CORRECTION: H.012082, Port Allen Bridge Interim Repairs, West Baton Rouge Parish
Friday, April 12, 2019 at 7:40:18 AM
Beginning on Friday, April 12th at 7 PM, and ending on Saturday, April 13th at 4 AM, there will be alternating lane closures on the Southbound Intracoastal Bridge. Steel plates with rubberized mats will be used as needed. These closures are needed for bridge joint repairs.

In addition, beginning on Saturday night, April 13th, at 7:00 PM, until Monday morning, April 15th, at 4:00 AM, alternating lane closures will continue on the Southbound Intercoastal bridge for joint repairs.

Then, beginning on Monday night, April 15th, and ending on Friday, April 19th, there will be continue to be alternating lane closures on the Southbound Intracoastal Bridge, from 7 PM until 4 AM for joint repairs.

Permit load restrictions will be up to 12 feet wide; anything over, please contact the Permit office.

DOTD appreciates your patience and reminds you to please drive with caution through construction sites, and be on the lookout for work crews and their equipment.

Chad Roubique
Project Engineer
District 61
225-342-7570