Huey P. Long Bridge
Wednesday, February 06, 2013 at 9:17:00 AM
Week of Monday 04 February 2013 through Sunday 10 February 2013 Huey P. Long Bridge
Main Bridge
Complete Closure Westbound 10:00 P.M. to 1:30 A.M. and Eastbound 1:30 A.M. to 5:00 A.M. (7 hours each night) from Monday 04 February 2013 through Saturday 09 February 2013 at 5:00 A.M. Staging of bridge deck construction and painting materials and equipment. Emergency vehicles will be allowed through.
Bridge City Avenue/Seven Oaks at US 90 Eastbound
Alternating lane closures at the new overpass 9:00 A.M. to 2:00 P.M. (5 hours daily) from Monday 04 February 2013 through Friday 08 February 2013 at 2:00 P.M. Removing overhang and diaphragm forms from the new eastbound overpass.
Eastbank River Road and Levee under the HPL
Closure to through traffic under the bridge 7:00 P.M. to 5:00 A.M. (10 hours daily) Monday 04 February 2013 through Saturday Morning 09 February 2013 at 5:00 A.M. The road will be closed to through traffic but businesses can access from each direction. The reason for the closure is the installation of preformed metal decking over the road and levee. Emergency vehicles will be allowed through.
Jefferson Highway East and Westbound
Alternating lane closures 9:00 A.M. to 3:00 P.M. Monday 04 February 2013through Friday 08 February 2013. Jefferson Highway paving work, manhole adjustments, and final striping. Single lane closures may remain in place overnight to allow for concrete cure time. All businesses and private accesses will remain open and unrestricted.
Clearview Parkway North and Southbound Left Lanes from Mounes to East Corporate
Left lane closure Clearview North and Southbound 9:00 A.M. to 3:00 P.M. Monday 04 February 2013 through Friday 08 February 2013 at 3:00 P.M. At 3:00 P.M. daily the left lane on southbound Clearview will be reopened, note that the left turn access from Clearview to the Vision Center Shopping Strip WILL be open. Trucks and equipment will be in the closed lanes travelers should be alert when traveling on Clearview. This activity will continue until Mid-March. The work involves be removal of the existing waterline and installation of a new 12-nch water main.
Week of Monday 11 February 2013 through Sunday 17 February 2013
Main Bridge
Complete Closure Westbound 10:00 P.M. to 1:30 A.M. and Eastbound 1:30 A.M. to 5:00 A.M. (7 hours each night) from Wednesday 13 February 2013 through Friday 15 February 2013 at 5:00 A.M. Staging of bridge painting materials. Emergency Vehicles will be allowed through.
Complete Eastbound Closure 12:00 A.M. until 2:00 P.M. (14 hours) on Saturday 16 February 2013. AT 2:00 P.M. the right lane eastbound will be reopened to vehicular traffic and light trucks until 2:00 P.M. on Sunday the 17th. At 2:00 on Sunday the 17th both lanes on the eastbound bridge will be reopened to all traffic. The purpose of the closure is to place concrete on the East Bank Eastbound Approach. This is the first of three scheduled concrete placements on the eastbank eastbound approach. The westbound bridge will remain completely open. Emergency vechicles will be allowed through if needed.
If weather causes cancellation of the Saturday placement, weather permitting the eastbound full closure will be rescheduled for 12:00 A. M. until 2:00 P.M. on Sunday 17 February 2013. At 2:00 P.M. the right lane eastbound will be reopened to vehicular traffic and light trucks until 5:00 A.M. on Monday the 18th at which time the both lanes on the eastbound approach will be reopened to all traffic.
Eastbank River Road and levee under the HPL bridge
Complete closure to through traffic from 12:00 A.M. until 10:00 A.M.. (10). Businesses can be accessed from each direction on river road. Reason for the closure is placement of concrete overhead on the eastbound HPL. Emergency vehicles will be allowed through.
If weather causes cancellation of the Saturday placement, weather permitting the River Road and levee closure to through vehicular and pedestrian traffic will be rescheduled for 12:00 A. M. until 10:00 A.M. on Sunday 17 February 2013.
Jefferson Highway East and Westbound
Alternating lane closures 9:00 A.M. to 3:00 P.M. Monday 11 February 2013. Jefferson Highway paving work, manhole adjustments. All businesses and private accesses will remain open and unrestricted.

Alternating lane closures 9:00 A.M. to 3:00 P.M. Wednesday 13 February 2013 through Friday 15 February 2013 at 3:00 P.M. Jefferson Highway paving work, manhole adjustments. All businesses and private accesses will remain open and unrestricted.
Clearview Parkway
Left lane closure Southbound 9:00 A.M. to 3:00 P.M. Monday 11 February 2013. Work on the new waterline between East Corporate Blvd and Mounes. The left turn to the Vision Center near East Corporate will be open.
Left lane Closure Southbound 9:00 A.M. to 3:00 P.M. Wednesday 13 February 2013 through Friday 15 February 2013 at 3:00 P.M. Work on the new waterline between East Corporate Blvd and Mounes. The left turn to the Vision Center near East Corporate will be open.
Please note that the northbound left lane on Clearview from East Corporate Blvd to Mounes will remain closed until mid-march in order to install the new waterline and build an additional left turn lane to Mounes. The left turn to Mounes has been move one lane over from where it is now.
Please note that the northbound left lane on Clearview from East Corporate Blvd to Mounes will remain closed until mid-march in order to install the new waterline and build an additional left turn lane to Mounes. The left turn to Mounes has been move one lane over from where it is now.