I-10 Widening Project lane closure update
Friday, September 11, 2009 at 2:40:03 PM

Sunday, Sept. 13, to Wednesday, Sept. 16, each night from 9 p.m. to 5 a.m., I-10 eastbound will be reduced to one lane of traffic from Siegen Lane to Pecue while crews remove concrete from the area.

Sunday, Sept. 13, to Wednesday, Sept. 16, each night from 9 p.m. to 5 a.m., I-10 westbound will be reduced to one lane of traffic from Bluebonnet to the I-10/I-12 split while crews complete embankment work.

Monday, Sept. 14, to Thursday, Sept. 17, from 7 p.m. to 5 a.m. each night, the right through travel lane of Essen Lane northbound will be closed between the I-10 overpass and the I-12 overpass while crews install drilled shafts that will be used for the foundation of the new bridge.

Motorists should use caution while traveling through the construction zone. The closures are subject to cancellation due to inclement weather.