Districtwide Projects
Ascension Parish
Note: The estimated completion date is based
on the work order date and the contract
days allowed.
Unavoidable contingencies and unforeseen events
often develop during construction, which may
impact the actual completion date.
LA 44: Widening and Roundabout at La 941 |
H.010909.6 - Traffic flow improvements - formerly turn lanes
|
Proj. Engr: Lobell, Scott |
Route: |
LA 44 LA 941
map
|
Contractor: Kcr Contractors, LLC |
Miles:
| 1.34 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2021-08-29 |
$6,238,599 |
Fall of 2022 |
LA 74: Iberville P/L - US 61 |
H.012713.6 - Asph concrete ovly over in place stabilized/cement treated base course
|
Proj. Engr: Lobell, Scott |
Route: |
LA 74
map
|
Contractor: Barriere Construction Co., LLC |
Miles:
| 7.02 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2021-10-03 |
$9,492,845 |
Beginning of 2023 |
I-10: US 61 to Laplace ITS Deployment |
H.013710.6 - ITS and emergency operations
|
Proj. Engr: Moore, Tony |
Route: |
I-10
map
|
Contractor: Grady Crawford Const. Co., Inc |
Miles:
| 19.87 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2021-08-20 |
$3,986,855 |
Beginning of 2023 |
LA 1: La 3089 - Iberville P/L |
H.014104.6 - Asphalt overlay of asphalt pavement
|
Proj. Engr: Lobell, Scott |
Route: |
LA 1
map
|
Contractor: Barber Bros. Contracting Co., |
Miles:
| 6.45 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-04-16 |
$3,267,595 |
Beginning of 2023 |
Ascension Parish Overlay Program |
H.014704.6 - Asphalt overlay of asphalt pavement
|
Proj. Engr: Burst, Jeff |
Route: |
LA 939
map
|
Contractor: R.J. Daigle & Sons Contractors |
Miles:
| 9.35 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-02-13 |
$3,797,650 |
End of 2023 |
Assumption Parish
Note: The estimated completion date is based
on the work order date and the contract
days allowed.
Unavoidable contingencies and unforeseen events
often develop during construction, which may
impact the actual completion date.
Napoleonville Linear Park |
H.007386.6 - Sidewalks/bike paths
|
Proj. Engr: Lobell, Scott |
Route: |
LA 1
map
|
Contractor: LA Contracting Enterprise LLC |
Miles:
| 0.06 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2021-01-14 |
$190,194 |
Fall of 2021 |
LA 70: La 1 - La 1015-1 |
H.012575.6-R1 - Asphalt overlay of asphalt pavement
|
Proj. Engr: Lobell, Scott |
Route: |
LA 70
map
|
Contractor: Barber Bros. Contracting Co., |
Miles:
| 12.64 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-12-18 |
$14,139,432 |
Summer of 2024 |
East Baton Rouge Parish
Note: The estimated completion date is based
on the work order date and the contract
days allowed.
Unavoidable contingencies and unforeseen events
often develop during construction, which may
impact the actual completion date.
