I-12, Livingston Parish, Lane Closure, S.P. H.011278
Friday, December 18, 2020 at 3:54:01 PM
I-12 Westbound and Eastbound will have partial road closures affecting the left lane with a scheduled start of December 20, 2020
and a scheduled end of December 23, 2020 (weather permitting). These closures will occur 8:00 pm - 5:00 am (Nightly, weather permitting). The Westbound location starts at LA 63 (Livingston) and ends at 1.3 Miles East Of Satsuma. The Eastbound location starts at 1.3 miles East of Satsuma and ends at LA 441 (Holden).
Comments:
These lane closure are to allow crews to install the concrete mowing strip, the cables and the end terminals for the new cable barrier system.
Detour:
Westbound I-12 motorists may take I-55 North to US 190 West to LA 447 South back to I-12 West.
Eastbound I-12 motorists may take LA 447 North to US 190 East to I-55 South back to I-12 East
Safety Reminder:
DOTD appreciates your patience and reminds you to please drive with caution through the construction site and be on the lookout for work crews and their equipment.
Darrick Berner
DOTD Project Engineer
District 62/Hammond
(225) 686-2689
Darrick.Berner@la.gov