Projects Under Construction

District 08

    Updated 4 Mar 2021

Districtwide Projects

Avoyelles Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

Bayou Boeuf and Turner Canal Bridges
H.007873.6 - New location/replacement of bridge
Proj. Engr: Montalvo, Joseph Route: LA 1176 map
Contractor: Diamond B Construction Co., L. Miles: 1.36
Work Order Date Contract Amount Estimated Completion Date
2020-07-12 $2,835,736 Fall of 2021


LA 106: Bayou Boeuf Bridge
H.009497.6 - New location/replacement of bridge
Proj. Engr: Moreau, Justin Route: LA 106 map
Contractor: Tl Hawk, LLC Miles: 0.13
Work Order Date Contract Amount Estimated Completion Date
2020-01-23 $2,012,065 Summer of 2021


LA 1: Moreau St - End Four Lane Section
H.012998.6 - Concrete pavement rehab-grinding/dowell retrofit/should drain install
Proj. Engr: Montalvo, Joseph Route: LA 1 map
Contractor: Jd's Rebar & Construction, Inc Miles: 1.56
Work Order Date Contract Amount Estimated Completion Date
2021-02-05 $827,063 Summer of 2021


Grant Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 471: Dartigo Creek & Creek Bridges
H.001842.6 - Asphalt new pavement-new roadway/new alignments
Proj. Engr: Pugh, David Route: LA 471 map
Contractor: Tl Hawk, LLC Miles: 0.66
Work Order Date Contract Amount Estimated Completion Date
2019-10-07 $3,770,874 Spring of 2021


Natchitoches Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 8 to La 6 (I-49 Signing)
H.003476.6 - Signing
Proj. Engr: Taylor, Jared Route: I-49 map
Contractor: Acacia Industries, LLC Miles: 35.24
Work Order Date Contract Amount Estimated Completion Date
2015-08-12 $1,138,285 Fall of 2017


LA 153: Jct La 9 - Five Forks Road
H.010357.6 - Asph concrete ovly over in place stabilized/cement treated base course
Proj. Engr: Taylor, Jared Route: LA 153 map
Contractor: Madden Contracting Co., LLC Miles: 3.46
Work Order Date Contract Amount Estimated Completion Date
2019-10-21 $2,902,600 Spring of 2020


LA 478: Vowells Mill to La 117
H.012144.6 - Asph concrete ovly over in place stabilized/cement treated base course
Proj. Engr: Duffey, Randall Route: LA 478 map
Contractor: Madden Contracting Co., LLC Miles: 5.21
Work Order Date Contract Amount Estimated Completion Date
2020-08-14 $2,814,548 Beginning of 2021


I-49: Cable Barriers Natchitoches
H.012196.6 - Crash devices
Proj. Engr: Pugh, David Route: I-49 map
Contractor: Progressive Construction Co., Miles: 50.70
Work Order Date Contract Amount Estimated Completion Date
2018-10-13 $5,699,351 Beginning of 2020


I-49: La 6 to Desoto Parish Line
H.012683.6 - Signing
Proj. Engr: Taylor, Jared Route: I-49 map
Contractor: Alpha Service and Products, In Miles: 19.29
Work Order Date Contract Amount Estimated Completion Date
2020-09-04 $525,121 Fall of 2021


LA 1225: US 71 to La 6
H.012972.6 - Asph concrete ovly over in place stabilized/cement treated base course
Proj. Engr: Taylor, Jared Route: LA 1225 map
Contractor: Madden Contracting Co., LLC Miles: 4.23
Work Order Date Contract Amount Estimated Completion Date
2020-09-28 $2,804,790 Beginning of 2021


Rapides Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

US 165-X: Kcs Railway Overpass
H.000577.6 - Bridge removal
Proj. Engr: Buskie, Steve Route: US 165-X map
Contractor: T.L. Construction LLC Miles: 0.38
Work Order Date Contract Amount Estimated Completion Date
2020-04-08 $1,922,213 Fall of 2021


LA 28: US 167 - La 3144
H.001581.6 - Concrete pavement rehab-grinding/dowell retrofit/should drain install
Proj. Engr: Buskie, Steve Route: LA 28 map
Contractor: Progressive Construction Co., Miles: 1.13
Work Order Date Contract Amount Estimated Completion Date
2021-02-16 $1,217,597 Summer of 2021


Alexandria ITS Phase 3
H.011505.6 - ITS and emergency operations
Proj. Engr: Buskie, Steve Route: US 71 map
Contractor: Ernest P. Breaux Electrical, L Miles: 9.54
Work Order Date Contract Amount Estimated Completion Date
2019-08-02 $1,901,943 Beginning of 2021


I-49: 2 Miles N La 3265 to 4 Miles N La 1
H.011938.6 - Signing
Proj. Engr: Buskie, Steve Route: I-49 map
Contractor: Alpha Service and Products, In Miles: 23.91
Work Order Date Contract Amount Estimated Completion Date
2020-09-19 $1,988,131 Fall of 2023


LA 112: US 165 - I-49
H.012967.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Moreau, Justin Route: LA 112 map
Contractor: Vance Brothers Inc. Miles: 6.97
Work Order Date Contract Amount Estimated Completion Date
2020-11-20 $990,482 Beginning of 2021


I-49 @ US 165: Ramp Truss Replacement
H.013856.6 - Signing
Proj. Engr: Buskie, Steve Route: I-49 map
Contractor: T.L. Construction LLC Miles: 0.38
Work Order Date Contract Amount Estimated Completion Date
2020-08-06 $430,550 End of 2020


Vernon Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 10: Look Out Rd - 850' E Bailey Rd
H.010339.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Duffey, Randall Route: LA 10 map
Contractor: Diamond B Construction Co., L. Miles: 5.73
Work Order Date Contract Amount Estimated Completion Date
2021-01-18 $2,932,801 Summer of 2021


LA 111: La 8 to John Keel Loop - Ast
H.012933.6 - Asphalt surface treatment
Proj. Engr: Duffey, Randall Route: LA 111 map
Contractor: P.R. Parker Company Inc Miles: 4.28
Work Order Date Contract Amount Estimated Completion Date
2020-10-26 $543,857 Beginning of 2021


District 08

No districtwide projects.