Current work:
Crews are currently forming the south pier and forming and pouring the columns on the north pier. Other crews are continuing to build the new road base and approaches to the bridge.

Completed work:
Crews have removed the entire old bridge structure. The new drainage work located along La. 3087 (Prospect Street) and La. 24 (Main Street) is complete. The foundation piles for the north pier are completed. Around 28,000 cubic yards of embankment have been placed on La. 24 and La. 3087 to elevate the new roadway to meet the south bridge.

Each of the two piers sit on 61 concrete pilings that are 18-inches wide and 155 feet in length.  If the concrete piling were laid end-to-end, it would stretch 1.8 miles.  The total amount of pilings for the project would stretch a total of 4.5 miles.

For questions or comments, contact DOTD’s Customer Service Center at 1-877-4LA-DOTD (1-877-452-3683) or e-mail customerservice@dotd.la.gov. The center is open 7:30 a.m. – 5 p.m., Monday through Friday. You can also visit the project’s Web page by going to www.dotd.gov and clicking on "Projects" from the Programs & Projects section of the main menu on the left-hand side of the page and selecting the Prospect Bridge La. 3087 Houma Project link.

You can also follow the Prospect Bridge (La. 3087) Houma Project on Facebook.

Again, we thank you for your feedback and patience during this construction. Additionally, at your convenience, please let us know how we are doing by filling out our Customer Service Survey.

State Project Number: 065-91-0016
Project Description: The new bridge and widened intersections will help to relieve congestion on this heavily traveled bridge.
Parish: Terrebonne
Start Date: May 24, 2010
Finish Date: Spring 2012
Cost: $26.7 Million