Projects Under Construction

District 61

    Updated 12 May 2025

Districtwide Projects

Ascension Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 44: Widening and Roundabout at La 941
H.010909.6 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Lobell, Scott Route: LA 44 LA 941 map
Contractor: Kcr Contractors, LLC Miles: 1.34
Work Order Date Contract Amount Estimated Completion Date
2021-08-29 $6,261,562 Fall of 2022


LA 30 Roundabouts @ Tanger Mall & I-10
H.010960.6-R1 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Zzzz Dunn, Marc Route: LA 30 I-10 map
Contractor: Barriere Construction Co., LLC Miles: 1.71
Work Order Date Contract Amount Estimated Completion Date
2024-02-01 $28,997,498 Fall of 2026


LA 431: Villar Canal and Drainage Bridges
H.012057.6 - New location/replacement of bridge
Proj. Engr: Elisar, Aaron Route: LA 431 map
Contractor: Brown Industrial Construction, Miles: 0.50
Work Order Date Contract Amount Estimated Completion Date
2024-10-07 $6,800,133 End of 2026


I-10: US 61 to Laplace ITS Deployment
H.013710.6 - ITS and emergency operations
Proj. Engr: Moore, Tony Route: I-10 map
Contractor: Grady Crawford Const. Co., Inc Miles: 19.87
Work Order Date Contract Amount Estimated Completion Date
2021-08-20 $4,016,759 Beginning of 2023


US 61: Int. Improvements at La 427
H.014088.6 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Elisar, Aaron Route: US 61 LA 427 map
Contractor: Command Construction Industrie Miles: 0.61
Work Order Date Contract Amount Estimated Completion Date
2024-09-27 $4,658,599 Summer of 2026


LA 943: La 308 - La 1 N Intersection
H.014116.6 - Asph concrete ovly over in place stabilized/cement treated base course
Proj. Engr: Elisar, Aaron Route: LA 943 map
Contractor: R.J. Daigle & Sons Contractors Miles: 7.82
Work Order Date Contract Amount Estimated Completion Date
2024-08-15 $5,807,381 Summer of 2025


LA 44: I-10 - La 621
H.014762.6 - Portland Cement Pavement patch
Proj. Engr: Elisar, Aaron Route: LA 44 map
Contractor: Progressive Construction Co., Miles: 4.62
Work Order Date Contract Amount Estimated Completion Date
2024-10-07 $4,083,835 Summer of 2026


US 61: La 74 - La 42
H.014865.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Zzzz Dunn, Nicole Route: US 61 map
Contractor: Barriere Construction Co., LLC Miles: 5.31
Work Order Date Contract Amount Estimated Completion Date
2023-12-14 $13,471,037 Summer of 2026


LA 30: Veteran's Blvd - US 61
H.014866.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Elisar, Aaron Route: LA 30 map
Contractor: Barber Bros. Contracting Co., Miles: 3.74
Work Order Date Contract Amount Estimated Completion Date
2024-09-13 $4,000,063 Spring of 2025


LA 431: Left Turn Lane at La 621
H.015267.6 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Elisar, Aaron Route: LA 431 map
Contractor: Richard Price Contracting Co, Miles: 0.53
Work Order Date Contract Amount Estimated Completion Date
2024-11-24 $2,110,665 Fall of 2025


LA 928: La 74 - La 427
H.015438.6 - Asphalt overlay of asphalt pavement
Proj. Engr: White, Ryan Route: LA 928 map
Contractor: Barriere Construction Co., LLC Miles: 5.69
Work Order Date Contract Amount Estimated Completion Date
2025-01-13 $3,882,785 Beginning of 2026


Assumption Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

Napoleonville Linear Park
H.007386.6 - Sidewalks/bike paths
Proj. Engr: Lobell, Scott Route: LA 1 map
Contractor: LA Contracting Enterprise, L.L Miles: 0.06
Work Order Date Contract Amount Estimated Completion Date
2021-01-14 $190,194 Fall of 2021


