Belle Chasse Bridge & Tunnel Project: Lane Closure Notice
Monday, March 24, 2025 at 10:47:22 AM
Note: All lanes on the Belle Chasse Bridge are estimated to be open soon and tolling will begin shortly after. For more information, please visit www.GeauxPass.com, www.bellechassebridge.com/tolling, or email customerservice@bellechassebridge.com.

Upcoming GeauxPass registration events to be held at the Belle Chasse Auditorium:
· Monday, March 24, 12pm-6pm
· Wednesday, March 26, 9am-3pm

BELLE CHASSE, LA.
- The Belle Chasse Bridge and Tunnel Replacement Project announces the following scheduled construction activities and anticipated traffic impacts. As always, these anticipated impacts are weather permitting and subject to potential changes.

Evening/Overnight (5 p.m.- 5 a.m.)

Monday, 3/24
· Two-way traffic on LA 23 northbound across the new bridge from Dale Ave. to L St.

Tuesday, 3/25
· Two-way traffic on LA 23 northbound across the new bridge from Dale Ave. to L St.

Wednesday, 3/25
· Engineers Rd detour & LA 23 southbound lane closure from Burmaster to Engineers Rd.

Sunday, 3/30
· LA23 – 2-way traffic on LA23 southbound across the new bridge from Dale Ave to L St, close Burmaster intersection and southbound turning lane

Monday, 3/31
· LA23 – 2-way traffic on LA23 northbound across the new bridge from Dale Ave. to L St, close to Burmaster turning land and Barriere Rd. intersection.

To sign up for project updates, please visit bellechassebridge.com and provide your email address for notifications to go directly to your inbox as the new bridge construction continues. Interested parties can submit questions to the project team via email at info@bellechassebridge.com. You can also follow the project on Facebook @BelleChasseBridge and Twitter @Bridge_BC