U.S. 190 (Florida Blvd) Resurfacing Project between U.S. 61 and La. 37 Project Update
Thursday, June 27, 2013 at 11:25:40 AM

The project is moving ahead steadily. The remaining asphalt overlay operations include westbound shoulders and turnouts, inside left turn-lanes and ramp shoulders to/from Airline Hwy.  Other remaining work includes completing median curb sealing remaining roadway joints, relocating light poles, installing shoulder rumble strips, and installing permanent striping.  All work is scheduled to be complete by the end of July 2013. 

 

This lane closure is subject to change depending on adverse weather conditions.

DOTD appreciates your patience and reminds you to please drive with caution through the construction site and be on the lookout for work crews and their equipment.