LA 308: La 1011 - Franklin Ave
H.015556.6 - Asphalt surface treatment
Proj. Engr: Elisar, Aaron Route: LA 308 map
Contractor: Barber Bros. Contracting Co., Miles: 6.76
Work Order Date Contract Amount Estimated Completion Date
2024-07-05 $1,969,337 Beginning of 2025


East Baton Rouge Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

Comite River Diversion Bridge
H.000710.6-R2 - New location/replacement of bridge
Proj. Engr: Payne, Roy Route: LA 964
Contractor: Brown Industrial Construction, Miles: 0.42
Work Order Date Contract Amount Estimated Completion Date
2022-06-01 $27,520,735 Fall of 2024


North Sherwood Forest Drive Improvements
H.002301.6 - Concrete new pavement
Proj. Engr: Olson, Mike Route: LA 37 map
Contractor: Command Construction Industrie Miles: 1.68
Work Order Date Contract Amount Estimated Completion Date
2019-11-01 $13,599,982 Spring of 2023


Sullivan Road (Wax - Hooper)
H.002320.6-R1 - Concrete new pavement
Proj. Engr: Sam, Desmond Route: LA 3034 LA 408 map
Contractor: Byron E. Talbot Contractor, In Miles: 1.13
Work Order Date Contract Amount Estimated Completion Date
2025-02-13 $11,594,274 Fall of 2026


Pecue Lane/I-10 Interchange Phase Iii
H.003047.6 - New location/replacement of bridge
Proj. Engr: Payne, Roy Route: I-10 map
Contractor: Brown Industrial Construction, Miles: 0.87
Work Order Date Contract Amount Estimated Completion Date
2023-03-17 $72,389,298 Summer of 2026


Ebr Computerized Traffic Signal, Ph Vb
H.007160.6 - Signalization
Proj. Engr: Payne, Roy Route: LA 3164 map
Contractor: Ernest P. Breaux Electrical, L Miles: 0.32
Work Order Date Contract Amount Estimated Completion Date
2021-02-08 $8,782,417 Beginning of 2025


Blackwater Bayou Bridge
H.007963.6 - New location/replacement of bridge
Proj. Engr: Sam, Desmond Route: LA 410 map
Contractor: Coastal Contractors, LLC Miles: 0.32
Work Order Date Contract Amount Estimated Completion Date
2022-10-01 $5,999,552 Fall of 2023


LA 73: US 61 (Airline) - Essen Lane
H.010652.6 - Portland Cement Pavement patch
Proj. Engr: Sam, Desmond Route: LA 73 map
Contractor: Merrick, LLC Miles: 2.27
Work Order Date Contract Amount Estimated Completion Date
2023-08-26 $20,273,821 Spring of 2026


D61: Chip & Removal of H. Isaac Veg. Debris
H.010717.6 - Miscellaneous
Proj. Engr: Zzzz Vosburg, Chad Route: US 61 LA 415 map
Contractor: Hensley R. Lee Contracting Inc Miles: 0.04
Work Order Date Contract Amount Estimated Completion Date
2013-07-22 $61,429 Fall of 2013


LA 30: South Blvd to W Chimes St
H.011098.6 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Cooley, Alanna Route: LA 30 I-10 map
Contractor: Command Construction Industrie Miles: 2.05
Work Order Date Contract Amount Estimated Completion Date
2022-07-05 $18,374,163 Fall of 2024


Quail Dr: Turn Lane at Perkins (La 427)
H.011496.6 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Cheng, Guangziang Route: map
Contractor: Industrial Enterprises, Inc. Miles: 0.01
Work Order Date Contract Amount Estimated Completion Date
2021-04-12 $397,400 Beginning of 2022


I-10 (Constitution/Bunker Hill): Curve
H.011757 - Miscellaneous
Proj. Engr: Zzzz Chatelain, Jeff Route: I-10 map
Contractor: Barber Bros. Contracting Co., Miles: 0.06
Work Order Date Contract Amount Estimated Completion Date
2015-08-08 $119,767 Fall of 2015


