I-310, St. Charles Parish, S.P. H.012617
Wednesday, April 01, 2020 at 6:58:59 AM

Southbound I-310, from LA 18 to LA 3127, in Luling – the left lane will be closed with one lane to remain open daily from 7:00 AM Saturday, April 4, 2020 through 7:00 PM Sunday, April 5, 2020; while crews sawcut for concrete patch work. All work associated with this lane closure is weather permitting.

This closure will allow oversized vehicles to pass through the construction zone along I-310 Southbound. I-310 Northbound will allow vehicles 16 feet wide or smaller to pass through the construction zone

The following Northbound and Southbound I-310 ramps in Luling will be closed for a short duration daily beginning 7:00 AM Saturday, April 4, 2020 through 7:00 PM Sunday, April 5, 2020; while crews sawcut for concrete patch work. All work associated with this lane closure is weather permitting.

- I-310 Southbound Exit 7 – LA 18 Hahnville and Luling
- I-310 Northbound Exit 7 – LA 18 Hahnville and Luling
- LA 18 – I-310 Northbound New Orleans
- LA 18 – I-310 Southbound Boutte

The Northbound and Southbound I-310 ramps will be closed to through traffic for short durations while work is being performed, detour details will be provided with signage.

DOTD appreciates your patience and reminds you to please drive with caution through the construction site and be on the lookout for work crews and their equipment.

Benny E. Herrington, III, P.E.
DOTD Project Engineer
District 02 Gang 212
13911 Frere Street
Luling, Louisiana 70070
Office: (504) 465-3474
Fax: (985) 331-0662
E-mail: Benny.herrington@la.gov
My DOTD: http://wwwapps.dotd.la.gov/administration/announcements/MyDOTD.aspx
Statewide Travel Information: http://www.511la.org/