La. 64 Magnolia Bridge Replacement Project Update
Friday, October 05, 2012 at 2:13:46 PM

La. 64 Magnolia Bridge Replacement Project Update

October 5, 2012

Current

Crews are currently working on the concrete roadway on the west end of bridge, guard rails, spur dike, and dressing up the fore slopes. The spur dike is a permanent earthen structure (similar to a levee) that protects the end of the bridge from erosion and scour during flood events.   Crews plan to install temporary striping on Monday, October 8, 2012. 

Completed

Crews recently completed asphalt work on roadway on the east side of bridge. 

Traffic

Additional lanes will be opened on the newly constructed pavement.  Lanes on the uncompleted west end roadway will remain closed.

 For questions or comments, contact DOTD’s Customer Service Center at 1-877-4LA-DOTD (1-877-452-3683) or e-mail dotdcs@la.gov. The center is open 7:30 a.m. – 5 p.m., Monday through Friday. You can also visit the project’s Web page by going to www.dotd.gov and clicking on "Projects" from the Programs & Projects section of the main menu on the left-hand side of the page and selecting the LA 64 Magnolia Bridge Replacement Project link.

 You can also follow the La. 64 Magnolia Bridge Replacement Project on Facebook.

 Again, we thank you for your feedback and patience during this construction. Additionally, at your convenience, please let us know how we are doing by filling out our Customer Service Survey.

 

State Project Number: 262-31-0016

Start date: October 2010

Finish date: Fall 2012

Cost: $19.9 Million

Contractor: L & A Contracting Co. of Hattiesburg, MS