LA 3064 to Bluebonnet Blvd. Phase II
H.012232.6 - Asphalt new pavement-new roadway/new alignments
Proj. Engr: Branch, David Route: I-10 map
Contractor: Boone Services LLC Miles: 0.49
Work Order Date Contract Amount Estimated Completion Date
2023-09-18 $17,048,770 Summer of 2025


LA 3064 to La 1248 Phase I Dijon Drive Extension
H.012233.6 - Asphalt new pavement-new roadway/new alignments
Proj. Engr: Zzzz Guidry, Blake Route: LA 3064 map
Contractor: Brown Industrial Construction, Miles: 0.10
Work Order Date Contract Amount Estimated Completion Date
2018-07-23 $8,079,765 Fall of 2020


I-12 @ Sherwood Forest Ped/Bike Safety
H.013029.6 - Planning study
Proj. Engr: Guidry, Blake Route: I-12 map
Contractor: LA Contracting Enterprise, L.L Miles: 0.20
Work Order Date Contract Amount Estimated Completion Date
2024-10-09 $2,525,511 Fall of 2025


I-110 ITS Deployment
H.013261.6 - ITS and emergency operations
Proj. Engr: Cooley, Alanna Route: I-110 map
Contractor: Ozark Traffic Management, LLC Miles: 9.06
Work Order Date Contract Amount Estimated Completion Date
2020-08-26 $1,327,239 Fall of 2022


Scotlandville Pkwy to Dwtn Br Trail - Ph 1
H.013267.6-R1 - Sidewalks/bike paths
Proj. Engr: Pechon, Brady Route: US 61-X US 61 map
Contractor: Triumph Construction, LLC Miles: 5.74
Work Order Date Contract Amount Estimated Completion Date
2024-09-08 $5,307,609 Spring of 2026


Pecue Lane/I-10 Interchange Phase Ii: Bridges Over I-10
H.013579.6 - New location/replacement of bridge
Proj. Engr: Collier, Zachary Route: I-10 map
Contractor: James Construction Group LLC Miles: 1.22
Work Order Date Contract Amount Estimated Completion Date
2019-06-02 $16,100,685 Summer of 2022


I-10 & I-12 College Dr Flyover Ramp
H.013897.6 - New location/replacement of bridge
Proj. Engr: Nelson, Gordon Route: I-10 I-12 map
Contractor: Boh Bros. Construction Co., Ll Miles: 2.61
Work Order Date Contract Amount Estimated Completion Date
2020-08-25 $66,417,996 Fall of 2025


LA 3006: La 19 - La 67
H.015251.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Sam, Desmond Route: LA 3006 map
Contractor: Barber Bros. Contracting Co., Miles: 2.54
Work Order Date Contract Amount Estimated Completion Date
2025-03-03 $7,398,251 Beginning of 2026


US 190: US 61 Overpass Int. Repairs
H.015352.6 - Bridges reconditioned
Proj. Engr: Cooley, Alanna Route: US 61 map
Contractor: Freyssinet, Inc Usa Miles: 0.04
Work Order Date Contract Amount Estimated Completion Date
2024-05-25 $1,124,035 Fall of 2024


LA 67: Plank Rd. @ Airline - Girder Rep.
H.015424.6 - Bridges reconditioned
Proj. Engr: Maurin, Roland Route: LA 67 US 61 map
Contractor: C.E.C., Inc. Miles: 0.12
Work Order Date Contract Amount Estimated Completion Date
2024-07-15 $2,195,034 Fall of 2024


I-10 & I-12: Patching
H.015838.6 - Portland Cement Pavement patch
Proj. Engr: Cooley, Alanna Route: I-10 I-12 map
Contractor: Diamond Surface, Inc. Miles: 9.86
Work Order Date Contract Amount Estimated Completion Date
2025-01-28 $7,569,896 Spring of 2026


East Feliciana Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 63 Bridges Near Bluff Creek
H.002365.6 - New location/replacement of bridge
Proj. Engr: Lecoq, Dane Route: LA 63 map
Contractor: Baker Pile Driving and Site Wo Miles: 1.71
Work Order Date Contract Amount Estimated Completion Date
2024-04-08 $20,483,331 Beginning of 2028


