I-10 & I-49 - Acadia, Jefferson Davis, St. Landry, & Evangeline Parish
Thursday, November 29, 2012 at 11:15:00 AM
Beginning Monday, December 3, 2012, there will be shoulder work on I-10 in both the eastbound and westbound directions from Mile Post 80 (Crowley-Eunice highway LA 13) to Mile Post 67 (3 miles west of Elton Rd. LA 26).

Also beginning Monday, December 3, 2012, there will be shoulder work on I-49 in both the northbound and southbound directions from Mile Post 26 (I-49 Rest Area) to Mile Post 45 (1 mile South of LA 106).

The work consists of the installation of milepost signs and will take place between the hours of 7:00 a.m. and 5:00 p.m. This work should be completed in three weeks – weather permitting.

There are no vehicle restrictions. Emergency vehicles have access to the area. No detour is necessary for this work.

DOTD appreciates your patience and reminds you to please drive with caution through the construction site and be on the lookout for work crews and their equipment.