Projects Under Construction

District 61

    Updated 17 Sep 2021

Districtwide Projects

Ascension Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

I-10: US 61 to Laplace ITS Deployment
H.013710.6 - ITS and emergency operations
Proj. Engr: Moore, Tony Route: I-10 map
Contractor: Grady Crawford Const. Co., Inc Miles: 19.87
Work Order Date Contract Amount Estimated Completion Date
2021-08-20 $3,986,855 Beginning of 2023


LA 70: Ascension P/L W - Ascension P/L E
H.013726.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Lobell, Scott Route: LA 70 map
Contractor: Barriere Construction Co., LLC Miles: 8.70
Work Order Date Contract Amount Estimated Completion Date
2021-09-13 $6,927,920 Beginning of 2022


US 61: Turn Lane Improvements @ La 3038
H.014474.6 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Lobell, Scott Route: US 61 map
Contractor: Barber Bros. Contracting Co., Miles: 0.20
Work Order Date Contract Amount Estimated Completion Date
2021-09-03 $395,360 Fall of 2021


Assumption Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

Napoleonville Linear Park
H.007386.6 - Sidewalks/bike paths
Proj. Engr: Lobell, Scott Route: LA 1 map
Contractor: LA Contracting Enterprise LLC Miles: 0.06
Work Order Date Contract Amount Estimated Completion Date
2021-01-14 $187,098 Fall of 2021


East Baton Rouge Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

North Sherwood Forest Drive Improvements
H.002301.6 - Concrete new pavement
Proj. Engr: Olson, Mike Route: LA 37 map
Contractor: Command Construction Industrie Miles: 1.68
Work Order Date Contract Amount Estimated Completion Date
2019-11-01 $13,475,086 Beginning of 2023


Ebr Computerized Traffic Signal, Ph Vb
H.007160.6 - Signalization
Proj. Engr: Payne, Roy Route: US 61-X LA 3164 map
Contractor: Ernest P. Breaux Electrical, L Miles: 0.32
Work Order Date Contract Amount Estimated Completion Date
2021-02-08 $5,605,561 Summer of 2022


US 61/190: Greenwell St - Miss River Br
H.009651.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Chatelain, Jeff Route: US 61 US 190 map
Contractor: Barber Bros. Contracting Co., Miles: 3.71
Work Order Date Contract Amount Estimated Completion Date
2018-08-05 $6,319,450 Spring of 2019


Acadian Street Pumping Station
H.010565.6 - Drainage
Proj. Engr: Chatelain, Jeff Route: LA 427 map
Contractor: Hard Rock Construction LLC Miles: 0.10
Work Order Date Contract Amount Estimated Completion Date
2019-09-20 $620,245 Summer of 2020


D61: Chip & Removal of H. Isaac Veg. Debris
H.010717.6 - Miscellaneous
Proj. Engr: Zzzz Vosburg, Chad Route: US 61 LA 415 map
Contractor: Hensley R. Lee Contracting Inc Miles: 0.04
Work Order Date Contract Amount Estimated Completion Date
2013-07-22 $61,429 Fall of 2013


LA 427: S. Acadian Thruway, I-10 - La 73 (Br)
H.011261.6-R2 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Divittorio, Alanna Route: LA 427 map
Contractor: R.J. Daigle & Sons Contractors Miles: 1.41
Work Order Date Contract Amount Estimated Completion Date
2020-03-26 $3,809,935 Beginning of 2021


LA 73 (Govt St) East Blvd - Lobdell Ave
H.011295.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Sam, Desmond Route: LA 73 map
Contractor: Barber Bros. Contracting Co., Miles: 2.98
Work Order Date Contract Amount Estimated Completion Date
2017-12-09 $17,364,728 Spring of 2022


I-10 (Constitution/Bunker Hill): Curve
H.011757 - Miscellaneous
Proj. Engr: Chatelain, Jeff Route: I-10 map
Contractor: Barber Bros. Contracting Co., Miles: 0.06
Work Order Date Contract Amount Estimated Completion Date
2015-08-08 $119,767 Fall of 2015