Comite River Diversion Bridge |
H.000710.6-R2 - New location/replacement of bridge
|
Proj. Engr: Payne, Roy |
Route: |
LA 964
|
Contractor: Brown Industrial Construction, |
Miles:
| 0.42 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-06-01 |
$22,018,573 |
Spring of 2024 |
North Sherwood Forest Drive Improvements |
H.002301.6 - Concrete new pavement
|
Proj. Engr: Olson, Mike |
Route: |
LA 37
map
|
Contractor: Command Construction Industrie |
Miles:
| 1.68 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2019-11-01 |
$13,503,859 |
Spring of 2023 |
Pecue Lane/I-10 Interchange Phase Iii |
H.003047.6 - New location/replacement of bridge
|
Proj. Engr: Payne, Roy |
Route: |
I-10
map
|
Contractor: Brown Industrial Construction, |
Miles:
| 0.87 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-03-17 |
$70,936,045 |
Summer of 2026 |
Ebr Computerized Traffic Signal, Ph Vb |
H.007160.6 - Signalization
|
Proj. Engr: Payne, Roy |
Route: |
LA 3164
map
|
Contractor: Ernest P. Breaux Electrical, L |
Miles:
| 0.32 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2021-02-08 |
$5,562,614 |
Summer of 2022 |
Blackwater Bayou Bridge |
H.007963.6 - New location/replacement of bridge
|
Proj. Engr: Sam, Desmond |
Route: |
LA 410
map
|
Contractor: Coastal Contractors, LLC |
Miles:
| 0.32 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-10-01 |
$4,884,883 |
Summer of 2023 |
US 61: Jefferson Highway Overpass Repair |
H.009489.6 - New location/replacement of bridge
|
Proj. Engr: Sam, Desmond |
Route: |
US 61
map
|
Contractor: Coastal Contractors, LLC |
Miles:
| 0.06 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-08-01 |
$815,220 |
Summer of 2023 |
LA 73: US 61 (Airline) - Essen Lane |
H.010652.6 - Portland Cement Pavement patch
|
Proj. Engr: Sam, Desmond |
Route: |
LA 73
map
|
Contractor: Merrick, LLC |
Miles:
| 2.27 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-08-26 |
$18,293,607 |
Beginning of 2026 |
D61: Chip & Removal of H. Isaac Veg. Debris |
H.010717.6 - Miscellaneous
|
Proj. Engr: Zzzz Vosburg, Chad |
Route: |
US 61 LA 415
map
|
Contractor: Hensley R. Lee Contracting Inc |
Miles:
| 0.04 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2013-07-22 |
$61,429 |
Fall of 2013 |
LA 30: South Blvd to W Chimes St |
H.011098.6 - Traffic flow improvements - formerly turn lanes
|
Proj. Engr: Divittorio, Alanna |
Route: |
LA 30 I-10
map
|
Contractor: Command Construction Industrie |
Miles:
| 2.05 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-07-05 |
$18,577,009 |
Beginning of 2024 |
Quail Dr: Turn Lane at Perkins (La 427) |
H.011496.6 - Traffic flow improvements - formerly turn lanes
|
Proj. Engr: Cheng, Guangziang |
Route: |
map
|
Contractor: Industrial Enterprises, Inc. |
Miles:
| 0.01 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2021-04-12 |
$397,400 |
Beginning of 2022 |
I-10 (Constitution/Bunker Hill): Curve |
H.011757 - Miscellaneous
|
Proj. Engr: Zzzz Chatelain, Jeff |
Route: |
I-10
map
|
Contractor: Barber Bros. Contracting Co., |
Miles:
| 0.06 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2015-08-08 |
$119,767 |
Fall of 2015 |
LA 3064 to La 1248 Phase I Dijon Drive Extension |
H.012233.6 - Asphalt new pavement-new roadway/new alignments
|
Proj. Engr: Zzzz Guidry, Blake |
Route: |
LA 3064
map
|
Contractor: Brown Industrial Construction, |
Miles:
| 0.10 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2018-07-23 |
$8,079,765 |
Fall of 2020 |
I-110 ITS Deployment |
H.013261.6 - ITS and emergency operations
|
Proj. Engr: Divittorio, Alanna |
Route: |
I-110
map
|
Contractor: Ozark Traffic Management, LLC |
Miles:
| 9.06 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2020-08-26 |
$1,207,649 |
Fall of 2022 |
Pecue Lane/I-10 Interchange Phase Ii: Bridges Over I-10 |
H.013579.6 - New location/replacement of bridge
