I-10 Wbr Queue Warning System
H.013482.6-R1 - ITS and emergency operations
Proj. Engr: Fremin, Dustin Route: I-10 map
Contractor: Diamond Electrical Co., Inc. Miles: 15.95
Work Order Date Contract Amount Estimated Completion Date
2023-04-06 $7,967,020 Fall of 2024


District 61

District 61: Thermoplastic Striping
H.011205 - Striping and pavement markers
Proj. Engr: Zzzz Chatelain, Jeff Route:
Contractor: Highway Graphics LLC Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2015-04-20 $286,609 Summer of 2015


District 61: Intersection Thermo Striping
H.011492 - Striping and pavement markers
Proj. Engr: Zzzz Chatelain, Jeff Route:
Contractor: Highway Graphics LLC Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2015-04-20 $225,887 Summer of 2015