LA 10 from LA 68 Project Update
Wednesday, April 11, 2012 at 12:02:43 PM

Current work: The contractor is completing the asphalt this week.  After completion, any final adjustments will be made as the work site is cleaned, and then striping will begin. The expected finish date is June 30.

For questions or comments, contact DOTD’s Customer Service Center at 1-877-4LA-DOTD (1-877-452-3683) or e-mail customerservice@dotd.la.gov. The center is open 7:30 a.m. – 5 p.m., Monday through Friday. You can also visit the project’s Web page by going to www.dotd.gov and clicking on "Projects" from the Programs & Projects section of the main menu on the left-hand side of the page and selecting the I-12 Widening St. Tammany Parish Project link.

You can also follow the I-12 Widening St. Tammany Parish Project on Facebook.

Again, we thank you for your feedback and patience during this construction. Additionally, at your convenience, please let us know how we are doing by filling out our Customer Service Survey.