LA 422: Bridge Over Unnamed Stream
H.014251.6 - New location/replacement of bridge
Proj. Engr: Lecoq, Dane Route: LA 422 map
Contractor: Merrick, LLC Miles: 0.29
Work Order Date Contract Amount Estimated Completion Date
2025-04-28 $1,351,653 Beginning of 2026


LA 10: La 67 - Smith Rd
H.015557.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Lecoq, Dane Route: LA 10 map
Contractor: R.J. Daigle & Sons Contractors Miles: 5.58
Work Order Date Contract Amount Estimated Completion Date
2025-02-12 $4,608,405 Fall of 2025


Iberville Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 75: Restriping and Signs
H.010908.6 - Striping and pavement markers
Proj. Engr: Zzzz Thomas, Timothy Route: LA 75 map
Contractor: Jack B. Harper Contractor, LLC Miles: 1.93
Work Order Date Contract Amount Estimated Completion Date
2014-06-01 $49,990 Summer of 2014


LA 1: Bayou Plaquemine Br Strengthening
H.014608.6 - Bridges reconditioned
Proj. Engr: Chatelain, Jeff Route: LA 1 map
Contractor: Reliant Industrial Solutions L Miles: 0.09
Work Order Date Contract Amount Estimated Completion Date
2023-06-09 $294,598 Beginning of 2024


LA 30 @ La 3115 Traffic Signal
H.015108.6 - Signalization
Proj. Engr: Zzzz Dunn, Nicole Route: LA 30 map
Contractor: Jack B. Harper Electrical LLC Miles: 0.01
Work Order Date Contract Amount Estimated Completion Date
2023-06-09 $243,686 Beginning of 2024


LA 69: 0.5 Mi N of La 404 - La 1
H.015440.6 - Portland Cement Pavement patch
Proj. Engr: White, Ryan Route: LA 69 map
Contractor: Gulf States Services, LLC Miles: 2.12
Work Order Date Contract Amount Estimated Completion Date
2025-02-01 $4,152,594 Spring of 2026


LA 77: Bayou Grosse Tete Er Repair
H.016026.6 - Moveable bridges reconditioned
Proj. Engr: Flynn, Mary Route: LA 77 map
Contractor: Coastal Contractors, LLC Miles: 0.07
Work Order Date Contract Amount Estimated Completion Date
2024-06-15 $3,840,452 Beginning of 2026


Pointe Coupee Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

Bayou Chenal & Bayou Discharge Bridges
H.002184.6-R1 - New location/replacement of bridge
Proj. Engr: Chatelain, Jeff Route: LA 413 map
Contractor: Jb James Construction LLC Miles: 0.45
Work Order Date Contract Amount Estimated Completion Date
2022-06-16 $8,169,664 Beginning of 2025


LA 1: Byu Moreau and Lateral W15#7a Brs
H.012061.6 - New location/replacement of bridge
Proj. Engr: Chatelain, Jeff Route: LA 1 map
Contractor: Diamond B Construction Co., L. Miles: 1.80
Work Order Date Contract Amount Estimated Completion Date
2024-08-09 $4,957,995 Spring of 2026


LA 1: S Jct La 1 - N Jct La 1
H.015441.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Chatelain, Jeff Route: LA 1 map
Contractor: Barriere Construction Co., LLC Miles: 1.79
Work Order Date Contract Amount Estimated Completion Date
2024-09-07 $2,237,574 Beginning of 2025


St. James Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 70: Sunshine Bridge - La 22
H.002424.6 - Asphalt new pavement-new roadway/new alignments
Proj. Engr: Zzzz Dunn, Nicole Route: LA 70 map
Contractor: Gilchrist Construction Company Miles: 5.16
Work Order Date Contract Amount Estimated Completion Date
2023-03-01 $54,379,636 Summer of 2026


LA 20 Bayou Chevreuil Bridge
H.009481.6 - Bridges reconditioned
Proj. Engr: Zzzz Dunn, Nicole Route: LA 20 map
Contractor: Tl Hawk, LLC Miles: 0.44
Work Order Date Contract Amount Estimated Completion Date
2020-06-15 $11,765,456 Summer of 2022


