US 61/US 190 (River Road), East Baton Rouge Parish
Tuesday, April 21, 2015 at 1:44:45 PM
US 61/190 (River Road) will continue to be reduced to 2 lanes of traffic from the intersection with North St to the intersection with State Capitol Drive from Tuesday, April 20 through Monday, May 4. One lane of traffic in each direction will be maintained through the closure.

Lane closures in this area are anticipated to last through the end of May, 2015, and this notification will be updated as necessary.

This closure will allow vehicles 11-feet wide or less to pass through the construction zone.

This closure is for sewer improvement construction.

DOTD appreciates your patience and reminds you to please drive with caution through the construction site and be on the lookout for work crews and their equipment.

If any questions, you may contact Clyde Pendergrass, JB James, Construction, at (225) 315-1018.