Projects Under Construction

District 08

    Updated 12 Dec 2019

Districtwide Projects

Avoyelles Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 451: La 114 to P Laborde Road
H.012143.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Montalvo, Joseph Route: LA 451 map
Contractor: Diamond B Construction Co., L. Miles: 11.63
Work Order Date Contract Amount Estimated Completion Date
2019-09-17 $4,559,110 Summer of 2020


Grant Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 471: Dartigo Creek & Creek Bridges
H.001842.6 - Asphalt new pavement-new roadway/new alignments
Proj. Engr: Pugh, David Route: LA 471 map
Contractor: Tl Hawk, LLC Miles: 0.66
Work Order Date Contract Amount Estimated Completion Date
2019-10-07 $3,699,131 Fall of 2020


LA 158: US 71 to Viney Ridge Rd
H.012916.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Pugh, David Route: LA 158 map
Contractor: Diamond B Construction Co., L. Miles: 3.82
Work Order Date Contract Amount Estimated Completion Date
2019-07-21 $2,353,348 Spring of 2020


Natchitoches Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 120: Bridges Near Provencal
H.001146.6 - New location/replacement of bridge
Proj. Engr: Pugh, David Route: LA 120 map
Contractor: W. E. Mcdonald & Son, LLC. Miles: 7.48
Work Order Date Contract Amount Estimated Completion Date
2018-01-03 $5,579,766 End of 2019


LA 8 to La 6 (I-49 Signing)
H.003476.6 - Signing
Proj. Engr: Bruce, Richard (Pete) Route: I-49 map
Contractor: Acacia Industries, LLC Miles: 35.24
Work Order Date Contract Amount Estimated Completion Date
2015-08-12 $1,138,285 Fall of 2017


LA 153: Jct La 9 - Five Forks Road
H.010357.6 - Asph concrete ovly over in place stabilized/cement treated base course
Proj. Engr: Pugh, David Route: LA 153 map
Contractor: Madden Contracting Co., LLC Miles: 3.46
Work Order Date Contract Amount Estimated Completion Date
2019-10-21 $2,887,958 Spring of 2020


I-49: Cable Barriers Natchitoches
H.012196.6 - Crash devices
Proj. Engr: Pugh, David Route: I-49 map
Contractor: Progressive Construction Co., Miles: 50.70
Work Order Date Contract Amount Estimated Completion Date
2018-10-13 $5,696,762 Beginning of 2020


LA 1-X: Four Lane to Three Lane Section
H.012399.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Pugh, David Route: LA 1-X map
Contractor: Madden Contracting Co., LLC Miles: 1.36
Work Order Date Contract Amount Estimated Completion Date
2018-02-21 $780,138 Summer of 2018


LA 1226 & La 1227: US 84 - Placid Oil Rd
H.012920.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Pugh, David Route: LA 1226 LA 1227 map
Contractor: Madden Contracting Co., LLC Miles: 6.24
Work Order Date Contract Amount Estimated Completion Date
2019-08-08 $3,314,350 Summer of 2020


I-49: Pavement Marking Replacement Iv
H.013152.6 - Striping and pavement markers
Proj. Engr: Pugh, David Route: I-49 map
Contractor: Highway Graphics LLC Miles: 20.27
Work Order Date Contract Amount Estimated Completion Date
2018-07-18 $780,944 Fall of 2018


Rapides Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

Jackson (La 1208-3) @ Horseshoe Roundabout
H.002672.6 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Buskie, Steve Route: LA 1208-3 LA 488 map
Contractor: Merrick, LLC Miles: 0.41
Work Order Date Contract Amount Estimated Completion Date
2018-12-14 $1,856,921 Spring of 2020


Alexandria ITS Phase 3
H.011505.6 - ITS and emergency operations
Proj. Engr: Buskie, Steve Route: US 71 map
Contractor: Ernest P. Breaux Electrical, L Miles: 9.54
Work Order Date Contract Amount Estimated Completion Date
2019-08-02 $1,901,943 Beginning of 2021


LA 3225: Turn Lanes at La 623
H.011660.6 - Traffic flow improvements - formerly turn lanes
Proj. Engr: Pugh, David Route: LA 3225 map
Contractor: T.L. Construction LLC Miles: 0.28
Work Order Date Contract Amount Estimated Completion Date
2018-10-03 $1,300,737 Summer of 2019


LA 1, La158 & US 71 Sign Truss & Cantilever
H.012015.6 - Signing
Proj. Engr: Pugh, David Route: US 71 map
Contractor: Alpha Service and Products, In Miles: 0.05
Work Order Date Contract Amount Estimated Completion Date
2018-10-09 $615,466 Summer of 2019


I-49: Cable Barriers Avoyelles & Rapides
H.012195.6 - Crash devices
Proj. Engr: Buskie, Steve Route: I-49 map
Contractor: Womack and Sons Constr. Group Miles: 63.28
Work Order Date Contract Amount Estimated Completion Date
2018-08-31 $6,935,452 Summer of 2020


Concrete Patching Rapides Parish
H.012963.6 - Concrete pavement rehab-grinding/dowell retrofit/should drain install
Proj. Engr: Buskie, Steve Route: US 71 US 167 map
Contractor: Progressive Construction Co., Miles: 6.65
Work Order Date Contract Amount Estimated Completion Date
2019-06-09 $1,519,890 Spring of 2020


I-49: Pavement Marking Replacement Vii
H.013568.6 - Striping and pavement markers
Proj. Engr: Buskie, Steve Route: I-49 map
Contractor: Highway Graphics LLC Miles: 25.08
Work Order Date Contract Amount Estimated Completion Date
2019-06-12 $452,703 End of 2019


LA 28 Signal Performance Measures
H.013878.6 - Signalization
Proj. Engr: Buskie, Steve Route: LA 28 map
Contractor: Jack B. Harper Electrical LLC Miles: 3.84
Work Order Date Contract Amount Estimated Completion Date
2019-09-19 $207,110 Spring of 2020


Sabine Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 175: 300' S of Shirwillis Dr - La 120
H.010366.6 - Asph concrete ovly over in place stabilized/cement treated base course
Proj. Engr: Duffey, Randall Route: LA 175 map
Contractor: Madden Contracting Co., LLC Miles: 5.52
Work Order Date Contract Amount Estimated Completion Date
2019-08-30 $4,061,592 Summer of 2020


Vernon Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 121: La 28 - Rapides Pl
H.011588.6-R1 - Asphalt overlay of asphalt pavement
Proj. Engr: Duffey, Randall Route: LA 121 map
Contractor: Prairie Contractors LLC Miles: 13.98
Work Order Date Contract Amount Estimated Completion Date
2019-04-22 $5,844,343 Spring of 2020


District 08

No districtwide projects.