|
Proj. Engr: Collier, Zachary |
Route: |
I-10
map
|
Contractor: James Construction Group LLC |
Miles:
| 1.22 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2019-06-02 |
$16,933,599 |
Summer of 2022 |
I-10 & I-12 College Dr Flyover Ramp |
H.013897.6 - New location/replacement of bridge
|
Proj. Engr: Nelson, Gordon |
Route: |
I-10 I-12
map
|
Contractor: Boh Bros. Construction Co., Ll |
Miles:
| 2.61 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2020-08-25 |
$61,262,144 |
Fall of 2024 |
LA 408: I-110 - End of Concrete Section |
H.014100.6 - Asphalt overlay of asphalt pavement
|
Proj. Engr: Sam, Desmond |
Route: |
LA 408
map
|
Contractor: Hard Rock Construction LLC |
Miles:
| 5.24 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-04-03 |
$9,569,898 |
Fall of 2024 |
I-10 Mississippi River Bridge Fender Repair (Pier 6) |
H.014323.6 - Bridges reconditioned
|
Proj. Engr: Divittorio, Alanna |
Route: |
I-10
map
|
Contractor: Southern Road & Bridge, LLC |
Miles:
| 0.86 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-05-14 |
$2,071,498 |
Beginning of 2024 |
LA 67: Rcut @ Blount Rd |
H.014408.6 - Concrete new pavement
|
Proj. Engr: Divittorio, Alanna |
Route: |
LA 67
map
|
Contractor: Briggs Brothers Enterprises Co |
Miles:
| 0.30 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-09-09 |
$480,445 |
Beginning of 2023 |
I-10 Wb Off Ramp: Lt Turn Lane at Siegen |
H.014506.6 - Traffic flow improvements - formerly turn lanes
|
Proj. Engr: Sam, Desmond |
Route: |
I-10
map
|
Contractor: Gulf States Services, LLC |
Miles:
| 0.25 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-05-01 |
$1,404,108 |
Summer of 2023 |
LA 426: La 73 - Sherwood Forest |
H.014694.6 - Portland Cement Pavement patch
|
Proj. Engr: Divittorio, Alanna |
Route: |
LA 426
map
|
Contractor: Cape Construction, LLC |
Miles:
| 3.14 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-09-09 |
$1,886,625 |
Summer of 2023 |
LA 64: US 61 - Barnett Rd |
H.014697.6 - Asphalt overlay of asphalt pavement
|
Proj. Engr: Sam, Desmond |
Route: |
LA 64-1
map
|
Contractor: Barriere Construction Co., LLC |
Miles:
| 1.98 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-07-14 |
$1,460,003 |
Fall of 2023 |
US 61: Int. Improvements at Alco Ave |
H.015111.6 - Traffic flow improvements - formerly turn lanes
|
Proj. Engr: Sam, Desmond |
Route: |
US 61
map
|
Contractor: Barber Bros. Contracting Co., |
Miles:
| 0.38 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-09-18 |
$626,436 |
Beginning of 2024 |
East Feliciana Parish
Note: The estimated completion date is based
on the work order date and the contract
days allowed.
Unavoidable contingencies and unforeseen events
often develop during construction, which may
impact the actual completion date.
LA 961: Sandy Creek Bridge |
H.013955.6 - New location/replacement of bridge
|
Proj. Engr: Lecoq, Dane |
Route: |
LA 961
map
|
Contractor: Brown Industrial Construction, |
Miles:
| 0.10 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-11-14 |
$2,273,783 |
Fall of 2023 |
Rumble Strips: District 61 - Area B |
H.015007.6 - Miscellaneous
|
Proj. Engr: Lecoq, Dane |
Route: |
LA 964 LA 68
map
|
Contractor: Highway Graphics LLC |
Miles:
| 46.63 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-07-05 |
$1,278,918 |
Fall of 2023 |
G.R. Repair Dist 02, 61, 62 (Hurric Ida) |
H.015029.6 - Guardrails
|
Proj. Engr: Burgess, Matthew |
Route: |
LA 63
map
|
Contractor: Traffic Commander, LLC |
Miles:
| 0.00 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-08-10 |
$326,349 |
Beginning of 2024 |
Iberville Parish
Note: The estimated completion date is based
on the work order date and the contract
days allowed.
Unavoidable contingencies and unforeseen events
often develop during construction, which may
impact the actual completion date.
