DOTD and Iberia Parish Government announce partial opening of La. 3212 roundabout
Wednesday, May 04, 2022 at 9:01:44 AM

UPDATE: The partial opening of the La. 3212 roundabout is now scheduled for Wednesday, May 4, at 12 p.m.


UPDATE: The partial opening of the La. 3212 roundabout is now scheduled for Monday, May 9, at 12 p.m.


IBERIA PARISH, La
. - The Louisiana Department of Transportation and Development, in conjunction with Iberia Parish Government, announced today that on Monday, April 25, at 12 p.m., the roundabout at the intersection of La. 3212 and Grand Prairie Road will be partially open to traffic.

Traffic will have access to three of the five legs of this roundabout (La. 3212 West, La. 3212 East and Grand Prairie Road).

Construction will continue on the north leg of the roundabout and on ARA Access Road south of the roundabout.

All signage for the previously installed detour routes will be removed. The diversion road along La. 3212 will be closed and removed.

Emergency vehicles will have access to the area, and there are no anticipated lane restrictions.

This project is estimated for completion in summer 2022.