I-12 Widening St. Tammany Parish Project Update
September 7, 2011
Current work: The contractor is currently building up the median to construct the concrete median barrier throughout the full length of the project. The approach slabs for Bayou Vincent Bridge are being extended and the barrier wall poured. Also, the contractor is driving the last group of footing piles on the Hwy 11 Bridge and will continue to pour columns and caps.
For questions or comments, contact DOTD’s Customer Service Center at 1-877-4LA-DOTD (1-877-452-3683) or e-mail customerservice@dotd.la.gov. The center is open 7:30 a.m. – 5 p.m., Monday through Friday. You can also visit the project’s Web page by going to www.dotd.gov and clicking on "Projects" from the Programs & Projects section of the main menu on the left-hand side of the page and selecting the I-12 Widening St. Tammany Parish Project link.
You can also follow the I-12 Widening St. Tammany Parish Project on Facebook.
Again, we thank you for your feedback and patience during this construction. Additionally, at your convenience, please let us know how we are doing by filling out our Customer Service Survey.
State Project Number: 454-04-0080
Start date: January 2011
Finish date: Summer 2012
Cost: $25.7 million
Contractor: James Construction LLC