The project engineer for the Grand Ecore Bridge Project is very pleased with the progress to date, and the contractor is on schedule.

Current work:
The stringers were adjusted to support the new decking, and crews are currently laying forms for the first four spans.

Completed work:
The westbound lane has been completed and is open for traffic. The eastbound lane has had the old concrete deck removed across the first four spans.

For questions or comments, contact DOTD’s Customer Service Center at 1-877-4LA-DOTD (1-877-452-3683) or e-mail customerservice@dotd.la.gov. The center is open 7:30 a.m. – 5 p.m., Monday through Friday. You can also visit the project’s Web page by going to www.dotd.gov and clicking on "Projects" from the Programs & Projects section of the main menu on the left-hand side of the page and selecting the Grand Ecore Bridge LA 6 / US 84 Project link.

You can also follow the Grand Ecore Bridge LA 6 / US 84 Project on Facebook.

Again, we thank you for your feedback and patience during this construction. Additionally, at your convenience, please let us know how we are doing by filling out our Customer Service Survey.

State Project Number: 034-06-0046
Start Date: Feb. 17, 2010
Finish Date: July 2011
Cost: $5,478,974.85
Contractor: Jensen Construction Company