Huey P. Long Bridge, Jefferson Parish, Traffic Notice
Wednesday, January 09, 2013 at 2:44:00 PM
Week of Monday 14 January 2013 through Sunday 20 January 2013

Main Bridge
Westbound Closure 10:00 P.M. to 1:30 A.M. and Eastbound 1:30 A.M. to 5:00 A.M. (7 hours each night) Monday 14 January 2013, Wednesday 16 January 2013 and Friday 18 January 2013 (no scheduled closure on Tuesday the 15th and Thursday the 17th). The reason of the closure is staging of materials for bridge painting and deck installation. Emergency vehicles will be allowed through.
Eastbank River Road and Levee under the HPL
Complete closure 7:00 A.M. through 5:00 A.M. (10 hours nightly) Sunday 13 January 2013 through Tuesday 15 January 2013 at 5:00 A.M. .). Businesses can be accessed from each direction and Emergency vehicles will be allowed through. The reason for the closure is painting of the steel bridge girders above the road and levee and installation of preformed metal decking over the roadway. Police will be on site to assist.
Complete closure 7:00 A.M. through 5:00 A.M. (10 hours nightly) Friday 18 January 2013 through Monday 21 January 2013 at 5:00 A.M. Businesses can be accessed from each direction and Emergency vehicles will be allowed through. The reason for the closure is painting of the steel bridge girders above the road and levee and installation of preformed metal decking over the roadway. Police will be on site to assist.

Clearview Parkway from East Corporate Blvd to Mounes
Alternating lane closure north and southbound 9:00 A.M. to 3:00 P.M. and again from 7:00 P.M. to 5:00 A.M. daily, Monday 14 January 2013 through Saturday 19 January 2013 at 5:00 A.M. The purpose of the work is to install waterline, new fire hydrants, water service taps, and begin demolition to construct new waterline and median. Demolition work will be done in the evening from 7:00 P.M. to 5:00 A.M. Two lanes on Clearview in either direction will always be open.
Alternating lane closure right lane north and southbound 7:00 A.M. to 5:00 P.M. and again from 7:00 P.M. to 5:00 A.M. Saturday 19 January 2013 through Sunday 20 January 2013 at 5:00 A.M. Continuing to install waterline and new fire hydrants and water service taps and demolition activity and waterline testing in the evening closures. Two lanes on Clearview in each direction will always be open.

Jefferson Highway East and Westbound
Alternating lane Closures east and west bound 9:00 A.M. to 3:00 P.M. (6 hours daily) from Monday14 January 2013 through Friday 18 January 2013 at 3:00 P.M. Completing paving work and manhole adjustments on Jefferson Highway.
Alternating lane Closures east and west bound 7:00 A.M. to 5:00 P.M. Saturday 19 January. Completing paving work and manhole adjustments on Jefferson Highway.