Projects Under Construction

District 61

    Updated 11 Dec 2018

Districtwide Projects

Ascension Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 42 Widening and Improvements
H.002370.6 - Concrete new pavement
Proj. Engr: Lobell, Scott Route: LA 42 LA 44 map
Contractor: Barber Bros. Contracting Co., Miles: 3.79
Work Order Date Contract Amount Estimated Completion Date
2017-08-27 $28,600,137 Spring of 2020


LA 431 at La 934 Intersection Improvement
H.007855.6 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Lobell, Scott Route: LA 431 LA 934 map
Contractor: LA Contracting Enterprise LLC Miles: 0.48
Work Order Date Contract Amount Estimated Completion Date
2017-09-18 $1,520,199 Fall of 2018


LA 44: Turn Lanes
H.009956.6 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Lobell, Scott Route: LA 44 map
Contractor: Kcr Contractors, LLC Miles: 1.25
Work Order Date Contract Amount Estimated Completion Date
2017-10-13 $3,534,932 Beginning of 2019


LA 3038 (Cornerview): Rehab & Turn Lane
H.010640.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Lobell, Scott Route: LA 3038 map
Contractor: R.J. Daigle & Sons Contractors Miles: 0.46
Work Order Date Contract Amount Estimated Completion Date
2017-12-27 $2,118,387 Beginning of 2019


LA 22: Near I-10 Geometric Improv
H.011314.6 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Lobell, Scott Route: LA 22 LA 70 map
Contractor: Barriere Construction Co., LLC Miles: 1.22
Work Order Date Contract Amount Estimated Completion Date
2018-07-19 $5,633,333 Summer of 2019


La70 Rehabilitation(La 22 - St James Pl)
H.011450.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Lobell, Scott Route: LA 70 map
Contractor: Barriere Construction Co., LLC Miles: 3.17
Work Order Date Contract Amount Estimated Completion Date
2016-12-13 $2,914,978 Summer of 2017


LA 22 Rehabilitation
H.011451.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Lobell, Scott Route: LA 22 map
Contractor: R.J. Daigle & Sons Contractors Miles: 3.62
Work Order Date Contract Amount Estimated Completion Date
2018-11-05 $2,540,448 Summer of 2019


LA 30: Turn Lanes @ S. Purpera & S. Hodgeson
H.011490.6 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Lobell, Scott Route: LA 30 map
Contractor: Command Construction Industrie Miles: 0.32
Work Order Date Contract Amount Estimated Completion Date
2018-08-17 $797,964 End of 2018


LA 70: Rcut at La 3120
H.012903.6 - Asphalt widening and overlay
Proj. Engr: Lobell, Scott Route: LA 70 map
Contractor: Barriere Construction Co., LLC Miles: 0.36
Work Order Date Contract Amount Estimated Completion Date
2018-10-03 $788,781 Beginning of 2019


Assumption Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

Bridge Repairs- Clean Paint,Bearing, Deck Joint, Anchor Bolt
H.012259.6 - Bridges reconditioned
Proj. Engr: Miller, Sam Route: LA 182 US 190 map
Contractor: Gibson & Associates Inc. Miles: 47.13
Work Order Date Contract Amount Estimated Completion Date
2017-11-23 $6,854,337 Spring of 2020


LA 645: Lafourche P/L - Jct La 1
H.012496.6 - Asph concrete ovly over in place stabilized/cement treated base course
Proj. Engr: Lobell, Scott Route: LA 645 map
Contractor: Huey P. Stockstill, LLC Miles: 2.22
Work Order Date Contract Amount Estimated Completion Date
2018-05-13 $1,232,874 Fall of 2018


East Baton Rouge Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

Nicholson Drive @ Brightside Lane/ West Lee Drive
H.002822.6 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Chatelain, Jeff Route: LA 30 map
Contractor: Kort's Construction Services, Miles: 0.46
Work Order Date Contract Amount Estimated Completion Date
2018-04-19 $8,552,733 Summer of 2020


I-10: Highland to La 73
H.009250.6 - Asphalt widening and overlay
Proj. Engr: Heraty, Stephen P. Route: I-10 map
Contractor: James Construction Group LLC Miles: 6.58
Work Order Date Contract Amount Estimated Completion Date
2017-08-10 $72,442,058 Summer of 2023


