US 90 Interchange at LA 85 update
Monday, April 18, 2011 at 10:51:07 AM

US 90 Interchange at LA 85

New Iberia

April 18, 2011

Project Update

 

Current Work:

 

The contractor has made great progress in 2011 on the US 90 Design Build project.  All mainline and new ramp paving is completed on the east side of LA 85.  Approximately, 95% of the paving on the west side of LA 85 was completed at the end of March.

 

Traffic will be diverted to the new paving in April.  This will allow us to begin removing the diversion and complete the frontage roads. 

 

Bridge crews have one deck left to pour.  While one crew works the west side of the bridge, another crew works the east side.  Crews should complete all deck pours this week.

 

For more information on this project visit our project website or the project Facebook page. To receive periodic e-mail updates on this project, or for any questions contact us by e-mail Customer Service or call 1-877-4LA-DOTD (452-3683). The Customer Service Center is open Monday – Friday from 7:30 a.m. to 5 p.m.