LA 174, I-49-Red River Parish Line, Natchitoches Parish
Monday, January 28, 2013 at 10:38:00 AM
The LA DOTD Engineer, David Pugh, advises the public that, weather permitting, work will begin during the week of February 4, 2013 on LA 174 in an eastward direction to the Red River Parish Line. The scope of work includes pavement patching, cold planing, saw cutting, surface preparation, 2” superpave asphaltic concrete overlay, aggregate surface course for shoulders and pavement striping.

The project was awarded to the low bidder, Gilchrist Construction CO. LLC, (Alexandria, LA) in the amount of $354,871.22.

Permit/Detour section
Thru traffic will be maintained at all times but there will be periodic lane closures and minor delays associated with this work.

Safety Reminder
DOTD appreciates your patience and reminds you to please drive with caution through the construction site and be on the lookout for work crews and their equipment.