I-12 & I-10 Patching In Ebr Parish
H.011936.6 - Portland Cement Pavement patch
Proj. Engr: Divittorio, Alanna Route: I-12 I-10 map
Contractor: Coastal Bridge Co., L.L.C. Miles: 10.55
Work Order Date Contract Amount Estimated Completion Date
2017-02-18 $20,140,317 Beginning of 2020


LA 3064 to La 1248 Phase I Dijon Drive Extension
H.012233.6 - Asphalt new pavement-new roadway/new alignments
Proj. Engr: Zzzz Guidry, Blake Route: LA 3064 map
Contractor: Brown Industrial Construction, Miles: 0.10
Work Order Date Contract Amount Estimated Completion Date
2018-07-23 $8,333,389 Summer of 2020


US 61: Bluebonnet Blvd - S End US 190
H.012964.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Divittorio, Alanna Route: US 61 map
Contractor: Barber Bros. Contracting Co., Miles: 3.04
Work Order Date Contract Amount Estimated Completion Date
2021-06-07 $3,257,623 Beginning of 2022


I-110 ITS Deployment
H.013261.6 - ITS and emergency operations
Proj. Engr: Roubique, Chad Route: I-110 map
Contractor: Ozark Traffic Management, LLC Miles: 9.06
Work Order Date Contract Amount Estimated Completion Date
2020-08-26 $1,207,649 Beginning of 2022


LA 73: La 3064 / Essen - La 426 (Rt Ii)
H.013328.6 - Concrete pavement rehab-grinding/dowell retrofit/should drain install
Proj. Engr: Sam, Desmond Route: LA 73 map
Contractor: Gulf States Services, LLC Miles: 1.13
Work Order Date Contract Amount Estimated Completion Date
2020-12-14 $2,354,916 Summer of 2021


LA 42: La 3246 - Gardere Lane (Rt Ii)
H.013330.6 - Asphalt overlay of concrete pavement
Proj. Engr: Divittorio, Alanna Route: map
Contractor: Hard Rock Construction LLC Miles: 2.81
Work Order Date Contract Amount Estimated Completion Date
2021-01-17 $1,909,880 Fall of 2021


Pecue Lane/I-10 Interchange Phase Ii: Bridges Over I-10
H.013579.6 - New location/replacement of bridge
Proj. Engr: Collier, Zachary Route: I-10 map
Contractor: James Construction Group LLC Miles: 1.22
Work Order Date Contract Amount Estimated Completion Date
2019-06-02 $16,189,633 Summer of 2022


US 190: Rcut @ Longbow Dr
H.013682.6 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Divittorio, Alanna Route: US 190 map
Contractor: Kort's Construction Services, Miles: 0.26
Work Order Date Contract Amount Estimated Completion Date
2020-08-22 $363,728 Beginning of 2021


US 61: Florida Blvd. - Greenwell St.
H.013731.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Roubique, Chad Route: US 61 map
Contractor: Barber Bros. Contracting Co., Miles: 3.80
Work Order Date Contract Amount Estimated Completion Date
2020-08-19 $5,336,101 Fall of 2021


Ebr Signal Detection Upgrade
H.013830.6 - Signalization
Proj. Engr: Manuel, Thaddaeus Route: US 61 US 61-X map
Contractor: Jack B. Harper Electrical LLC Miles: 13.55
Work Order Date Contract Amount Estimated Completion Date
2020-08-19 $1,347,905 Spring of 2021


I-10 & I-12 College Dr Flyover Ramp
H.013897.6 - New location/replacement of bridge
Proj. Engr: Nelson, Gordon Route: I-10 I-12 map
Contractor: Boh Bros. Construction Co., Ll Miles: 2.61
Work Order Date Contract Amount Estimated Completion Date
2020-08-25 $52,385,000 Spring of 2023


