Huey P. Long , Orleans & Jefferson Parish, Traffic Notice
Tuesday, January 29, 2013 at 9:00:00 AM
Main Bridge


Complete Closure Eastbound 10:00 P.M. to 1:30 A.M. and Westbound 1:30 A.M. to 5:00 A.M. (7 hours each night) from Tuesday 29 January 2013 through Saturday 02 February 2013 at 5:00 A.M. Staging of bridge deck construction and painting materials and equipment. Emergency vehicles will be allowed through.

Bridge City Avenue/Seven Oaks at US 90 Eastbound


Alternating lane closures at the new overpass 9:00 A.M. to 2:00 P.M. (5 hours daily) from Tuesday 29 January 2013 through Friday 01 February 2013 at 2:00 P.M. Removing overhang forms from the new eastbound overpass.

Westbank River Road (LA 541) under the HPL


Closure to through traffic 9:00 A.M. to 2:00 P.M. Tuesday 29 January 2013 through Friday 01 February 2013. Installing and removing painter access over LA 541. A detour will be clearly marked and emergency vehicles will be allowed through.

Clearview Parkway North and Southbound Left Lanes from Mounes to East Corporate


Alternating left lane closures adjacent to the existing median 7:00 P.M. to 5:00 A.M. Tuesday 29 January 2013 Wednesday Morning 30 January 2013 at 5:00 A.M. Demolition of light posts and foundations and installation of new waterline and valves.

Left lane closure Clearview North and Southbound 9:00 A.M. to 3:00 P.M. Tuesday 29 January 2013 through Friday 01 February 2013 at 3:00 P.M. At 3:00 P.M. daily the left lane on southbound Clearview will be reopened, note that the left turn access from Clearview to the Vision Center Shopping Strip WILL be open. Trucks and equipment will be in the closed lanes travelers should be alert when traveling on Clearview. This activity will continue until Mid-March. The work involves be removal of the existing waterline and installation of a new 12-nch water main.

Eastbank River Road and Levee under the HPL


Closure to through traffic under the bridge 7:00 P.M. to 5:00 A.M. (10 hours daily) Tuesday 29 January 2013 through Saturday Morning 02 February 2013 at 5:00 A.M. The road will be closed to through traffic but businesses can access from each direction. The reason for the closure is the installation of preformed metal decking over the road and levee. Emergency vehicles will be allowed through.

Jefferson Highway East and Westbound


Alternating lane closures 9:00 A.M. to 3:00 P.M. Monday 28 January 2013 through Friday 01 February 2013. Jefferson Highway paving work, manhole adjustments.


Week of 04 February 2013 through Sunday 10 February 2013

 

Main Bridge

Complete Closure Eastbound 10:00 P.M. to 1:30 A.M. and Westbound 1:30 A.M. to 5:00 A.M. (7 hours each night) from Monday 04 February 2013 through Saturday 09 February 2013 at 5:00 A.M. Staging of bridge deck construction and painting materials and equipment.  Emergency vehicles will be allowed through.

 

Bridge City Avenue/Seven Oaks at US 90 Eastbound

Alternating lane closures at the new overpass 9:00 A.M. to 2:00 P.M. (5 hours daily) from Monday 04 February 2013 through Friday 08 February 2013 at 2:00 P.M.    Removing overhang forms from the new eastbound overpass.

 

Eastbank River Road and Levee under the HPL

Closure to through traffic under the bridge 7:00 P.M. to 5:00 A.M. (10 hours daily) Monday 04 February 2013 through Saturday Morning 09 February 2013 at 5:00 A.M. The road will be closed to through traffic but businesses can access from each direction.  The reason for the closure is the installation of preformed metal decking over the road and levee.  Emergency vehicles will be allowed through.

 

Jefferson Highway East and Westbound

Alternating lane closures 9:00 A.M. to 3:00 P.M. Monday 04 February 2013through Friday 08 February 2013.  Jefferson Highway paving work, manhole adjustments, and final striping.

 

Clearview Parkway North and Southbound Left Lanes from Mounes to East Corporate

Left lane closure Clearview North and Southbound 9:00 A.M. to 3:00 P.M. Monday 04 February 2013 through Friday 08 February 2013 at 3:00 P.M.  At 3:00 P.M. daily the left lane on southbound Clearview will be reopened, note that the left turn access from Clearview to the Vision Center Shopping Strip WILL be open.  Trucks and equipment will be in the closed lanes travelers should be alert when traveling on Clearview.  This activity will continue until Mid-March.  The work involves be removal of the existing waterline and installation of a new 12-inch water main.