US 61 Westbound & Eastbound from Transcontinental Dr. to Labarre Rd
Friday, December 13, 2013 at 10:03:00 AM

Westbound & Eastbound US 61 from Labarre Rd. to Transcontinental Dr., alternating single lane closures on Monday, December 16th, 2013 thru Friday, December 20th, 2013; from 6 a.m. to 9 p.m.; while crews grind bumps, saw and seal asphalt joints, stripe roadway, and install traffic signal loops. (Note: If traffic delays during daylight hours become extensive, contractor will have to pull off the road until traffic clears.)

 

Westbound & Eastbound US 61 from Labarre Rd. to Transcontinental Dr., alternating double lane closures on Monday, December 16th, 2013 thru Saturday, December 21st, 2013; from 9 p.m. to 6 a.m.; while crews grind bumps, saw and seal asphalt joints, stripe roadway, and install traffic signal loops.

 

DOTD appreciates your patience and reminds you to please drive with caution through the construction site and be on the lookout for work crews and their equipment.