Perkins Road Widening Project Lane closure update
Wednesday, June 02, 2010 at 9:18:03 AM

LA 427 (Perkins Rd) in Baton Rouge from Bawell St. to Essen Lane – there will be a moving single lane closure starting Sunday, June 6, from 8 P.M. to Monday, June 14, at 5 A.M. while striping crews replace the all of the permanent striping on this entire 3.6 mile segment of Perkins Rd.  This work will be ongoing until June 14th. The work schedule will be Sunday through Thursday nights from 8 P.M. to 5 A.M. nightly.  No work will occur Friday or Saturday nights.

 

This closure will allow vehicles 12 feet wide or smaller to pass through the construction zone.  Road is open for regular traffic but oversize vehicles must detour using I-10 east bound or west bound.

 

DOTD appreciates your patience and reminds you to please drive with caution through the construction zone and be on the lookout for work crews and their equipment.