I-12 - Partial Road Closure - Project #: H.011278 - Livingston Parish
Wednesday, September 16, 2020 at 4:09:37 PM

Road or Lane Status
Roadwork - Road Construction

I-12 - Partial Lane Closure - Project #: H.011278 - Livingston Parish


I-12- Partial - Project #: H.011278 - Livingston Parish

Closure Details:
I-12 will have a partial road closure affecting the left lane with a scheduled start of September 16, 2020 and a scheduled end of September 19, 2020. The closure will have intermittent travel through the area and at least one lane will be open at all times. This closure will occur Nightly (Weather Permitting). The location starts at 1.3 miles East of Satsuma and ends at LA 43 (Albany).

Comments:
These lane closures will allow crews to install concrete aprons for the future cable barrier system.

Detour:
Eastbound I-12 motorists may take LA 447 North to US 190 East to I-55 South back to I-12 East.

Restrictions:
8:00 pm - 5:00 am

Darrick Berner
DOTD Project Engineer
District 62/Hammond
(225) 686-2689
Darrick.Berner@la.gov
DOTD website: www.dotd.la.gov


Call 511 or visit www.511la.org for additional information. Out-of-state travelers may call 1-888-ROAD-511 (1-888-762-3511). Motorists may also monitor the LA DOTD website at www.dotd.la.gov, by selecting MyDOTD, or by visiting the DOTD Facebook and Twitter pages.

DOTD appreciates your patience and reminds you to please drive with caution through the work zone and be on the lookout for work crews and equipment.