US 61 Resurfacing and Safety Improvements From LA 22 to LA 74 Project Update
Thursday, January 03, 2013 at 3:38:46 PM

Good afternoon, this is a brief update on the US 61 Resurfacing and Safety Improvements From LA 22 to LA 74.

 

Completed: Our crews have completed all roadway resurfacing and ground-in rumble strips

 

Current Work: The crews are grinding out the deficient areas of roadway and installing concrete pavement in median areas, guard rail asphalt pads and guard rails. A few side road turnouts remain to be paved.

 

Remaining Work: Final dressing and clean up throughout the project limits and reinstallation of street lights.

 

This project is still expected to be finished by Late January-early February.

 