**UPDATE**
Roundabout: US 171 at Boone St
Route US 171
S.P. H.011909
Vernon Parish

The Louisiana Department of Transportation and Development (DOTD) announces that, weather permitting, a new phase of work will begin on the US 171 roundabout at Boone St. on Friday, September 20th, 2024 at 7:00 am. Two-way traffic will be permitted along Boone Street, and the one-way detour roads on Boone St. will be closed. The U-turn on south bound US 171, 1,500 feet south of the LA 1211 intersection, will be open. The median left turn lane on north bound US 171 at Stanton Road will be open. All other current lane closures will remain closed during this phase of construction. This phase of construction will allow for the completion of the remaining class II base course, lime treatment, concrete paving, drainage, instillation of driveways, and related work. This phase of the project will continue for approximately three (3) months.

Permit/Detour section

Beginning Friday, September 20th, 2024, Boone St. will be converted into a temporary signalized T-intersection at US 171. Two lane traffic will be permitted on Boone St.

One-way detour roads on Boone St. will be closed.

US 171 southbound traffic will continue to be diverted to the northbound lanes beginning approximately 800 feet south of Franklin St.

Beginning near Stanton St., US 171 northbound traffic will continue to be reduced to one through lane and a dedicated left turn lane for the WalMart drive and surrounding businesses.

The roadway will remain open to local and through traffic with no restrictions for passenger vehicles and a 10’ wide lane width restriction for all oversize vehicles.





May 28, 2024


**UPDATE**
Roundabout: US 171 at Boone St
Route US 171
S.P. H.011909
Vernon Parish

The Louisiana Department of Transportation and Development (DOTD) announces that, weather permitting, beginning Monday, June 3, 2024 US 171 will be reduced to one-lane in each direction beginning approximately 800 feet south of Franklin St to near Stanton St. The contractor will divert US 171 traffic to the existing northbound lanes and begin utilization of the temporary detour roads and temporary signalized intersection at Boone St. This phase of the project is expected to be completed in three (3) months.

Permit/Detour section

Beginning Monday, June 3, 2024, US 171 southbound traffic will be diverted to the northbound lanes beginning approximately 800 feet south of Franklin St.

Beginning near Stanton St, US 171 northbound traffic will be reduced to one through lane and a dedicated left turn lane for the WalMart drive and surrounding businesses.

The existing traffic signals at Boone St, WalMart drive, and Redtown Rd will be replaced with temporary traffic signals during this phase of the project.

One-way detour roads will provide access to Boone St from US 171.

The roadway will remain open to local and through traffic with no restrictions for passenger vehicles and a 10’ wide lane width restriction for all oversize vehicles.




September 28, 2023

Roundabout: US 171 at Boone St
Route US 171
S.P. H.011909
Vernon Parish

The Louisiana Department of Transportation and Development (DOTD) announces that, weather permitting, work will begin on the US 171 roundabout at Boone St project on Monday, October 9, 2023. This roundabout and corridor improvement project is located on US 171, beginning approximately 1,500 feet south of the LA 1211 intersection and ending approximately 2,000 feet north of the Boone St intersection. This 1.387-mile long project will receive clearing and grubbing, grading, drainage structures, class II base course, lime treatment, asphalt concrete pavement, portland cement concrete pavement, and related work.

The project was awarded to the lowest bidder, Apeck Construction, LLC, in the amount of $9,770,606.43.

Permit/Detour section
On Monday, October 9, 2023, the contractor will begin Phase I of the project beginning with the construction of a new J-turn approximately 1,500 feet south of the US 171 and LA 1211 intersection. At this time, the existing roadway will be reduced from 12 foot to 11 foot travel lanes in this area, but all lanes of the roadway will remain open to all local and through traffic with no restrictions. As the project progresses, updates will be provided for changes impacting traffic such as lane closures or restrictions.

Safety reminder
DOTD appreciates your patience and reminds you to please drive with caution and be on the lookout for work crews and their equipment.

Additional Information
Call (318) 561-5100 or (800) 542-3509 or 511 or visit www.511LA.org for additional information. Motorists may also monitor the LA DOTD website @ www.dotd.la.gov, by selecting MYDOTD, the Way to Geaux Application for iPhone or Android devices, the DOTD Facebook page or the LA DOTD Twitter page, @AlexTraffic for further information and details.

Project Contact
Mr. Randall Duffey, P.E.
Sabine and Vernon Parishes Project Engineer
Office: (337) 238-6406
Email: randall.duffey@la.gov

Media Contact
Mrs. Erin Buchanan Mills
Public Information Officer 3
District 08: Avoyelles, Grant, Natchitoches, Rapides, Sabine, Vernon, and Winn Parishes
Phone: (318) 549-8402
Email: erin.buchanan@la.gov