LA 67: US 61/190 - La 3006
H.009649.6 - Portland Cement Pavement patch
Proj. Engr: Chatelain, Jeff Route: LA 67 map
Contractor: Hard Rock Construction LLC Miles: 4.78
Work Order Date Contract Amount Estimated Completion Date
2015-08-15 $7,118,344 Spring of 2018


US 61/190: Greenwell St - Miss River Br
H.009651.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Chatelain, Jeff Route: US 61 US 190 map
Contractor: Barber Bros. Contracting Co., Miles: 3.71
Work Order Date Contract Amount Estimated Completion Date
2018-08-05 $5,798,734 Spring of 2019


Boyd Street & 21st St Pumping Sta Imp I-110
H.010439.6 - Drainage
Proj. Engr: Chatelain, Jeff Route: I-110 map
Contractor: Wharton-Smith, Inc Miles: 0.20
Work Order Date Contract Amount Estimated Completion Date
2017-08-28 $3,921,692 Summer of 2018


D61: Chip & Removal of H. Isaac Veg. Debris
H.010717.6 - Miscellaneous
Proj. Engr: Vosburg, Chad Route: US 61 LA 415 map
Contractor: Hensley R. Lee Contracting Inc Miles: 0.04
Work Order Date Contract Amount Estimated Completion Date
2013-07-22 $61,429 Fall of 2013


I-12: Sound Barrier Wall at Essen Lane
H.011213.6 - Miscellaneous
Proj. Engr: Chatelain, Jeff Route: I-12 map
Contractor: C.E.C., Inc. Miles: 0.50
Work Order Date Contract Amount Estimated Completion Date
2016-02-11 $2,445,158 Summer of 2016


LA 73 (Govt St) East Blvd - Lobdell Ave
H.011295.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Coco, Gregory Route: LA 73 map
Contractor: Barber Bros. Contracting Co., Miles: 2.98
Work Order Date Contract Amount Estimated Completion Date
2017-12-09 $12,058,859 Summer of 2020


US 61 at US 190 Interchange Signing
H.011708.6 - Signing
Proj. Engr: Coco, Gregory Route: US 61-X US 190 map
Contractor: Alpha Service and Products, In Miles: 1.44
Work Order Date Contract Amount Estimated Completion Date
2017-11-15 $1,391,825 Beginning of 2020


I-10 (Constitution/Bunker Hill): Curve
H.011757 - Miscellaneous
Proj. Engr: Chatelain, Jeff Route: I-10 map
Contractor: Barber Bros. Contracting Co., Miles: 0.06
Work Order Date Contract Amount Estimated Completion Date
2015-08-08 $119,767 Fall of 2015


I-12 & I-10 Patching In Ebr Parish
H.011936.6 - Portland Cement Pavement patch
Proj. Engr: Chatelain, Jeff Route: I-12 I-10 map
Contractor: Coastal Bridge Co., L.L.C. Miles: 10.55
Work Order Date Contract Amount Estimated Completion Date
2017-02-18 $20,090,322 Spring of 2019


LA 3064 to La 1248 Phase I Dijon Drive Extension
H.012233.6 - Asphalt new pavement-new roadway/new alignments
Proj. Engr: Guidry, Blake Route: LA 3064 map
Contractor: Brown Industrial Construction, Miles: 0.10
Work Order Date Contract Amount Estimated Completion Date
2018-07-23 $8,301,301 Summer of 2020


I-110: Interchange Modification @ Terrace
H.012422.6 - Concrete new pavement
Proj. Engr: Chatelain, Jeff Route: I-10 map
Contractor: Brown Industrial Construction, Miles: 0.30
Work Order Date Contract Amount Estimated Completion Date
2018-03-15 $8,789,230 Summer of 2019


LA 19: I-110 - S Canal Bayou
H.012840.6 - Asphalt overlay of concrete pavement
Proj. Engr: Chatelain, Jeff Route: LA 19 map
Contractor: Barriere Construction Co., LLC Miles: 5.26
Work Order Date Contract Amount Estimated Completion Date
2017-11-13 $2,624,899 Summer of 2018


I-110: 625' S of Spanish Town Rd - US 61
H.013115.6 - Portland Cement Pavement patch
Proj. Engr: Chatelain, Jeff Route: I-110 map
Contractor: Jb James Construction LLC Miles: 7.85
Work Order Date Contract Amount Estimated Completion Date
2018-03-14 $2,130,833 Summer of 2018