LA 75: Bayou Breaux Bridge |
H.009484.6 - New location/replacement of bridge
|
Proj. Engr: Lobell, Scott |
Route: |
LA 75
map
|
Contractor: Tl Hawk, LLC |
Miles:
| 0.40 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2021-04-08 |
$2,467,237 |
Beginning of 2022 |
LA 75: Restriping and Signs |
H.010908.6 - Striping and pavement markers
|
Proj. Engr: Zzzz Thomas, Timothy |
Route: |
LA 75
map
|
Contractor: Jack B. Harper Contractor, LLC |
Miles:
| 1.93 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2014-06-01 |
$49,990 |
Summer of 2014 |
I-10: Atch Basin Br - W Baton Rouge P/L |
H.012588.6 - Asphalt new pavement-new roadway/new alignments
|
Proj. Engr: Zzzz Palermo, Keith |
Route: |
I-10
map
|
Contractor: Madden Contracting Co., LLC |
Miles:
| 6.26 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2021-08-13 |
$20,903,949 |
Summer of 2023 |
LA 1 @ Evergreen: Uprr Xing (Iberville) |
H.014466.6 - Railroads
|
Proj. Engr: Lobell, Scott |
Route: |
LA 1
map
|
Contractor: Barber Bros. Contracting Co., |
Miles:
| 2.15 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-02-17 |
$1,186,733 |
Spring of 2023 |
LA 1: Bayou Plaquemine Br Strengthening |
H.014608.6 - Bridges reconditioned
|
Proj. Engr: Chatelain, Jeff |
Route: |
LA 1
map
|
Contractor: Reliant Industrial Solutions L |
Miles:
| 0.09 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-06-09 |
$258,463 |
Beginning of 2024 |
LA 30 @ La 3115 Traffic Signal |
H.015108.6 - Signalization
|
Proj. Engr: Dunn, Nicole |
Route: |
LA 30
map
|
Contractor: Jack B. Harper Electrical LLC |
Miles:
| 0.01 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-06-09 |
$243,686 |
Beginning of 2024 |
Pointe Coupee Parish
Note: The estimated completion date is based
on the work order date and the contract
days allowed.
Unavoidable contingencies and unforeseen events
often develop during construction, which may
impact the actual completion date.
Bayou Chenal & Bayou Discharge Bridges |
H.002184.6-R1 - New location/replacement of bridge
|
Proj. Engr: Fremin, Dustin |
Route: |
LA 413
map
|
Contractor: Jb James Construction LLC |
Miles:
| 0.45 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-06-16 |
$7,568,149 |
Beginning of 2025 |
LA 15: La 1 - Concordia P/L |
H.010434.6 - Asph concrete ovly over in place stabilized/cement treated base course
|
Proj. Engr: Lecoq, Dane |
Route: |
LA 15
map
|
Contractor: Madden Gulf Coast, LLC |
Miles:
| 7.37 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-09-05 |
$13,377,997 |
Fall of 2024 |
LA 78: US 190 - La 1 |
H.012936.6 - Asphalt surface treatment
|
Proj. Engr: Chatelain, Jeff |
Route: |
LA 78
map
|
Contractor: Barriere Construction Co., LLC |
Miles:
| 7.56 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-08-14 |
$5,765,213 |
Spring of 2024 |
US 190: 0.5 Mi W of La 978 - La 976 |
H.013196.6 - Asphalt surface treatment
|
Proj. Engr: Chatelain, Jeff |
Route: |
US 190
map
|
Contractor: Barriere Construction Co., LLC |
Miles:
| 6.10 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-05-13 |
$21,822,076 |
Summer of 2026 |
LA 976: La 81 - US 190 |
H.015022.6 - Asph concrete ovly over in place stabilized/cement treated base course
|
Proj. Engr: Fremin, Dustin |
Route: |
LA 976 LA 81
map
|
Contractor: Barber Bros. Contracting Co., |
Miles:
| 0.69 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-12-18 |
$1,645,539 |
Spring of 2023 |
St. James Parish
Note: The estimated completion date is based
on the work order date and the contract
days allowed.
Unavoidable contingencies and unforeseen events
often develop during construction, which may
impact the actual completion date.
