EXTENDED!! I-10 EB from MM 108 (Bayou Teche) to MM 110 (Breaux Bridge), Lafayette Parish, Lane Closure
Monday, February 01, 2021 at 10:24:32 AM
UPDATE: The outside lane of I-10 eastbound from mile marker 108 (Bayou Teche) to mile marker 110 (Breaux Bridge) will also be closed as follows:

• Wednesday, February 3 at 8:00 p.m. until Thursday, February 4 at 6:00 a.m., weather permitting.

The outside lane of I-10 eastbound from mile marker 108 (Bayou Teche) to mile marker 110 (Breaux Bridge) will be closed as follows, weather permitting:

• Saturday, January 30 at 8:00 p.m. until Sunday, January 31 at 6:00 a.m.
• Sunday, January 31 at 8:00 p.m. until Monday, February 1 at 6:00 a.m.
• Monday, February 1 at 8:00 p.m. until Tuesday, February 2 at 6:00 a.m.
• Tuesday, February 2 at 8:00 p.m. until Wednesday, February 3 at 6:00 a.m.

These closures are necessary to allow crews to prepare the roadway for asphalt operations.

There will be no vehicle width restrictions associated with this lane closure.

Emergency vehicles will have access to the area but may encounter delays. No detour route is necessary.

The $124.7 million I-10 widening project will involve widening a 7.11-mile section from I-49 to Breaux Bridge (State Project Number H.003003). The project will include pavement replacement within the existing lanes and the construction of one additional lane in each direction along I-10 from I-49 to LA 328 (Breaux Bridge).

The project began in May 2017 and is estimated for completion in May 2021.