Interstate 10 Calcasieu River Bridge Maintenance Project Update
Thursday, May 31, 2012 at 1:19:05 PM

Interstate 10 Calcasieu River Bridge Maintenance Project
5-30-12

Construction:
Remaining items on the I-10 Calcasieu River Bridge Maintenance project include handrail repairs, deck patching, joint work, and bolt replacements and repairs.

Traffic:
A number of lane closures are expected to occur during nighttime and off-peak daytime hours until mid-August.  The closures will be needed to facilitate the replacement of handrail bolts, repairing handrail posts, and accessing areas underneath the decking to perform additional structural steel repairs. The project is expected to be complete by late September.

All above-mentioned work schedules are subject to change in the event of adverse weather. Please see public notices for exact times, dates and cancellations.

For additional questions or comments, contact DOTD’s Customer Service Center at 1-877-4LA-DOTD (1-877-452-3683) or e-mail dotdcs@la.gov. The center is open 7:30 a.m. - 5 p.m. Monday through Friday. You can also visit the project’s Web page by going to www.dotd.la.gov and clicking on “Projects” from the Programs & Projects section of the main menu on the left-hand side of the page and selecting the “I-10 Calcasieu River Bridge” link.

If you are a member of a homeowners association and would like a DOTD speaker to attend one of your meetings to share information about this project, please let me know. Also, feel free to forward this e-mail on to anyone you think would like to receive this information.

Additionally, at your convenience, please let us know how we are doing by filling out our customer service survey below. Again, we thank you for your feedback and patience during this construction.

State Project No. ................................................................................... 450-91-0178
Parish............................................................................................... Calcasieu Parish
Contractor......................................................................................... Topcor Services
Contract Time............................................................................... 244 Calendar Days
Contract Amount................................................................................... 6,828,313.81
Project Start Date....................................................................................... June 2011
Anticipated Completion Date............................................................ September 2012

DOTD never shares, sells or discloses any e-mail addresses of anyone who signs up for our project update. Please let us know how we may better serve you: Customer Service Survey