LA 408: Restripe La 408 Eastbound Lane
H.014090.6 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Sam, Desmond Route: LA 408 map
Contractor: Highway Graphics LLC Miles: 0.28
Work Order Date Contract Amount Estimated Completion Date
2021-08-19 $60,316 Fall of 2021


LA 73: Drainage Improvement
H.014369.6 - Drainage
Proj. Engr: Sam, Desmond Route: map
Contractor: Merrick, LLC Miles: 0.06
Work Order Date Contract Amount Estimated Completion Date
2021-03-16 $795,093 Fall of 2021


I-110:nb Ramp Rep @ Cap Access Rd;la3045
H.014404.6 - Asphalt overlay of concrete pavement
Proj. Engr: Divittorio, Alanna Route: LA 3045 I-110 map
Contractor: Kcr Contractors, LLC Miles: 0.71
Work Order Date Contract Amount Estimated Completion Date
2021-03-25 $847,068 Fall of 2021


I-12 Eb: Median Rep Near Millerville
H.014571.6 - Miscellaneous
Proj. Engr: Divittorio, Alanna Route: I-12 map
Contractor: Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2021-05-23 $24,991 Spring of 2021


I-10 Wb: Barrier Repair Over College Dr.
H.014630.6 - Miscellaneous
Proj. Engr: Divittorio, Alanna Route: I-10 map
Contractor: Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2021-05-23 $38,996 Summer of 2021


East Feliciana Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 67: Ebr P/L to 8.0 Mi North of Ebr P/L
H.009633.6 - Asph concrete ovly over in place stabilized/cement treated base course
Proj. Engr: Palermo, Keith Route: LA 67 map
Contractor: Barriere Construction Co., LLC Miles: 8.00
Work Order Date Contract Amount Estimated Completion Date
2021-01-01 $4,661,699 Beginning of 2022


Iberville Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 75: Bayou Breaux Bridge
H.009484.6 - New location/replacement of bridge
Proj. Engr: Lobell, Scott Route: LA 75 map
Contractor: Tl Hawk, LLC Miles: 0.40
Work Order Date Contract Amount Estimated Completion Date
2021-04-08 $2,236,489 Beginning of 2022


LA 75: Restriping and Signs
H.010908.6 - Striping and pavement markers
Proj. Engr: Zzzz Thomas, Timothy Route: LA 75 map
Contractor: Jack B. Harper Contractor, LLC Miles: 1.93
Work Order Date Contract Amount Estimated Completion Date
2014-06-01 $49,990 Summer of 2014


I-10: Atch Basin Br - W Baton Rouge P/L
H.012588.6 - Asphalt new pavement-new roadway/new alignments
Proj. Engr: Palermo, Keith Route: I-10 map
Contractor: Madden Contracting Co., LLC Miles: 6.26
Work Order Date Contract Amount Estimated Completion Date
2021-08-13 $18,727,509 Beginning of 2023


I-10 & US 61 Overhead Sign Upgrade
H.013833.6 - Signing
Proj. Engr: Palermo, Keith Route: I-10 US 61 map
Contractor: Traffic Commander, LLC Miles: 1.27
Work Order Date Contract Amount Estimated Completion Date
2020-07-24 $683,228 Beginning of 2021


Pointe Coupee Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

Morganza Floodway Bridge Joint Repairs
H.010025.6 - Bridges reconditioned
Proj. Engr: Zzzz Thomas, Timothy Route: US 190 map
Contractor: Interstate Road Management Cor Miles: 3.56
Work Order Date Contract Amount Estimated Completion Date
2013-07-15 $246,707 Fall of 2013


St. James Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 20 Bayou Chevreuil Bridge
H.009481.6 - Bridges reconditioned
Proj. Engr: Lobell, Scott Route: LA 20 map
Contractor: Tl Hawk, LLC Miles: 0.44
Work Order Date Contract Amount Estimated Completion Date
2020-06-15 $11,765,456 Summer of 2022


