US 61 Westbound & Eastbound from Transcontinental Dr. to Labarre Rd
Friday, December 20, 2013 at 2:07:00 PM
Westbound & Eastbound US 61 from Labarre Rd. to Transcontinental Dr., alternating single lane closures on Thursday, December 26th, 2013 thru Monday, December 30th, 2013; from 6 a.m. to 9 p.m.; while crews install thermoplastic striping, weather permitting. (Note: If traffic delays during daylight hours become extensive, more than 20 minutes to get thru the work zone, contractor will have to pull off the road until traffic clears.)


 

Westbound & Eastbound US 61 from Labarre Rd. to Transcontinental Dr., alternating double lane closures on Sunday, December 29th, 2013 Monday, December 30th, 2013; from 9 p.m. to 6 a.m and while crews install traffic signal loops, weather permitting.




DOTD appreciates your patience and reminds you to please drive with caution through the construction site and be on the lookout for work crews and their equipment.