LA 70: Sunshine Bridge - La 22 |
H.002424.6 - Asphalt new pavement-new roadway/new alignments
|
Proj. Engr: Dunn, Nicole |
Route: |
LA 70
map
|
Contractor: Gilchrist Construction Company |
Miles:
| 5.16 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-03-01 |
$50,385,650 |
Summer of 2025 |
LA 20 Bayou Chevreuil Bridge |
H.009481.6 - Bridges reconditioned
|
Proj. Engr: Lobell, Scott |
Route: |
LA 20
map
|
Contractor: Tl Hawk, LLC |
Miles:
| 0.44 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2020-06-15 |
$11,765,456 |
Summer of 2022 |
LA 20 Widen: La 307 - S. Vacherie |
H.013116.6 - Asphalt widening and overlay
|
Proj. Engr: Elisar, Aaron |
Route: |
LA 20
map
|
Contractor: Barber Bros. Contracting Co., |
Miles:
| 3.20 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-09-21 |
$19,838,207 |
Summer of 2026 |
LA 70: Sunshine Bridge Pier 4 Fender Repair |
H.013946.6 - Bridges reconditioned
|
Proj. Engr: Lobell, Scott |
Route: |
LA 70
map
|
Contractor: Bo-Mac Contractors Ltd |
Miles:
| 1.64 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2021-06-28 |
$3,663,630 |
Fall of 2023 |
West Baton Rouge Parish
Note: The estimated completion date is based
on the work order date and the contract
days allowed.
Unavoidable contingencies and unforeseen events
often develop during construction, which may
impact the actual completion date.
LA 1: Port Allen Canal Br Repl (Ph1)(Hbi) |
H.001234.6 - New location/replacement of bridge
|
Proj. Engr: Payne, Roy |
Route: |
LA 1
map
|
Contractor: Kiewit Louisiana Co. |
Miles:
| 2.49 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2021-09-10 |
$69,559,972 |
Spring of 2024 |
Joliet Trail (Brusly) |
H.012834.6 - Sidewalks/bike paths
|
Proj. Engr: Fremin, Dustin |
Route: |
LA 988 LA 1
map
|
Contractor: Industrial Enterprises, Inc. |
Miles:
| 1.52 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2022-04-06 |
$991,986 |
Beginning of 2023 |
LA 1: La 75 - Port Allen Canal Br |
H.013191.6 - Asphalt overlay of concrete pavement
|
Proj. Engr: Zzzz Palermo, Keith |
Route: |
LA 1
map
|
Contractor: Barber Bros. Contracting Co., |
Miles:
| 11.63 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2020-09-16 |
$13,165,680 |
Fall of 2023 |
I-10 Wbr Queue Warning System |
H.013482.6-R1 - ITS and emergency operations
|
Proj. Engr: Fremin, Dustin |
Route: |
I-10
map
|
Contractor: Diamond Electrical Co., Inc. |
Miles:
| 15.95 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2023-04-06 |
$7,967,020 |
Fall of 2024 |
US 190: Rougon Rd - 0.5 Mi W of La 978 |
H.014146.6 - Asph concrete ovly over in place stabilized/cement treated base course
|
Proj. Engr: Zzzz Palermo, Keith |
Route: |
US 190
map
|
Contractor: Barriere Construction Co., LLC |
Miles:
| 8.44 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2021-10-15 |
$20,073,926 |
Fall of 2023 |
District 61
District 61: Thermoplastic Striping |
H.011205 - Striping and pavement markers
|
Proj. Engr: Zzzz Chatelain, Jeff |
Route: |
|
Contractor: Highway Graphics LLC |
Miles:
| 0.00 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2015-04-20 |
$286,609 |
Summer of 2015 |
District 61: Intersection Thermo Striping |
H.011492 - Striping and pavement markers
|
Proj. Engr: Zzzz Chatelain, Jeff |
Route: |
|
Contractor: Highway Graphics LLC |
Miles:
| 0.00 |
Work Order Date |
Contract Amount |
Estimated Completion Date |
2015-04-20 |
$225,887 |
Summer of 2015 |