US 61 @ Greenwell Spgs Emer. Pipe Repair
H.013287.6 - Drainage
Proj. Engr: Chatelain, Jeff Route: US 61 map
Contractor: Brown Industrial Construction, Miles: 0.01
Work Order Date Contract Amount Estimated Completion Date
2017-11-13 $905,364 Beginning of 2018


LA 1248: La 30 - I-10 North C of a (Rt)
H.013318.6 - Concrete pavement rehab-grinding/dowell retrofit/should drain install
Proj. Engr: Guidry, Blake Route: LA 1248 map
Contractor: Hard Rock Construction LLC Miles: 5.83
Work Order Date Contract Amount Estimated Completion Date
2018-08-07 $2,975,814 Fall of 2020


Iberville Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 404: Bayou Choctaw Bridge
H.009485.6 - New location/replacement of bridge
Proj. Engr: Roubique, Chad Route: LA 404 map
Contractor: Coastal Bridge Co., L.L.C. Miles: 0.30
Work Order Date Contract Amount Estimated Completion Date
2018-07-11 $2,799,794 Summer of 2019


Rosedale Gateway Enhancement
H.009769.6 - Sidewalks/bike paths
Proj. Engr: Bacas, Chad Route: LA 77 map
Contractor: Pointe Coupee Contractors LLC Miles: 0.12
Work Order Date Contract Amount Estimated Completion Date
2018-01-11 $196,351 Summer of 2018


LA 75: Restriping and Signs
H.010908.6 - Striping and pavement markers
Proj. Engr: Zzzz Thomas, Timothy Route: LA 75 map
Contractor: Jack B. Harper Contractor, LLC Miles: 1.93
Work Order Date Contract Amount Estimated Completion Date
2014-06-01 $49,990 Summer of 2014


LA 75 & La 141-1: Cp, Ovlay & Stab, Ovlay
H.011617.6 - Asph concrete ovly over in place stabilized/cement treated base course
Proj. Engr: Lobell, Scott Route: LA 75 LA 141-1 map
Contractor: Barber Bros. Contracting Co., Miles: 6.36
Work Order Date Contract Amount Estimated Completion Date
2018-02-20 $2,705,185 Beginning of 2019


Pointe Coupee Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

Livonia Signage Enhancement Project
H.007534.6 - Miscellaneous
Proj. Engr: Payne, Roy Route: US 190 map
Contractor: Lamay Group, LLC Miles: 1.54
Work Order Date Contract Amount Estimated Completion Date
2018-01-16 $156,099 Spring of 2018


Morganza Floodway Bridge Joint Repairs
H.010025.6 - Bridges reconditioned
Proj. Engr: Zzzz Thomas, Timothy Route: US 190 map
Contractor: Interstate Road Management Cor Miles: 3.56
Work Order Date Contract Amount Estimated Completion Date
2013-07-15 $246,707 Fall of 2013


St. James Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 70: Mississippi River Bridge - Phase Iii
H.012343.6-R1 - Bridges reconditioned
Proj. Engr: Lobell, Scott Route: LA 70 map
Contractor: Coastal Bridge Co., L.L.C. Miles: 2.29
Work Order Date Contract Amount Estimated Completion Date
2017-09-06 $10,646,997 Spring of 2020


West Baton Rouge Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 1: Up / Industry Abandoned RR Xings (Wbr)
H.012240.6 - Railroads
Proj. Engr: Roubique, Chad Route: LA 1 map
Contractor: Coastal Bridge Co., L.L.C. Miles: 1.18
Work Order Date Contract Amount Estimated Completion Date
2018-07-11 $604,207 Fall of 2018


West Feliciana Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 66: Big Bayou Sara Bridge Rehab
H.002281.6-R1 - Bridges reconditioned
Proj. Engr: Delee, Glenn Route: LA 66 map
Contractor: Wl Bass Construction Inc. Miles: 0.39
Work Order Date Contract Amount Estimated Completion Date
2017-04-14 $7,150,882 Summer of 2019


District 61

District 61: Thermoplastic Striping
H.011205 - Striping and pavement markers
Proj. Engr: Chatelain, Jeff Route:
Contractor: Highway Graphics LLC Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2015-04-20 $286,609 Summer of 2015


District 61: Intersection Thermo Striping
H.011492 - Striping and pavement markers
Proj. Engr: Chatelain, Jeff Route:
Contractor: Highway Graphics LLC Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2015-04-20 $225,887 Summer of 2015