LA 20: Improvements at La 3127
H.012073.6 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Lobell, Scott Route: LA 20 map
Contractor: Barber Bros. Contracting Co., Miles: 0.13
Work Order Date Contract Amount Estimated Completion Date
2021-05-17 $438,944 Summer of 2021


LA 70: Sunshine Bridge Pier 4 Fender Repair
H.013946.6 - Bridges reconditioned
Proj. Engr: Lobell, Scott Route: LA 70 map
Contractor: Bo-Mac Contractors Ltd Miles: 1.64
Work Order Date Contract Amount Estimated Completion Date
2021-06-28 $3,065,752 Fall of 2023


LA 641 & La 3125: Int. Improvements
H.014473.6 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Lobell, Scott Route: LA 641 LA 3125 map
Contractor: Barriere Construction Co., LLC Miles: 0.14
Work Order Date Contract Amount Estimated Completion Date
2021-08-10 $313,749 Fall of 2021


West Baton Rouge Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 1: Port Allen Canal Br Repl (Ph1)(Hbi)
H.001234.6 - New location/replacement of bridge
Proj. Engr: Luton, Loyd Route: LA 1 map
Contractor: Kiewit Louisiana Co. Miles: 2.49
Work Order Date Contract Amount Estimated Completion Date
2021-09-10 $57,666,023 Beginning of 2023


LA 1: La 75 - Port Allen Canal Br
H.013191.6 - Asphalt overlay of concrete pavement
Proj. Engr: Palermo, Keith Route: LA 1 map
Contractor: Barber Bros. Contracting Co., Miles: 11.63
Work Order Date Contract Amount Estimated Completion Date
2020-09-16 $7,716,131 Fall of 2021


I-10: Iberville Pl to La 415 (Rpms)
H.013891.6 - Striping and pavement markers
Proj. Engr: Palermo, Keith Route: I-10 map
Contractor: Highway Graphics LLC Miles: 24.66
Work Order Date Contract Amount Estimated Completion Date
2020-09-07 $561,562 Beginning of 2021


LA 986 Pavement Rehabilitation
H.014188.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Palermo, Keith Route: LA 986 map
Contractor: Barber Bros. Contracting Co., Miles: 0.60
Work Order Date Contract Amount Estimated Completion Date
2021-01-21 $345,753 Spring of 2021


West Feliciana Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 66: Big Bayou Sara Bridge Rehab
H.002281.6-R1 - Bridges reconditioned
Proj. Engr: Lecoq, Dane Route: LA 66 map
Contractor: Wl Bass Construction Inc. Miles: 0.39
Work Order Date Contract Amount Estimated Completion Date
2017-04-14 $7,802,757 Spring of 2020


LA 965: La 966 to La 10
H.011576.6 - Asph concrete ovly over in place stabilized/cement treated base course
Proj. Engr: Palermo, Keith Route: LA 965 map
Contractor: Barriere Construction Co., LLC Miles: 2.57
Work Order Date Contract Amount Estimated Completion Date
2021-05-03 $2,141,387 Fall of 2021


US 61: Thompson Creek Br Replacement
H.013193.6 - New location/replacement of bridge
Proj. Engr: Palermo, Keith Route: US 61 map
Contractor: Jb James Construction LLC Miles: 0.64
Work Order Date Contract Amount Estimated Completion Date
2019-02-18 $9,691,580 Fall of 2021


District 61

District 61: Thermoplastic Striping
H.011205 - Striping and pavement markers
Proj. Engr: Chatelain, Jeff Route:
Contractor: Highway Graphics LLC Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2015-04-20 $286,609 Summer of 2015


District 61: Intersection Thermo Striping
H.011492 - Striping and pavement markers
Proj. Engr: Chatelain, Jeff Route:
Contractor: Highway Graphics LLC Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2015-04-20 $225,887 Summer of 2015