LA 20 Bayou Chevreuil Bridge
H.009481.6A - Bridges reconditioned
Proj. Engr: White, Ryan Route: LA 20 map
Contractor: Tl Hawk, LLC Miles: 0.44
Work Order Date Contract Amount Estimated Completion Date
2024-04-19 $17,111,541 Spring of 2026


LA 20 Widen: La 307 - S. Vacherie
H.013116.6 - Asphalt widening and overlay
Proj. Engr: Elisar, Aaron Route: LA 20 map
Contractor: Barber Bros. Contracting Co., Miles: 3.20
Work Order Date Contract Amount Estimated Completion Date
2023-09-21 $22,190,299 Summer of 2026


LA 44: La 3274 - 0.5 Mi W of La 642
H.015558.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Elisar, Aaron Route: LA 44 map
Contractor: Barber Bros. Contracting Co., Miles: 4.36
Work Order Date Contract Amount Estimated Completion Date
2024-09-20 $2,503,370 Spring of 2025


LA 3125: La 70 - La 3213
H.015944.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Elisar, Aaron Route: LA 3125 map
Contractor: R.J. Daigle & Sons Contractors Miles: 13.62
Work Order Date Contract Amount Estimated Completion Date
2024-09-03 $12,977,681 Summer of 2026


West Baton Rouge Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 1: Port Allen Canal Br Repl (Ph1)(Hbi)
H.001234.6 - New location/replacement of bridge
Proj. Engr: Payne, Roy Route: LA 1 map
Contractor: Kiewit Louisiana Co. Miles: 2.49
Work Order Date Contract Amount Estimated Completion Date
2021-09-10 $86,013,515 Fall of 2025


Joliet Trail (Brusly)
H.012834.6 - Sidewalks/bike paths
Proj. Engr: Fremin, Dustin Route: LA 988 LA 1 map
Contractor: Industrial Enterprises, Inc. Miles: 1.52
Work Order Date Contract Amount Estimated Completion Date
2022-04-06 $958,506 Spring of 2023


LA 1: La 75 - Port Allen Canal Br
H.013191.6 - Asphalt overlay of concrete pavement
Proj. Engr: Zzzz Palermo, Keith Route: LA 1 map
Contractor: Barber Bros. Contracting Co., Miles: 11.63
Work Order Date Contract Amount Estimated Completion Date
2020-09-16 $13,462,323 Beginning of 2024


I-10 Wbr Queue Warning System
H.013482.6-R1 - ITS and emergency operations
Proj. Engr: Fremin, Dustin Route: I-10 map
Contractor: Diamond Electrical Co., Inc. Miles: 15.95
Work Order Date Contract Amount Estimated Completion Date
2023-04-06 $8,221,642 Fall of 2024


LA 1: Port Allen Canal Br Repl (Ph2)(Hbi)
H.014258.6 - New location/replacement of bridge
Proj. Engr: Payne, Roy Route: LA 1 map
Contractor: Jb James Construction LLC Miles: 1.23
Work Order Date Contract Amount Estimated Completion Date
2025-01-12 $115,911,453 Summer of 2028


LA 76: La 415 - La 1
H.015761.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Chatelain, Jeff Route: LA 415 LA 76 map
Contractor: Barriere Construction Co., LLC Miles: 2.40
Work Order Date Contract Amount Estimated Completion Date
2025-04-28 $2,758,241 Fall of 2025


District 61

District 61: Thermoplastic Striping
H.011205 - Striping and pavement markers
Proj. Engr: Zzzz Chatelain, Jeff Route:
Contractor: Highway Graphics LLC Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2015-04-20 $286,609 Summer of 2015


District 61: Intersection Thermo Striping
H.011492 - Striping and pavement markers
Proj. Engr: Zzzz Chatelain, Jeff Route:
Contractor: Highway Graphics LLC Miles: 0.00
Work Order Date Contract Amount Estimated Completion Date
2015-04-20 $225,887 Summer of 2015